Procurement Plan I. General 1. Project Information Project Name: Second Rural Access Project Country: Yemen P085231 for Credit No 4121 Project ID & Loan/Credit Numbers: : P0117408 for Additional Financing Grant No H5430 2. Bank's approval date of Procurement PlanOriginal: November 15, 2009 Revision 1:April 20,2010 Revision 2: Septamber 11,2011 Revision3: Feb 2012 Revision4: May 29, 2012 Revision 5: December 2012 Revision 6: April 2013 Revision 7: Jan. 2014 3. July 16,2008 for Credit No 4121 Date of General Procurement Notice Updated November 2, 2009 for Additional Financing to Credit No II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] 1a. Procurement Category Prior Review Threshold (USD) Comments Goods Greater than or Equal 500,000 All contracts Works Greater than or Equal 5,000,0000 All contracts Non-Consultant Services Greater than or Equal 200,000 All contracts Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments ICB and LIB (Goods) Greater than or Equal 300,000 NCB (Goods) Less than 300,000 First contract is subject to Prior Review Shopping IS (Goods) Less than 50,000 First contract is subject to Prior Review Shopping NS(Goods) Less than 50,000 First contract is subject to Prior Review ICB (Works) Greater than 5,000,0000 NCB (Works) Less than or equal 5,000,0000 First contract is subject to Prior Review ICB (Non-Consultant Services) Greater than or Equal 200,000 Include all methods authorized by the loan agreement 2. Prequalification. Bidders for 10,000,000_ shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): Refer to the relevant CDD project implementation document NA approved by the Bank 4. Reference to (if any) Project Operational/Procurement Manual: RAPCMO Drafted Manual of Procedures 5. Any Other Special Procurement Arrangements: Including advance procurement and retroactive financing, if applicable NA 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 1a. Procurement Category Prior Review Threshold (USD) Comments Consulting Firms (Competitive) Greater than or Equal 200,000 All contracts Consulting Firms (National adv.) greater than 200,000 All TOR Consulting Firms (Sole Source) all All Contracts Individual Consultants (Competitive) greater than or equil 100,000 All TOR Individual Consultants (Sole Source) All All Contracts Include all categories authorized by the loan agreement Procurement Method 1b. Procurement Method Threshold (USD) Comments QCBS Greater than or equial 300,000 QCB Less than 300,000 FCS Less than 300,000 LCS Less than 300,000 CQS Less than 300,000 Consulting Firms (Competitive) Any Value Consulting Firms (Sole Source) Less than 100,000 Individual Consultants (Competitive) Less than 100,000 Individual Consultants (Sole Source) Less than 50,000 ICB (Non-Consultant Services) Greater than or Equal 200,000 Include all methods authorized by the loan agreement 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300.000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. NA http://go.worldbank.org/MKXO98RY40 Note: OPCPR list of ceilings can be found here: 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] NA 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet Procurement Plan for Works and Goods 10-Oct-52 ** Applicable in case of Bank's prior review Prequalification Bank’s No No Objection No Objection Objection to Review Bank’s No from Bank for from Bank for Preparation Contract Bid Name, City, and Goods/ by Domestic Prequalifi