Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and non- 1.5 consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Com No. Cost Preference by Bank ments US$ million (yes/no) (Prior / Post) July 9, 2010 1 Summary of 32 2 To be Prior the ICB Determined (Works) 2 Summary of 10.2 6 To be Prior the ICB Determined (Goods) 3 Summary of 19.4 5 No Post the NCB (Works) 4 Summary of 0.28 1 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 3.5 3 Prior number of contracts that will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts July 9, 2010 that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2018-01-15 2019-04-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 Executing Agency(ies): Ministry of Water Irrigation and Electricity, WSS Program Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-77733-CW-DIR / Pending Pipe laying for Dire Dewa IDA / 60070 Post Direct Selection Direct 0.00 Implementati 2018-11-28 2018-12-03 2019-01-07 2019-05-07 town water supply project by on Dire Dewa town GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43004-GO-DIR / Supply of pipes and fittings Under for the remaining work of IDA / 60070 Prior Direct Selection Direct 0.00 Implementati 2018-01-12 2018-01-17 2018-02-24 2018-05-25 Dire Dewa City Water on Supply and Sanitation Project ET-MOWIE-43329-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-17 2018-06-16 copy machines and lap top Quotations Envelope on computers) for Gambella City Water Supply and Sewerage Service ET-MOWIE-43286-GO-RFQ / procurement of office equipment (printers, desk Pending top computers, scanners, Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-22 2018-05-03 2018-06-02 photo copy machines and lap Quotations Envelope on top computers)for Deghabur Town Water Supply and Sewerage Service ET-MOWIE-43289-GO-RFQ / procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-22 2018-05-03 2018-06-02 copy machines and lap top Quotations Envelope on computers) for Arbaminch Town Water Supply and Sewerage Service Page 1 ET-MOWIE-43291-GO-RFQ / procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-22 2018-05-03 2018-06-02 copy machines and lap top Quotations Envelope on computers) for Harar Town Water Supply and Sewerage Service ET-MOWIE-43294-GO-RFQ / procurement of office equipment(printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Bishoftu Town Water Supply and Sewerage Service ET-MOWIE-43297-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-17 2018-06-16 copy machines and lap top Quotations Envelope on computers) for Shashemane City Water Supply and Sewerage Service ET-MOWIE-43299-GO-RFQ / procurement of office equipment(printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-17 2018-06-16 copy machines and lap top Quotations Envelope on computers) for Jigjiga City Water Supply and Sewerage Service ET-MOWIE-43300-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Hawassa City Water Supply and Sewerage Service ET-MOWIE-43035-GO-RFQ / Procurement of IT equipment Pending (printers, desk top Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-04-14 2018-06-09 2018-07-09 computers, scanners, photo Quotations Envelope on copy machines and lap top computers) for Ministry PIU ET-MOWIE-43317-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-17 2018-06-16 copy machines and lap top Quotations Envelope on computers) for Assosa City Water Supply and Sewerage Service ET-MOWIE-43319-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Asella City Water Supply and Sewerage Service Page 2 ET-MOWIE-43322-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Sodo City Water Supply and Sewerage Service ET-MOWIE-43324-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Debre Berhan City Water Supply and Sewerage Service ET-MOWIE-43326-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Dessie City Water Supply and Sewerage Service ET-MOWIE-43328-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Gonder City Water Supply and Sewerage Service ET-MOWIE-43331-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Nekmte City Water Supply and Sewerage Service ET-MOWIE-43333-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Jimma City Water Supply and Sewerage Service ET-MOWIE-43303-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Adama City Water Supply and Sewerage Service ET-MOWIE-43304-GO-RFQ / Procurement of office equipment (printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Mekelle City Water Supply and Sewerage Service Page 3 ET-MOWIE-43307-GO-RFQ / Procurement of office equipment(printers, desk top Pending computers, scanners, photo Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope on computers) for Bahir Dar City Water Supply and Sewerage Service ET-MOWIE-43310-GO-RFQ / Procurement of office equipment for Dire Dawa City Water Supply and Pending Request for Single Stage - One Sewerage Service(Printers, IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope desk top computers, on scanners, photo copy machines and lap top computers) ET-MOWIE-43311-GO-RFQ / Procurement of office equipment for Semera City Pending Water Supply and Sewerage Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 Service(Printers, desk top Quotations Envelope