The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Climate Resilient Agriculture and Productivity Enhancement Project (P162956) AFRICA | Chad | Agriculture Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 2 | ARCHIVED on 09-May-2019 | ISR36638 | Implementing Agencies: Republic of Chad, Ministry of Agriculture, Irrigation and Agricultural Equipment, West and Central African Council for Agricultural Research and Development (CORAF/WECARD) Key Dates Key Project Dates Bank Approval Date: 30-Apr-2018 Effectiveness Date: 30-Nov-2018 Planned Mid Term Review Date: 25-Oct-2021 Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective (PDO) is to “to promote the adoption of improved technologies leading to increased productivity and to enhance the climate resilience of agricultural production systems in the areas targeted by the Project”. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional support for sustainable agriculture development and climate resilience:(Cost $12.60 M) Supporting adoption of demand driven technologies and climate-smart agriculture:(Cost $23.60 M) Contingency emergency response Project management, coordination, monitoring and evaluation and knowledge management:(Cost $4.80 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions The project was made effective in November 30, 2018 and was technically launched in December 18, 2018. The project will focus primarily on the following activities: - Preparation of the national agricultural extension strategy, the national strategy for agricultural research and development, and the feasibility study for the development of the seed sector in Chad; - Finalization of studies on new agricultural extension approaches including e-voucher and e- extension. The next implementation support mission will be carried out in June 2019. 5/9/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies High High High Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Moderate Substantial Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- -- -- Overall High High High Results PDO Indicators by Objectives / Outcomes Supporting adoption of demand-driven technologies and climate-smart agriculture IN00690577 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 360,000.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690580 Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 108,000.00 IN00690602 ►Surface area under improved technology disseminated by the Project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 21,400.00 5/9/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690603 Surface area under Climate-smart Agriculture technolgies/practices (Hectare(Ha), Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10,700.00 Institutional support for sustainable agriculture development and climate resilience IN00690578 ►Percentage increase in average agriculture yield of direct beneficiaries compared to average yields in the Project area (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Project management, coordination, M&E, and knowledge management IN00690579 ►Share of targeted beneficiaries with rating ‘Satisfied’ or above on project interventions (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690601 Share of targeted female beneficiaries with rating ‘Satisfied’ or above on project interventions (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 90.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Overall Comments PDO The Project's activities have not started yet. Intermediate Results Indicators by Components Project management, coordination, monitoring and evaluation and knowledge management IN00690607 ►Annual audits submitted on time and without major qualification (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 5/9/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Value 0.00 0.00 0.00 4.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690609 ►Grievance Resolution Mechanism established and operational (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690613 ►Technical audit report for matching grants funded sub-projects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 21-Feb-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Supporting adoption of demand driven technologies and climate-smart agriculture IN00690605 ►Operational regional innovation platforms (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 9.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690608 ►Direct beneficiaries using agricultural climate services (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690612 ►Improved seeds produced by the targegeted beneficiairies (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3,000.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690614 ►Number of sub-projects to intensify sustainable production systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,100.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690617 5/9/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) ►Number of diversification sub-projects supported (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 360.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690618 ►Number of CSA sub-projects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Contingency emergency response IN00690606 ►Time required for the government to make requested funds available for an eligible crisis or emergency (Weeks, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Institutional support for sustainable agriculture development and climate resilience IN00690604 ►Young researchers trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 17.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690610 Young researchers trained - female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 IN00690611 ►Quantity of foundation seeds produced - cereals (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 97.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690615 Quantity of foundation seeds - other crops (Metric ton, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 5/9/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Value 0.00 0.00 0.00 48.00 IN00690616 ►Improved technologies disseminated by the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 IN00690619 ►Agriculture sector reform/ policies & strategies supported (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Jan-2018 02-Oct-2018 25-Mar-2019 30-Jun-2023 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P162956 IDA-D3020 Effective USD 41.00 41.00 0.00 2.12 37.25 5.4% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P162956 IDA-D3020 Effective 30-Apr-2018 19-Jun-2018 30-Nov-2018 31-Dec-2023 31-Dec-2023 Cumulative Disbursements 5/9/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/9/2019 Page 7 of 7