Objection to Bid Bid Bid Contract Value Expenditure Contract Completion Expenditure Expenditure SL Package/ Method of Draft Evaluation of of Bid Award Evaulation Contract Phase II Contract Country of Description of Goods/ Works Works/ Bank Preferenc cation Bidding Invitation Closing Opening +Vartion Order incurred from Currenc of Contract incurred to incurred from Remarks No. Reference No. Selection Prequalificatio Prequalificatio Document Decision Report and Signed (Date) Commitments No. Contractor (incl. NCS (Prior/ e (yes/no) (yes/no) Document (Date) (Date) (Date) (US$) phase I y (Date) Date phase II n documents n Application (Date) (Date) Contract Zip Code if US) Post) (Date)** (Date)** (Date)** Award (Date)** Yemen P085231: Yemen Rural Access Project-Phase II Cerdit No 4121 First:- RAP Components Planned Prior ICB No Yes NA NA 1-Dec-01 16-Nov-01 1-Mar-02 1-Mar-02 1-Mar-02 2-Apr-02 19-Jun-02 1-Jul-02 26-Feb-03 Kahlan Trading & Revised 1 IFB#1C.W/02 Thula – Amran RR + Some VA Works 3,212,705 3,107,026 105,679 USD I CW\02 3,211,133.49 104,107 Completed Contracting Actual Prior ICB No Yes 26-Dec-02 1-Aug-01 16-Nov-01 1-Jan-02 9-Mar-02 9-Mar-02 17-Mar-02 19-Jun-02 17-Jul-02 25-May-04 Planned Prior ICB No Yes NA NA 1-Dec-01 16-Nov-01 1-Mar-02 1-Mar-02 1-Mar-02 2-Apr-02 19-Jun-02 1-Jul-02 28-Feb-04 Kuhlan – Al Maghrabah RR + Technohouse & Revised 2 IFB#2C.W/02 Works 2,078,885 2,068,539 10,347 USD 3CW/02 2,078,364.44 9,826 Completed Some VA Betonut Actual Prior ICB No Yes 26-Dec-02 1-Aug-01 16-Nov-01 1-Jan-02 9-Mar-02 9-Mar-02 8-Apr-02 6-Aug-02 22-Sep-02 26-Mar-06 Planned Prior ICB No Yes NA NA 1-Aug-02 16-Nov-01 15-Sep-02 1-Nov-02 1-Nov-02 1-Dec-02 19-Jun-02 1-Mar-03 30-Apr-08 Kahlan Trading & Revised 3 IFB#8C.W/02 Azzaher – Al Ribat RR Works 3,476,596 2,742,618 733,978 YR CW5/03 3,463,143.35 720,525 Completed Contracting Actual Prior ICB No Yes 5-Aug-02 12-Sep-02 17-Sep-02 27-Nov-02 27-Nov-02 28-Dec-02 19-Mar-03 31-Mar-03 27-Mar-08 Planned Prior ICB No Yes NA NA 1-Aug-02 16-Nov-01 15-Sep-02 1-Nov-02 1-Nov-02 1-Dec-02 19-Jun-02 28-Feb-03 10-Nov-06 Revised 4 IFB#9C.W/02 Seham – Bora’a RR Works 3,698,458 3,253,330 445,128 YR CW6/03 Al Ryan 3,698,437.46 445,108 Completed Actual Prior ICB No Yes 5-Aug-02 12-Sep-02 17-Sep-02 27-Nov-02 27-Nov-02 28-Dec-02 18-Mar-03 1-Apr-03 10-Apr-08 Planned Prior ICB No Yes NA NA 1-Aug-02 16-Nov-01 15-Sep-02 1-Nov-02 1-Nov-02 1-Dec-02 19-Jun-02 28-Feb-03 30-Apr-07 Akamat Al Agoud – Mudykhirah Abdulgabar Revised 5 IFB#11C.W/02 Works 6,472,709 4,625,756 1,846,953 YR CW8/03 6,472,899.29 1,847,143 Completed RR Aladimi Actual Prior ICB No Yes 5-Aug-02 12-Sep-02 17-Sep-02 27-Nov-02 27-Nov-02 28-Dec-02 23-Mar-03 31-Mar-03 15-Feb-08 Planned Prior NA NA NA NA NA 15-May-03 16-Nov-01 15-Aug-03 1-Oct-03 1-Oct-03 1-Nov-03 19-Jun-02 31-Jan-04 30-Sep-06 Revised 6 IFB#15CW/03 Al Qanawis – Al Kadan RR Works Prior ICB No No 1,366,000 1,132,443 233,557 USD CW10/04 Al Ozari Corp. 1,364,466.39 232,023 Completed Actual Prior ICB No No 1-Jul-03 15-Aug-03 25-Aug-03 1-Oct-03 1-Oct-03 3-Dec-03 3-Mar-04 3-Apr-04 21-Nov-06 Planned Prior NA NA NA NA NA 15-May-03 16-Nov-01 15-Aug-03 1-Oct-03 1-Oct-03 1-Nov-03 19-Jun-02 31-Jan-04 30-Jan-07 Revised 7 IFB#16CW/03 Al Udien – Mudykhirah RR Works Prior ICB No No 2,655,562 2,089,098 566,464 USD CW11/04 Sheba Co. 2,655,561.71 566,464 Completed Actual Prior ICB No No 1-Jul-03 15-Aug-03 25-Aug-03 22-Oct-03 22-Oct-03 2-Dec-03 2-Mar-04 3-Apr-04 