on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-43313-GO-RFQ / Procurement of office equipment for Adegrat City Pending Water Supply and Sewerage Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-03-29 2018-05-10 2018-06-09 Service (printers, desk top Quotations Envelope on computers, scanners, photo copy machines and lap top computers) ET-MOWIE-50407-GO-DIR / Procurement of Bulk Flow meter for Mekelle Town IDA / 60070 Prior Direct Selection Direct 0.00 Canceled 2018-02-28 2018-03-05 2018-04-06 2018-07-05 Water Supply and Sewerage Service by Mekelle town WSSS ET-MOWIE-55837-GO-RFB / Pending Single Stage - One Procurement of Automatic IDA / 60070 Post Request for Bids Open - National 0.00 Implementati 2018-06-20 2018-06-25 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Envelope Water Meter Test Bench on ET-MOWIE-43018-GO-RFB / Procurement of 44 vehicles(double Cabins) for secondary city utilities, Under Regional Water Bureaus IDA / 60070 Prior Direct Selection Direct 0.00 Implementati 2018-06-20 2018-06-25 2018-07-30 2018-11-27 and 2 Vehicles( double on Cabins) for Ministry PIU by the Ministry of Water Irrigation and Electricity through UNOPS ET-MOWIE-75633-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Pending Request for Single Stage - One laptop computers for Amhara IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 Quotations Envelope Region Water,Irrigation and on Energy Development Bureau by Amhara Region Water,Irrigation and Energy Development Bureau Page 4 ET-MOWIE-75634-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Pending photocopy machines and Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 laptop computers for Oromia Quotations Envelope on Region Water,Mineral and Energy Bureau by Oromia Region Water,Mineral and Energy Bureau. ET-MOWIE-75635-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Pending Request for Single Stage - One laptop computers for SNNPR IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 Quotations Envelope Region Water,Irrigation and on Energy Development Bureau by SNNPR Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75636-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners Pending photocopy machines and Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 laptop computers for Afar Quotations Envelope on Region Water Resource Development Bureau by Afar Region Water Resource Development Bureau ET-MOWIE-75637-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Pending Request for Single Stage - One laptop computers for Somali IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 Quotations Envelope Region Water Resource on Development Bureau by Somali Region Water Resource Development Bureau ET-MOWIE-75641-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Pending laptop computers for Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 Gambella Region Quotations Envelope on Water,Irrigation and Energy Development Bureau by Gambella Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75643-GO-RFQ / Procurement of office equipment (printers, desk top computers, scanners photocopy machines and Pending laptop computers for Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 Benshangul Gumuz Region Quotations Envelope on Water,Irrigation and Energy Development Bureau by Benshangul Region Water,Irrigation and Energy Development Bureau Page 5 ET-MOWIE-75646-GO-RFQ / Procurement of Office Equipment (printers, desktop Pending computers, scanners, Request for Single Stage - One IDA / 60070 Post Limited 0.00 Implementati 2018-09-15 2018-11-10 2018-12-10 photocopy machines and Quotations Envelope on laptop computers) for Tigray Region Water Bureau by Tigray Region Water Bureau ET-MOWIE-84615-GO-RFB / Procurement of 44 Double Under Cup vehicles for 22 Open - Single Stage - One IDA / 60080 Prior Request for Bids 0.00 Implementati 2018-11-15 2018-11-20 2019-01-01 2019-01-31 2019-03-07 2019-09-03 Secondary Cities, Regional International Envelope on Water Bureaus PMU, and Federal PMU ET-MOWIE-98176-GO-RFB / Supply and Installation Equipment for Water Pending Quality Laboratory and Open - Single Stage - One IDA / 60070 Post Request for Bids 0.00 Implementati 2019-03-14 2019-03-19 2019-04-30 2019-05-30 2019-07-04 2019-11-01 Training Center for Mekelle International Envelope on Town Water Supply Project by Mekelle Town Water Supply Office NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43244-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Implementation Water Management System for Harari town by Harari Town water supply and sewerage service ET-MOWIE-50559-CS-QCBS / Consultancy Service for Establishment of Urban Water Supply and Waste Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-06-20 2018-07-20 2018-09-02 2018-09-30 2018-10-30 2018-12-04 2019-01-08 2020-01-08 Water Management Service Based Selection Implementation Regulation in Ethiopia by Ministry of Water Irrigation and Electricity ET-MOWIE-43193-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - IDA / 60070 Prior 0.00 Under Review 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Detail Design of Waste Based Selection International Water Management System for Jimma and Nekemte Towns by Oromia Water