Document of The World Bank FOR OFFICIAL USE ONLY Report No: 76378-AR RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF ADDITIONAL FINANCING FOR BUENOS AIRES INFRASTRUCTURE SUSTAINABLE INVESTMENT DEVELOPMENT PROJECT LOAN 7947-AR APPROVED ON July 27, 2010 TO THE PROVINCE OF BUENOS AIRES WITH THE GUARANTEE OF THE ARGENTINE REPUBLIC May 2, 2013 Sustainable Development Department Argentina, Paraguay and Uruguay Country Management Unit Latin America and Caribbean Region Regional Vice President: Hasan Tuluy Country Director: Penelope Brook Sector Manager: Wambui G. Gichuri Task Team Leader: Lilian Pena Pereira Weiss ARGENTINA – ADDITIONAL FINANCING FOR BUENOS AIRES INFRASTRUCTURE SUSTAINABLE INVESTMENT DEVELOPMENT PROJECT P088032 LOAN 7947-AR Restructuring Paper 1. The closing date for the Argentina Additional Financing for Buenos Aires Infrastructure Sustainable Investment Development Project – Phase 1 (APL1), Loan 7947-AR, P088032 will be extended from December 31, 2013 until May 30, 2015. The Project’s grace period will end 4 months after the new closing date, on September 30, 2015. 2. The Additional Financing in the amount of US$50 million, approved by the Board on July 27, 2010, aims at filling the financing gap in the parent Project caused by unforeseen cost increases and scaling up the parent Project to include additional works. Because of reasons outside of the Borrower’s control, the Additional Financing loan only became effective on February 17, 2012, 18 months after its approval by the Bank’s Board. Thanks to the Borrower’s proactive engagement, the Additional Financing loan has disbursed US$15.07 million (30%) in just one year since effectiveness. The Project implementation progress and the performance of the implementing agency have been rated satisfactory in the parent Project for several years (and continue to be satisfactory currently), the Project is not under suspension of disbursements, and the Project has no outstanding audit reports or audit reports not satisfactory to the Bank. 3. Currently, work contracts for a total amount of US$56.41 million are ongoing in the overall Project (parent Project and Additional Financing), of which US$41.21 will be financed by the Additional Financing loan. Two works contracts for an amount of US$10.26 million are in the final contracting phase (pending contract signature). Consequently, no additional procurements or activities will be commenced under this Project. However, the expected completion dates of two major civil works (Catonas II and III) to be financed by the Additional Financing will require until early 2015 to be finalized, and a 17-month extension of the current closing date (almost equivalent to the Additional Financing’s effectiveness delay) is required to complete these activities. 4. The proposed extension is necessary to allow the Borrower to complete the civil works and substantially achieve the indicator targets and the PDO. Please note that the Borrower has prepared an action plan to complete the Project by the new closing date and that the Project objectives continue to be achievable. 5. This will be the first extension of the Additional Financing (Loan 7947-AR). The original loan (7268-AR), which has been extended twice, will not be extended. 2