7-Mar-07 Planned Prior NA NA NA NA NA 15-Jul-03 16-Nov-01 31-Aug-03 15-Oct-03 15-Oct-03 15-Nov-03 19-Jun-02 15-Feb-04 28-Feb-04 Revised 8 IFB#17CW/03 Bayhan- Al Harajh - Al Kura’a RR Works Prior ICB No No 1,839,756 1,545,057 294,700 USD CW12/04 Al Shahra . Co 1,839,744.71 294,688 Completed Actual Prior ICB No No 10-Aug-03 1-Sep-03 2-Sep-03 22-Oct-03 22-Oct-03 2-Dec-03 2-Mar-04 3-Apr-04 13-Mar-07 Planned Prior NA NA NA NA NA 15-Jul-03 16-Nov-01 31-Aug-03 15-Oct-03 15-Oct-03 15-Nov-03 19-Jun-02 15-Feb-04 15-Feb-06 Abyn Rural Roads(Zunjbar- Revised 9 IFB#18CW/03 Works Prior ICB No No 1,090,940 937,646 153,294 USD CW13/04 Al Masar Co. 1,063,880.16 126,234 Completed Shiekh Abdullah+Zarah - Al Jouf) Actual Prior ICB No No 10-Aug-03 29-Aug-03 2-Sep-03 22-Oct-03 22-Oct-03 2-Dec-03 2-Mar-04 31-Mar-04 26-Aug-06 Planned Prior NA NA NA 15-Sep-03 16-Nov-01 15-Nov-03 10-Jan-04 10-Jan-04 15-Apr-04 19-Jun-02 30-Aug-07 8-Aug-05 Terminated & Final An Nadirah – Damt RR + Khwal Sharaf for Revised 10 IFB#21CW/03 Works Prior ICB No No 3,250,901 2,050,879 1,200,022 USD CW14/04 2,838,165.78 787,287 payment has been Alshaier VA Gen.Con. Actual Prior ICB No No 15-Sep-03 31-Oct-03 20-Nov-03 15-Feb-04 15-Feb-04 4-May-04 28-Jul-04 9-Aug-04 20-May-07 issued Planned Prior NA NA NA 15-Sep-03 16-Nov-01 15-Jan-04 25-Feb-04 25-Feb-04 5-Jun-04 19-Jun-04 25-Jun-04 15-Sep-05 Under Terminating & Al Kharaz Revised 11 IFB#22CW/03 Jabl Al Dar – Ribad Emran RR Works Prior ICB No No 1,534,558 981,879 552,679 USD CW15/04 1,276,051.84 294,173 Final payment has not Contracting Actual Prior ICB No No 15-Sep-03 25-Nov-03 11-Jan-04 22-Feb-04 22-Feb-04 24-Mar-04 28-Jul-04 9-Aug-04 - been issued yet Planned Prior NA NA NA 1-Mar-04 16-Nov-01 30-May-04 20-Jul-04 20-Jul-04 15-Aug-04 29-Aug-04 31-May-08 24-Apr-07 Kahlan Trading & Closed & Final payment Revised 12 IFB#24CW/04 Orod – Souq Al Horiah RR Works Prior ICB No No 3,713,875 1,164,185 2,549,691 YR CW17/04 2,912,331.85 1,748,147 Contracting has been issued Actual Prior ICB No No 1-May-04 24-May-04 29-May-04 18-Jul-04 18-Jul-04 8-Aug-04 15-Oct-04 12-Dec-04 - Planned Prior NA NA NA 1-Mar-04 16-Nov-01 25-Feb-05 25-Apr-05 25-Apr-05 10-Jun-05 20-Jun-05 27-Oct-06 20-Apr-07 Al-Mesqah Al-Haqlain RR + Bayt Al Bashiri for Revised 13 IFB#25CW/04 Works Prior ICB No No 2,545,158 902,005 1,643,153 YR CW18/04 2,527,820.60 1,625,816 Completed Hlbob VA Trading Actual Prior ICB No No 1-May-04 24-May-04 9-Mar-05 20-Apr-05 20-Apr-05 25-May-05 8-Sep-06 8-Nov-05 7-Feb-08 Planned Prior NA NA NA 1-Mar-04 16-Nov-01 30-May-04 20-Jul-04 20-Jul-04 20-Oct-04 15-Nov-04 15-Dec-04 15-Feb-06 Al-Dhabab – Al-Manaom RR + Kahlan Trading & Revised 14 IFB#26CW/04 Works Prior ICB No No 2,122,304 1,015,712 1,106,591 YR CW19/04 1,999,949.05 984,237 Completed Yufrus jabal Habashi RR Contracting Actual Prior ICB No No 1-May-04 24-May-04 29-May-04 18-Jul-04 18-Jul-04 8-Aug-04 15-Dec-04 7-Feb-05 21-Jun-10 Planned Prior NA NA NA 1-Mar-04 16-Nov-01 30-May-04 20-Jul-04 20-Jul-04 20-Oct-04 15-Nov-04 1-Feb-05 3-Mar-06 ALRehab Eng'g Revised 15 IFB#27CW/04 Al Madn – Al Shabareeq RR Works Prior ICB No No 1,439,490 565,537 873,954 YR CW20/04 1,066,054.80 500,518 Completed ,Agen. & Gen. Con. Actual Prior ICB No No 1-May-04 24-May-04 29-May-04 18-Jul-04 18-Jul-04 8-Aug-04 15-Oct-04 7-Feb-05 15-Jan-08 Planned Prior NA NA NA 15-May-04 16-Nov-01 30-Jun-04 15-Aug-04 15-Aug-04 15-Nov-04 15-Jan-05 20-Feb-05 19-Jan-06 Completed but & Final Al Kharaz