Mineral and Energy Bureau Page 6 ET-MOWIE-43212-CS-QCBS / Consultancy Service for Development of an Integrated City Wide Quality And Cost- Sanitation plan and IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Feasibility Study and Detail Design for Asella Town WSSS by Asella Town water supply and sewerage service ET-MOWIE-43209-CS-QCBS / Consultancy Service for Development of an Integrated City Wide Quality And Cost- Under Sanitation plan and IDA / 60070 Post Open - National 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Based Selection Implementation Feasibility Study and Detail Design for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-43208-CS-QCBS / Consultancy Service for Development of an Integrated City Wide Quality And Cost- Sanitation plan and IDA / 60070 Post Open - National 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Based Selection Feasibility Study and Detail Design for Sodo Town WSSS by Sodo Town water supply and sewerage service ET-MOWIE-43214-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan Quality And Cost- Under and Feasibility Study and IDA / 60070 Post Open - National 0.00 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Implementation Detail Design of Waste Water Management System for Adegrat town by Tigray Region Water Bureau ET-MOWIE-43206-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Dessie town by Dessie Town water supply and sewerage service ET-MOWIE-43200-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Gambella town by Gambella Town water supply and sewerage service ET-MOWIE-43198-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-06-24 2018-07-22 2018-09-20 2018-11-01 2018-12-13 2019-09-09 Detail Design of Waste Based Selection Water Management System for Nekemet town by Nekemet Town water supply and sewerage service Page 7 ET-MOWIE-43237-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Jigjiga town by Jigijiga Town water supply and sewerage service ET-MOWIE-43239-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Shashemene town by Shashemene Town water supply and sewerage service ET-MOWIE-43216-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Semera town by Semera Town water supply and sewerage service ET-MOWIE-43241-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Bishoftu town by Bishoftu Town water supply and sewerage service ET-MOWIE-43059-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Deghabur town by Deghabur Town water supply and sewerage service ET-MOWIE-43248-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Arbaminch town by Arbaminch Town water supply and sewerage service Page 8 ET-MOWIE-43203-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Detail Design of Waste Based Selection Water Management System for Gonder town by Gonder Town water supply and sewerage service ET-MOWIE-65731-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - Under Detail Design of Waste IDA / 60080 Prior 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Based Selection International Implementation Water Management System for Gambella, Semera and Asosa Towns by Ministry of Water Irrigation and Electricity ET-MOWIE-65735-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - Detail Design of Waste IDA / 60080 Prior 0.00 Under Review 2018-06-28 2018-07-19 2018-09-01 2018-09-29 2018-10-29 2018-12-03 2019-01-07 2019-10-04 Based Selection International Water Management System for Asella, Shashemene and Bishoftu towns by Oromia Water, Mineral and Energy Bureau ET-MOWIE-65737-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - Under IDA / 60080 Prior 0.00 2018-06-28 2018-07-19 2018-09-01 2018-09-29 2018-10-29 2018-12-03 2019-01-07 2019-10-04 Detail Design of Waste Based Selection International Implementation Water Management System for Gonder, Dessie and Debreberhan towns by Amehara Water Bureau ET-MOWIE-65751-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - Under IDA / 60080 Prior 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Detail Design of Waste Based Selection International Implementation Water Management System for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-65753-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Feasibility Study and Quality And Cost- Open - Detail Design of Waste IDA / 60080 Prior 0.00 Under Review 2018-06-26 2018-07-17 2018-08-30 2018-09-27 2018-10-27 2018-12-01 2019-01-05 2019-10-02 Based Selection International Water Management System for Jijiga and Deghabur Towns by Somali Region Water Resource Development Bureau Page 9 ET-MOWIE-43213-CS-QCBS / Consultancy Service for Development of an Integrated City Wide Sanitation plan and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Feasibility Study and Detail Based Selection Design for Aossosa Town WSSS by Assosa Town water supply and sewerage service ET-MOWIE-55840-CS-QCBS / Procurement of re- innovation of Enterprise level Quality And Cost- Pending Information Management IDA / 60070 Post Open - National 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-12-30 Based Selection Implementation System by Mekele Town Water Supply and Sewerage Service ET-MOWIE-43218-CS-QCBS / Consultancy service for Development of an integrated Quality And Cost- Town Sanitation