The World Bank Report No: ISR11959 Implementation Status & Results Peru PE Social Inclusion TAL (P131029) Public Disclosure Copy Operation Name: PE Social Inclusion TAL (P131029) Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 07-Nov-2013 Country: Peru Approval FY: 2013 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Technical Assistance Loan Implementing Agency(ies): Ministry of Social Inclusion Key Dates Board Approval Date 13-Dec-2012 Original Closing Date 31-Jan-2017 Planned Mid Term Review Date 14-Apr-2015 Last Archived ISR Date 10-Apr-2013 Effectiveness Date 11-Apr-2013 Revised Closing Date 31-Jan-2017 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to strengthen MIDIS’s systems and capacity to improve the performance of MIDIS’s programs and to monitor social inclusion policy. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Component 1: Quality improvement of MIDIS’s Programs 3.53 Component 2: Improving knowledge management, information and communication 3.73 Component 3: Strengthening of MIDIS’s capacity on results orientation, monitoring and evaluation 3.49 Component 4: Strengthening of human resource management and capacity 2.29 Component 5: Support to Project Administration 1.24 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status Overview After effectiveness, disbursement concentrated mainly on activities related to Project management and to strengthening the Ministry of Development and Social Inclusion (MIDIS)’ social programs. During the initial phase of implementation, the team invested a significant amount of energy ensuring a proper coordination between the administrative coordinating Page 1 of 5 The World Bank Report No: ISR11959 unit in MEF (Coordinating Unit for Sectoral Loans -UCPS) and the Project Technical Coordination in MIDIS, in order to ensure the speed and quality of processes. During the latest supervision mission (September 30 - October 4, 2013) the new Minister highlighted the new priorities of MIDIS (Early Child dDevelopment, targeting and decentralization) which are expected to influence the areas of focus of this Project and introduce adjustments to activities and the procurement plan. Public Disclosure Copy Locations No Location data has been entered Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Coverage of MIDIS programs is improved Percentage Value 0.00 0.00 (Percentage points increase of users families Date 31-Jan-2017 of MIDIS's programs of total families eligiblefor Comments N/A N/A at least one MIDIS's program). Key monitoring and evaluation, and Number Value 0.00 2.00 coordination mechanisms are established Date 31-Jan-2017 (Number of Programs' “Improvement Comments Unit of Measure: Year 1, 2 agreements� signed between programs and MIDIS). and 3: Programs’ “Improvement agreements� based on the Technical Reports from the monitoring dashboard and evaluations signed between the General Directorate of Monitoring and Evaluation (DGSYE) and the programs. Year 4: Two new Programs’ “Improvement agreements� signed; and one Public Disclosure Copy “Improvement Agreement� signed in previous years evaluated and showing, at least, partial fulfillment. Intermediate Results Indicators Page 2 of 5 The World Bank Report No: ISR11959 Indicator Name Core Unit of Measure Baseline Current End Target Improvement in quality of MIDIS's programs as Number Value 0.00 4.00 shown by the implementation of users Date 31-Jan-2017 Public Disclosure Copy accountability mechanisms (number of MIDIS's Comments programs with user accountability mechanisms). MIDIS operates in a de-concentrated way Number Value 0.00 1.00 along the country’s territory (steps to support Date 31-Jan-2017 that MIDIS's one-stop shops or decentralized Comments Year 1: MIDIS one-stop shops offices use tool for territorial coordination). (or decentralized offices) operating in the territory are using planning tools designed to facilitate territorial coordination; Year 2: MIDIS one-stop shops are using a common information system; Year 3 and 4: MIDIS one-stop shops areusing monitoring and evaluation tools designed to facilitate territorial coordination. MIDIS is implementing an integrated Number Value 0.00 4.00 information system for its programs (number of Date 31-Jan-2017 MIDIS's programs that share a common Comments informationplatform). Improved performance of SISFOH by Percentage Value 0.00 100.00 interconnecting Local Targeting Units Date 31-Jan-2017 (Percentage ULFs interconnected and with Comments End Target: 100%. their staff trained on standardized practices). A national communications strategy for MIDIS Number Value 0.00 1.00 is in place and includes different approaches Date 31-Jan-2017 Public Disclosure Copy for different population groups (i.e., indigenous Comments Unit of Measure: Number of peoples) (Number of steps completed). Steps: Step 1: Design of the communication strategy; Step 2: Pilots of strategy; Step 3 and 4: A national strategy is in place and includes different approaches for different population groups. Page 3 of 5 The World Bank Report No: ISR11959 MIDIS monitors infant malnutrition and Number Value 0.00 10.00 development plans indicators at the regional Date 31-Jan-2017 level (number of regions). Comments Unit of Measure: Number of Public Disclosure Copy regions with an operating information dashboard on infant malnutrition and development plans indicators. MIDIS's programs and policies are being Number Value 0.00 6.00 evaluated (number of programs and policies Date 31-Jan-2017 that are being evaluated). Comments MIDIS designs and implements a policy tool to Number Value 0.00 0.00 coordinate interventions to reduce chronic Date 31-Jan-2017 malnutrition (Number of operations rules Comments designed to coordinate interventions to reduce chronic malnutrition). MIDIS introduces results-oriented human Number Value 0.00 1.00 resource management practices (number of Date 31-Jan-2017 steps completed). Comments Unit of Measure: Step 1: Design of the methodology to introduce results-oriented human resources management practices; Step 2: Pilots of methodology; Step 3: Official document formalizing the incorporation of performance evaluations in MIDIS’ human resources management practices. Step 4: Performance based human resources policy is in operation. Public Disclosure Copy Data on Financial Performance (as of 13-Aug-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P131029 IBRD-82220 Effective 13-Dec-2012 15-Jan-2013 11-Apr-2013 31-Jan-2017 31-Jan-2017 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Page 4 of 5 The World Bank Report No: ISR11959 P131029 IBRD-82220 Effective USD 10.00 10.00 0.00 0.11 9.89 1.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation MIDIS is expected to present a proposal for Project restructuring to reflect the new priorities of the Minister. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 5 of 5