Revised 16 IFB#28CW/04 Rusabah- Shareh - Al Qubah Works Prior ICB No No 684,503 557,525 126,978 YR CW21/05 557,524.67 0 payment has not been Contracting Actual Prior ICB No No 5-Jun-04 24-Jun-04 28-Jun-04 15-Aug-04 15-Aug-04 5-Sep-04 9-Feb-05 20-Feb-05 - issued yet Planned Prior NA NA NA NA NA 15-May-04 16-Nov-01 30-Jun-04 15-Aug-04 15-Aug-04 15-Sep-04 29-Sep-04 15-Dec-04 30-Dec-05 Lawder - Jisr Malihah RR+ Al Revised 17 IFB#29CW/04 Works Prior ICB No No 1,608,744 1,044,819 563,925 YR CW22/04 Al Masar Co. 1,610,530.57 565,712 Completed Hamra - Al Kayial VA Actual Prior ICB No No 5-Jun-04 24-Jun-04 28-Jun-04 15-Aug-04 15-Aug-04 5-Sep-04 23-Dec-04 15-Feb-05 28-Apr-07 Planned Prior NA NA NA NA NA 15-Jul-04 16-Nov-01 17-Oct-05 1-Dec-05 1-Dec-05 31-Dec-05 14-Jan-06 30-Apr-06 Yemen Road 30-Jun-08 Maswer District Center RR + Bayt Revised 18 IFB#30CW/05 Works Prior ICB No No 3,572,057 1,006,122 2,565,936 YR CW23/06 Construction & 3,464,018.77 2,457,897 Completed Athagah-Bayt Salah VA Actual Prior ICB No No 9-Jan-04 15-Dec-04 4-Sep-05 20-Dec-05 20-Dec-05 2-Jan-06 9-Mar-06 15-Mar-06 Trading 28-Jun-08 Planned Prior NA NA NA NA NA 1-Jul-04 16-Nov-01 20-Dec-05 2-Feb-06 2-Feb-06 2-Mar-06 16-Mar-06 30-Oct-06 30-Oct-08 Hawk Revised 19 IFB#32CW/04 Al Sadah – Al Radh'ai RR Works Prior ICB No No 5,572,820 0 5,572,820 YR CW32/06 5,526,579.67 5,485,781 Completed International Actual Prior ICB No No 1-Sep-04 22-Dec-05 29-Dec-05 12-Feb-06 12-Feb-06 28-May-06 26-Aug-06 30-Oct-06 9-Jun-09 Planned Prior NA NA NA NA NA 1-Jul-04 16-Nov-01 1-Nov-05 15-Dec-05 15-Dec-05 15-Jan-06 29-Jan-06 15-May-06 Yemen Road 30-Jul-08 Al Kadan - Malhan District Center Revised 20 IFB#33CW/04 Works Prior ICB No No 3,317,474 0 3,317,474 YR CW33/ 05 Construction & 3,177,349.90 3,177,350 Completed RR Actual Prior ICB No No 1-Sep-04 17-Nov-05 25-Nov-05 22-Jan-06 22-Jan-06 8-Feb-06 23-May-06 1-Jul-06 Trading 28-Jan-10 Planned Prior NA NA NA NA NA 1-Jan-04 16-Nov-01 20-Jul-05 20-Oct-05 20-Oct-05 20-Nov-05 4-Dec-05 20-Nov-06 30-Jun-08 Maghrabat Al Hareesh Al Revised 21 IFB#36CW/04 Works Prior ICB No No 2,191,068 0 2,191,068 YR 36 CW /05 Griffin Limited 2,168,124.42 1,890,582 Completed Maghrabah DC RR Actual Prior ICB No No 1-Dec-04 14-Jul-05 3-Aug-05 20-Nov-05 20-Nov-05 14-Feb-06 18-Jul-06 30-Oct-06 28-Feb-09 Planned Prior ICB No No NA NA 1-Nov-07 16-Nov-01 12-Jul-08 1-Sep-08 1-Sep-08 1-Nov-08 15-Nov-08 1-Mar-09 1-Aug-10 Al Solayhi Revised 22 IFB#38CW/08 Akamat Hubaish- Anbyan RR Works 2,000,250 0 2,000,250 YR 38 CW /08 30-Jun-12 1,997,139.32 1,997,139 Completed brothers Comp. Actual Prior ICB No No 1-Dec-07 5-Jul-08 12-Jul-08 9-Sep-08 9-Sep-08 24-Dec-08 27-Jan-09 8-Apr-09 24-Apr-12 Planned Post NCB No No NA NA 1-Jun-09 1-Aug-09 1-Aug-09 1-Oct-09 15-Oct-09 1-Nov-09 1-May-10 Repari works in Al Madn – Al Revised 23 IFB#39CW/09 Works NA 262,998 0 262,998 YR 39 CW /09 Al Omaesy Corp. 259,787.89 259,788 Completed Shabareeq RR Actual Post NCB No No 3-May-09 19-May-09 2-Jun-09 13-Jul-09 13-Jul-09 17-Aug-09 NA 28-Sep-09 24-May-10 Planned Post NCB No No NA NA 1-Jun-10 22-Jun-10 29-Jun-10 8-Aug-10 8-Aug-10 22-Sep-10 NA 6-Oct-10 4-Apr-11 Remaining work at Al Jumari- AlMamluk for Revised 24 IFB#40CW/10 Works 29-Oct-10 12-Nov-10 654,651 0 654,651 YR 40 CW /10 30-Sep-12 596,511.61 596,512 Completed Khwal Al Shar Project Gen. Cotracting Actual Post NCB No No NA NA 1-Jul-10 9-Jul-10 5-Aug-10 19-Sep-10 19-Sep-10 28-Dec-10 NA 19-Jan-11 Planned Post