plan for IDA / 60070 Post Open - National 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Based Selection Dire Dewa town by Dire Dawa Town water supply and sewerage service ET-MOWIE-43231-CS-QCBS / Consultancy service for Development of an integrated Quality And Cost- Town Sanitation plan for IDA / 60070 Post Open - National 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Based Selection Adama town by Adama Town water supply and sewerage service ET-MOWIE-43234-CS-QCBS / Consultancy service for Development of an integrated Quality And Cost- Town Sanitation plan for IDA / 60070 Post Open - National 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Based Selection Hawassa town by Hawassa Town water supply and sewerage service ET-MOWIE-43227-CS-QCBS / Consultancy service for Development of an integrated Quality And Cost- Town Sanitation plan for IDA / 60070 Post Open - National 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Based Selection Mekelle town by Mekelle Town water supply and sewerage service ET-MOWIE-43222-CS-QCBS / Consultancy service for Development of an integrated Quality And Cost- City Wide Sanitation plan IDA / 60070 Post Open - National 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-08-28 2018-10-09 2018-11-20 2019-08-17 Based Selection for Bahir Dar town by Bahir Dar Town water supply and sewerage service ET-MOWIE-77757-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic plan and Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2019-10-09 implementation mechanisms Based Selection Implementation for Harar town Water supply and Sewerage authorities by Harar town Water supply and Sewerage authorities Page 10 ET-MOWIE-75921-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of business plan and NRW Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-11-22 2018-12-13 2019-01-26 2019-02-23 2019-03-25 2019-04-29 2019-06-03 2019-11-30 Reduction strategic plan and Based Selection Implementation implementation mechanisms for for Adama, Asella, Shashamene and Bishoftu towns by Oromia WMEB ET-MOWIE-75919-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of Quality And Cost- Under business plan and NRW IDA / 60070 Post Open - National 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2019-12-08 Based Selection Implementation Reduction strategic plan and implementation mechanisms for Jimma and Nekemte towns by Oromia WMEB ET-MOWIE-75930-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of business plan and NRW Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2019-10-09 Reduction strategic plan and Based Selection Implementation implementation mechanisms Mekele and Adigrat towns by Tigray regional water bureau ET-MOWIE-77755-CS-QCBS / Consultancy service service for preparation of business plan and NRW Reduction strategic plan and Quality And Cost- Under implementation m for IDA / 60070 Post Open - National 0.00 2018-11-29 2018-12-20 2019-02-02 2019-03-02 2019-04-01 2019-05-06 2019-06-10 2019-10-08 Based Selection Implementation Gambella, Semera and Asosa towns Water supply and Sewerage authorities by Ministry of Water Irrigation and Electricity ET-MOWIE-77754-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic plan and implement Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-11-14 2018-12-05 2019-01-18 2019-02-15 2019-03-17 2019-04-21 2019-05-26 2019-09-23 for A/Minch, Sodo and Based Selection Implementation Hawassa towns Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-77756-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strategic plan and Quality And Cost- Under IDA / 60070 Post Open - National 0.00 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-09-24 implementation for JIjiga Based Selection Implementation and Deghabur towns Water supply and Sewerage authorities by Somali Region Water Bureau ET-MOWIE-77761-CS-QCBS / Consultancy service for preparation of business plan and NRW Reduction strafor Quality And Cost- Under Gonder, Dessie, Debreberhan IDA / 60070 Post Open - National 0.00 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-09-24 Based Selection Implementation and Bahirdar towns Water supply and Sewerage authorities by Amhara Region Water Bureau Page 11 ET-MOWIE-77764-CS-QCBS / consultancy service for preparation of business plan for Jima, Nekemte and Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-08-06 Bishoftu Towns Water Based Selection Supply project by Oromia Water, Mineral and Energy Bureau ET-MOWIE-75929-CS-QCBS / Selection and employment of consultant for situational assessment and Quality And Cost- development of NRW IDA / 60070 Post Open - National 0.00 Canceled 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-08-06 Based Selection reduction and management interventions for Jigjiga and Deghabur towns by Somali Region Water Bureau ET-MOWIE-75924-CS-QCBS / Selection and employment of consultant for situational assessment and Quality And Cost- development of NRW IDA / 60070 Post Open - National 0.00 Canceled 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-10-05 Based Selection reduction and management interventions for Bahirdar, D/berhan and Dessie towns by Amhara Water Bureau ET-MOWIE-77752-CS-QCBS / Consultancy service for