NCB No No NA NA 15-May-10 5-Jun-10 12-Jun-10 22-Jul-10 22-Jul-10 5-Sep-10 NA 19-Sep-10 18-Mar-11 Protection work for Al Sadah – Al Revised 26 IFB#42CW/10 Works 8-Nov-10 22-Nov-10 304,700.81 0 304,700.81 YR 42 CW /10 Al Gerba Office 1-Sep-12 350,348.89 350,349 Completed Radh'ai RR Actual Post NCB No No 3-May-10 17-May-10 7-Jun-10 11-Jul-10 11-Jul-10 13-Nov-10 NA 8-Feb-11 25-Mar-13 Planned Post NCB No No NA NA 1-Apr-12 NA 18-Apr-12 2-Jun-12 2-Jun-12 2-Jul-12 NA 17-Jul-12 17-Jul-13 Remaining work at Akamat Letter of Acceptance Revised 27 IFB#38CW (b) /12 Works Post NCB No No NA NA 15-May-12 NA 19-Apr-13 3-Jun-13 3-Jun-13 15-Jan-14 NA 13-Jan-14 1,772,442 0 1,772,442 US$ Al Dogymei Co. 13-Jan-15 0.00 0 Hubaish- Anbyan RR has been issued Actual Post NCB No No NA NA 13-May-12 NA 21-Jul-13 1-Sep-13 1-Sep-13 29-Dec-13 NA P.P for RAP / Works oods 3[Page] Bank’s No No Objection No Objection Objection to Review Bank’s No from Bank for from Bank for Preparation Contract Bid Name, City, and Goods/ by Domestic Prequalifi Objection to Bid Bid Bid Contract Value Expenditure Contract Completion Expenditure Expenditure SL Package/ Method of Draft Evaluation of of Bid Award Evaulation Contract Phase II Contract Country of Description of Goods/ Works Works/ Bank Preferenc cation Bidding Invitation Closing Opening +Vartion Order incurred from Currenc of Contract incurred to incurred from Remarks No. Reference No. Selection Prequalificatio Prequalificatio Document Decision Report and Signed (Date) Commitments No. Contractor (incl. NCS (Prior/ e (yes/no) (yes/no) Document (Date) (Date) (Date) (US$) phase I y (Date) Date phase II n documents n Application (Date) (Date) Contract Zip Code if US) Post) (Date)** (Date)** (Date)** Award (Date)** 1-Aug-05 Yemen P085231: Yemen Rural 5-Aug-05 Access 17-Aug-05 Project-Phase 17-Aug-05 19-Aug-05 II Cerdit No 4121 20-Aug-05 25-Aug-05 Planned Procurement of Network Post LS No No Revised 1 LS20/05 Connection for the New Office Goods 1,980 0 1,980 US$ Sharp Systems 1,980 1,980 Completed Actual Building Post LS No No NA NA NA NA NA 18-Aug-05 NA 4-Sep-05 21-Sep-05 Planned Post LS No No Procurement of Portable Hard Yemen Expert Revised 2 LS21/05 Goods 680 0 680 US$ 680 680 Completed Disks Solutions Actual Post LS No No NA NA 25-Aug-05 NA NA 29-Aug-05 NA NA 3-Sep-09 Planned Post NCB No No NA NA NA NA NA NA NA Al Jeel AlGaded Revised 3 LS19/05 Stationary for RAPCMO Goods 5,341 0 5,341 US$ 19B/2005 5,341 5,341 Completed Group Actual Post NCB No No NA NA 31-Oct-05 14-Nov-05 14-Nov-05 5-Dec-05 NA 17-Dec-05 28-Dec-05 Planned Procurement of Al uminuim Post LS No No Obayah for Revised 4 Partition for the New Office Goods 1,121 0 1,121 US$ 1,121 1,121 Completed Decoret Actual Building Post LS No No NA NA NA NA NA NA NA 8-Jan-06 15-Jan-06 Planned Procurement of Survuy Equpment Prior NCB No No 10-Mar-06 NA 5-Mar-06 5-Apr-06 5-Apr-06 Revised 5 IFB#20G-08 & GPS for Ministry of Public Goods 116,938 0 116,938 US$ IFB#20G-08 Rayman Eng. 116,938 116,938 Completed Actual Works and Highways NCB No No 1-Feb-08 18-Mar-08 30-Mar-08 10-May-08 10-May-08 12-Jul-08 NA 15-Oct-08 9-Feb-09 Planned Procurement of Communication Prior ICB No No 20-Feb-06 25-Feb-06 28-Feb-06 15-Apr-06 15-Apr-06 1-Aug-06 10-Aug-06 NA 20-Feb-07 Computer Eng. Revised 6 IFB#21G-08 Net Work and IT for Ministry of Goods 250,004 0 250,004 US$ 21G-08 250,004 250,004 Completed world Actual Public Works and Highways Prior ICB No No 1-Apr-08 10-May-08 26-May-08 6-Aug-08 6-Aug-08 22-Nov-08 3-Jan-09 31-Jan-09 3-Apr-10 Planned Prior NCB No No NA NA NA NA NA NA NA NA Procurement of Computers for Revised 7 IFB#22G-08 Goods 81,965 0 81,965 US$ 22G-08 AlMagaleh Group 81,965 81,965 Completed RAPCMO Actual Prior NCB No No 10-Feb-07 3-Mar-07 8-Mar-07 10-Apr-07 10-Apr-07 10-Jun-07 NA 15-Jul-07 31-Jan-08 Planned Post NCB No No NA NA NA NA NA NA Al Fajer Al Jadeed Revised 8 Stationary for RAPCMO Goods 9,090 0 9,090 US$ 9,090 9,090 Completed St, Actual Post NCB No No 15-Mar-07 NA 1-Apr-07 30-Apr-07 30-Apr-07 11-Jun-07 NA 16-Jun-07 25-Jun-07 Planned Post LS No No NA NA NA NA NA NA Procurement of Finger Print for Revised 9 Goods 1,800 0 1,800 US$ Beta Sys 1,800 1,800 Completed RAPCMO Actual Post LS No No NA NA 10-Jul-07 17-Jul-07 17-Jul-07 18-Sep-07 NA NA 24-Jul-07 Planned Post LS No No 1-Jul-06 NA 5-Jul-06 5-Aug-06 5-Aug-06 NA NA NA 1-Sep-06 Office Furniture for CMO & Revised 10 Goods 5,775 0 5,775 US$ Ardh Himyar 5,775 5,775 Completed Regional Offices Actual Post LS No No 1-Aug-08 NA 11-Aug-08 19-Aug-08 19-Aug-08 4-Oct-08 NA 11-Oct-08 Planned Procurement of carpet, Curtain Post LS No No NA NA NA NA NA NA NA NA Al Doubai Revised 11 and delivery of furniture for new Goods 7,976 0 7,976 US$ 7,976 7,976 Completed Furniture Center Actual building Post LS No No NA NA 17-Sep-08 20-Sep-08 20-Sep-08 21-Sep-08 NA 23-Sep-08 30-Nov-08 Planned Post LS No No NA NA NA NA NA NA NA Procurement of Ne twork for new Al Alimi Revised 12 Goods 14,726 0 14,726 US$ 14,726 14,726 Completed building Computer Servies Actual Post LS No No NA NA 16-Sep-08 20-Sep-08 20-Sep-08 21-Sep-08 NA 23-Sep-08 28-Nov-08 Planned Post NCB No No NA NA NA NA NA NA NA NA Revised 13 1B\09 Stationary for RAPCMO Goods 5,075 0 5,075 US$ 1B\09 Eatimad St. 5,075 5,075 Completed Actual Post NCB No No NA NA 5-Feb-09 7-Mar-09 7-Mar-09 14-Mar-09 NA 30-Mar-09 11-Apr-09 Planned Post LS No No NA NA 1-Jul-09 8-Jul-09 8-Jul-09 12-Jul-09 NA 14-Jul-09 13-Aug-09 Marib Travel Revised 14 Movement to new office building Goods 20-Jul-09 24-Jul-09 24-Jul-09 28-Jul-09 NA 30-Jul-09 4,750 0 4,750 US$ 29-Aug-09 4,750 4,750 Completed &Tourism Actual No No NA NA 26-Jul-09 2-Aug-09 2-Aug-09 5-Aug-09 NA 6-Aug-09 16-Dec-09 Planned Procurement of Al uminuim Post LS No No NA NA 1-Oct-09 11-Oct-09 11-Oct-09 25-Oct-09 NA 28-Oct-09 12-Dec-09 Taj Sheba for Revised 15 Partition for the New Office Goods 15-Oct-09 25-Oct-09 25-Oct-09 8-Nov-09 NA 11-Nov-09 9,118 0 9,118 YR 26-Dec-09 3,885 3,885 Completed Alumanime Actual Building Post LS No No NA NA 13-Oct-09 21-Oct-09 21-Oct-09 25-Oct-09 NA 28-Oct-09 Second:- RMF Component P.P for RAP / Works oods 4[Page] Bank’s No No Objection No Objection Objection to Review Bank’s No from Bank for from Bank for Preparation Contract Bid Name, City, and Goods/ by Domestic Prequalifi Objection to Bid Bid Bid Contract Value Expenditure Contract Completion Expenditure Expenditure SL Package/ Method of Draft Evaluation of of Bid Award Evaulation Contract Phase II Contract Country of Description of Goods/ Works Works/ Bank Preferenc cation Bidding Invitation Closing Opening +Vartion Order incurred from Currenc of Contract incurred to incurred from Remarks No. Reference No. Selection Prequalificatio Prequalificatio Document Decision Report and Signed (Date) Commitments No. Contractor (incl. NCS (Prior/ e (yes/no) (yes/no) Document (Date) (Date) (Date) (US$) phase I y (Date) Date phase