preparation of business plan Quality And Cost- for Mekele and Adegrat IDA / 60070 Post Open - National 0.00 Canceled 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-08-06 Based Selection towns Water supply and Sewerage authorities by Tigray Region Water Bureau ET-MOWIE-75935-CS-QCBS / Selection and employment of consultant for situational assessment and Quality And Cost- development of NRW IDA / 60070 Post Open - National 0.00 Canceled 2018-10-02 2018-10-23 2018-12-06 2019-01-03 2019-02-02 2019-03-09 2019-04-13 2019-07-12 Based Selection reduction and management interventions for Harari town by Harari water supply and sewerage service ET-MOWIE-77885-CS-QCBS / Consultancy Service for preparation of Business plan Quality And Cost- for Adama, Asella and IDA / 60070 Post Open - National 0.00 Canceled 2018-10-05 2018-10-26 2018-12-09 2019-01-06 2019-02-05 2019-03-12 2019-04-16 2019-08-14 Based Selection Shashamene towns by Oromia Water Mineral and Energy Bureau ET-MOWIE-75932-CS-QCBS / Selection and employment of consultant for Consultancy service for preparation of business plan and NRW Quality And Cost- Pending IDA / 60070 Post Open - National 0.00 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-09-24 Reduction strategic plan and Based Selection Implementation implementation mechanisms for Soda, Hawasa and Arbamich towns by SNNP reginal water bureaus ET-MOWIE-75927-CS-QCBS / Selection and employment of consultant for situational assessment and Quality And Cost- development of NRW IDA / 60070 Post Open - National 0.00 Canceled 2018-09-27 2018-10-18 2018-12-01 2018-12-29 2019-01-28 2019-03-04 2019-04-08 2019-10-05 Based Selection reduction and management interventions for Gambella, Semera and Asosa towns by MoWIE Page 12 ET-MOWIE-84640-CS-QCBS / Consultancy Service for Quality And Cost- Open - Under Preparation of Urban Water IDA / 60080 Prior 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-06-10 Based Selection International Implementation Supply Study and Design Criteria ET-MOWIE-77886-CS-QCBS / Consultancy Service for Quality And Cost- Under preparation of Business plan IDA / 60070 Post Open - National 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-21 2019-03-23 2019-04-27 2019-06-01 2019-09-29 Based Selection Implementation for Dire Dewa town by Diredewa town water utility ET-MOWIE-75898-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Care, FM improvement, Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 network management and Based Selection and capacity Building for Deghabur and Jigjiga towns by Somali Region Water Resource Development Bureau ET-MOWIE-75900-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- Care, FM improvement, IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 Based Selection network management and and capacity Building for Adegrat and Mekelle towns by Tigray Region Water Bureau ET-MOWIE-75896-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Care, FM improvement, Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 network management and Based Selection and capacity Building for Bahirdar, Gonder, Debrebrihan and Dessie towns by Amahara Water Bureau ET-MOWIE-75897-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 Care, FM improvement, Based Selection network management and and capacity Building for Gambella, Semera, and Asosa towns by MoWIE ET-MOWIE-75892-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 Care, FM improvement, Based Selection network management and and capacity Building for Nekemte and Jimma towns by by Oromia WMEB Page 13 ET-MOWIE-75903-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- Care, FM improvement, IDA / 60070 Post Open - National 0.00 Canceled 2018-11-14 2018-12-05 2019-01-18 2019-02-15 2019-03-17 2019-04-21 2019-05-26 2019-11-22 Based Selection network management and and capacity Building for Hawassa, Sodo, and Arbaminch towns by SNRPR Water Bureau ET-MOWIE-75888-CS-INDV / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- Care, FM improvement, IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 Based Selection network management and Capacity Building for Adama, Assela, Bishoftu and Shashamene towns by Oromia WMEB ET-MOWIE-75899-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-08-25 Care, FM improvement, Based Selection network management and and capacity Building for Harar town by by Harar WMEB ET-MOWIE-75905-CS-QCBS / Selection and Employment of Consultant for Development of Billing and Accounting System, Customer Quality And Cost- IDA / 60070 Post Open - National 0.00 Canceled 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-08-25 Care, FM improvement, Based Selection network management and and capacity Building for Diredewa town WSSS by diredewa town WSSS ET-MOWIE-107044-CS- QCBS / Selection and employment of consultant for Consultancy service for preparation of business plan and NRW Reduction Quality And Cost- Pending IDA / 60070 Post Open - National 0.00 2019-04-10 2019-05-01 2019-06-14 2019-07-12 2019-08-11 2019-09-15 2019-10-20 2020-04-17 strategic plan and Based Selection Implementation implementation mechanisms for Adama, Asella, Shashamene, Nekemte, Jimma and Bishoftu towns by Oromia WMEB INDIVIDUAL CONSULTANTS Page 14