II n documents n Application (Date) (Date) Contract Zip Code if US) Post) (Date)** (Date)** (Date)** Award (Date)** Yemen Yemen P0117408: P085231: Yemen Yemen Additional Rural Access Financing Project-Phase for Rural II Cerdit No 4121 Access Project-Phase II Grant No H-543 First:- RAP Components Planned Construction of Maghrb Ans - Prior ICB No Yes 31-Mar-10 10-Apr-10 30-Apr-10 14-Jun-10 14-Jun-10 14-Jul-10 24-Jul-10 13-Aug-10 2-Aug-12 Manar A'ans Road Project Al-Amal Revised 1 IFB# 40/CW/12 Works Prior ICB No No NA NA 15-Apr-12 12-Apr-13 12-May-13 26-Jun-13 26-Jun-13 27-Oct-13 10-Nov-13 25-Nov-13 8,989,320 - 8,989,320 YR 40CW/ID 15-Nov-15 0 0 Ongoing (35.974km)In Dhamar Gov. Company Actual Prior ICB No No NA NA 13-May-12 9-Apr-13 24-Jun-13 18-Aug-13 18-Aug-13 19-Nov-13 5-Dec-13 22-Dec-13 A/12 Planned Construction of three sub- rural Prior ICB No No 1-Jun-13 16-Jun-13 16-Jul-13 30-Aug-13 30-Aug-13 29-Oct-13 12-Nov-13 27-Dec-13 17-Dec-15 Revised 2 IFB# 41/CW/13 road projects located in Al Works Prior ICB No No NA NA 1-Jan-14 16-Jan-14 31-Jan-14 17-Mar-14 17-Mar-14 1-May-14 8-May-14 23-May-14 - 14-Nov-15 0 Actual Baydha (35 km) Planned Construction of Hajdeh- Prior ICB No Yes 31-Mar-10 10-Apr-10 30-Apr-10 14-Jun-10 14-Jun-10 14-Jul-10 24-Jul-10 13-Aug-10 2-Aug-12 For ICB projects , World IFB# 42- Revised 3 Makhatah-Rasian-Alhaiajem Works Prior ICB No No 1-Apr-14 16-Apr-14 1-May-14 15-Jun-14 15-Jun-14 30-Jul-14 6-Aug-14 21-Aug-14 - 12-Feb-16 0 Bank’s SBD for small A/CW/13 Actual RR(34.3km) in Taiz Gov. works will be used Planned Construction of Alafyoush- Prior ICB No Yes 31-Mar-10 10-Apr-10 30-Apr-10 14-Jun-10 14-Jun-10 14-Jul-10 24-Jul-10 13-Aug-10 2-Aug-12 IFB# 42- Revised 4 Alkasimeya RR ( 26.3 km) in Ibb Works Prior ICB No No 1-Apr-14 16-Apr-14 1-May-14 15-Jun-14 15-Jun-14 30-Jul-14 6-Aug-14 21-Aug-14 - 12-Feb-16 0 B/CW/13 Actual Gov. Planned Construction of Alabediah Post NCB No No NA NA 1-Sep-13 16-Sep-13 1-Oct-13 15-Nov-13 15-Nov-13 14-Jan-14 28-Jan-14 27-Feb-14 21-Aug-15 Revised 5 IFB# 43/CW/12 District Center Road ( 20 km) in Works 1-Nov-13 16-Nov-13 1-Dec-13 15-Jan-14 15-Jan-14 16-Mar-14 30-Mar-14 29-Apr-14 - - 0 Actual Mareb Gov Planned Remaining and Additional Works Post NCB No No NA NA 15-Apr-12 NA 29-May-12 3-Jul-12 3-Jul-12 1-Sep-12 NA 1-Oct-12 25-Mar-14 Abdulazaq Al Letter of Acceptance Revised 6 IFB# 44/CW/13 for Orod – Souq Al Horiah Road Works Post NCB No No NA NA 15-May-12 NA 1-May-13 15-Jun-13 15-Jun-13 16-Oct-13 NA 15-Jan-14 2,492,103 0 2,492,103 US$ 10-Jan-15 Wadee Co has been issued Actual project Post NCB No No NA NA 13-May-12 NA 21-Jul-13 1-Sep-13 1-Sep-13 28-Nov-13 NA Planned Construction of Jablarrabwah- Post NCB No No NA NA 1-Sep-13 11-Sep-13 1-Oct-13 15-Nov-13 15-Nov-13 15-Dec-13 25-Dec-13 14-Jan-14 8-Jul-15 For NCB projects , Revised 7 IFB# 45/CW/12 Aldhanabah RR (8km) in Lahej Works Post NCB No No NA NA 6-Jan-14 21-Jan-14 5-Feb-14 22-Mar-14 22-Mar-14 21-May-14 4-Jun-14 4-Jul-14 - - 0 National SBD for works Actual Gov will be used Planned Procurement of photocopier for Post LS No No NA NA 27-Apr-10 04-May-10 18-May-10 18-May-10 02-Jun-10 NA 09-Jun-10 APEX YEMEN 09-Jul-10 Revised 8 IFB# 25 /G electronic archive for RAP's Goods 01-May-12 15-Jun-12 29-Jun-12 29-Jun-12 14-Jul-12 NA 21-Jul-12 8,750 - 8,750 US$ TRADING 19-Sep-12 8,750 8750 Completed Actual procurement department Post LS No No NA NA 21-Jul-12 24-Jul-12 06-Aug-12 06-Aug-12 30-Sep-12 NA 09-Oct-12 (Xerox) 14-Nov-12 Planned IFB# 26 /G Prior NCB No No 01-Feb-10 15-Feb-10 22-Feb-10 14-Mar-10 14-Mar-10 28-Apr-10 12-May-10 19-May-10 18-Jul-10 Procurement of 2 Cars for Revised 9 Goods Post LS 01-Sep-10 15-Sep-10 22-Sep-10 12-Oct-10 12-Oct-10 26-Nov-10 10-Dec-10 17-Dec-10 47,500 - 47,500 US$ AMTC 15-Feb-11 47,500 47,500 Completed RAPCMO Actual Post LS NA NA NA NA 20-Jul-10 28-Jul-10 28-Jul-10 09-Aug-10 NA 10-Aug-10 23-Aug-10 Natco Planned IFB# 27/G Post NCB No No 01-Jan-13 NA 11-Jan-13 15-Feb-13 15-Feb-13 16-Apr-13 NA 23-Apr-13 21-Aug-13 Procurement of IT equipment Information Revised 10 Goods 30-Apr-13 NA 14-May-13 181,145.72 - 181,146 US$ 10-Dec-13 0 0 95% delivered for supervision units of MPWH Technology Actual Post NCB No No 09-Feb-13 NA 22-Feb-13 31-Mar-13 31-Mar-13 22-Jun-13 NA 13-Jul-13 Com. LTD Planned IFB# 27-B/G Post LS No No 01-Jun-14 NA 08-Jun-14 22-Jun-14 22-Jun-14 22-Jul-14 NA 29-Jul-14 27-Sep-14 Procurement of addational IT Revised 11 Goods - - 0 equipment for MPWH Actual Planned IFB# 34/G Procurement of 2 Survey Post LS No No 01-Jan-14 NA 08-Jan-14 22-Jan-14 22-Jan-14 21-Feb-14 NA 28-Feb-14 29-Apr-14 Revised 12 Equipment (Total station) for Goods - - 0 Ongoing Actual RAP Planned IFB# 28 /G Prior LS No No 01-Aug-10 NA 08-Aug-10 22-Aug-10 22-Aug-10 21-Sep-10 NA 28-Sep-10 23-Oct-10 Procurement of Office Furniture Revised 13 Goods Post 8,836 - 8,836.0 US$ Ardh Himyar 8,606 8,606 Completed for New Staff of RAPCMO Actual Post LS No No NA NA NA NA 29-Jun-10 07-Jul-10 07-Jul-10 19-Jul-10 31-Jul-10 15-Apr-11 Planned IFB# 29 /G Procurement of IT equipment Post LS No No 01-Jun-11 NA 08-Jun-11 22-Jun-11 22-Jun-11 22-Jul-11 05-Aug-11 12-Aug-11 11-Oct-11 Revised 14 for Three Regional offices of Goods 26,590.95 - 26,590.95 US$ CEW 01-Jun-12 24,678 24,678 Completed Actual RAPCMO Post LS No No NA 05-Jan-11 26-Jan-11 26-Jan-11 19-Feb-11 NA 14-Jul-11 22-Nov-12 Planned IFB# 30 /G Procurement of Office Furniture Post LS No No 01-Jun-11 NA 08-Jun-11 22-Jun-11 22-Jun-11 22-Jul-11 NA 29-Jul-11 23-Aug-11 Revised 15 for Two Regional offices of Goods 01-Nov-13 NA 08-Nov-13 22-Nov-13 22-Nov-13 22-Dec-13 NA 29-Dec-13 - - 23-Jan-14 0 Actual RAPCMO Planned IFB# 31 /G Post LS No No 01-Jan-11 NA 08-Jan-11 22-Jan-11 22-Jan-11 06-Feb-11 NA 13-Feb-11 10-Mar-11 Procurement of RAP's Revised 16 Goods 5,507.09 - 5,507.09 YR Al Resalah St. 01-Jun-12 4,390 4,390 Completed Stationary for 2011 Actual Post LS No No NA NA NA NA 06-Oct-10 20-Oct-10 20-Oct-10 08-Dec-10 NA 13-Dec-10 29-Dec-12 Planned IFB# 32 /G Post LS No No 01-Jan-12 NA 08-Jan-12 22-Jan-12 22-Jan-12 06-Feb-12 NA 13-Feb-12 09-Mar-12 Procurement of RAP's Al Maktaba offiec Revised 17 Goods 01-Nov-13 NA 08-Nov-13 22-Nov-13 22-Nov-13 07-Dec-13 NA 14-Dec-13 9,978 - 9,978 US$ IFB#32G/13 12-Feb-14 0 0 Ongoing Stationary for 2013 and 2014 supplies Actual Post LS No No NA 10-Nov-13 27-Nov-13 27-Nov-13 22-Dec-13 NA 02-Jan-14 03-Mar-14 Planned IFB# 33 /G Post LS No No 01-Jan-13 NA 08-Jan-13 22-Jan-13 22-Jan-13 06-Feb-13 NA 13-Feb-13 10-Mar-13 Procurement of RAP's Revised 18 Goods 01-Nov-14 NA 08-Nov-14 22-Nov-14 22-Nov-14 07-Dec-14 NA 14-Dec-14 - - 08-Jan-15 0 Stationary for 2015 Actual Planned IFB# 34 /G Post LS No No 01-Feb-14 NA 08-Feb-14 22-Feb-14 22-Feb-14 09-Mar-14 NA 16-Mar-14 15-May-14 Procurement of Al uminuim Revised 19 Goods - - 0 Partition Actual RAP Original Allocation in Additional Financing to Credit No 4121 Category Category Description 1(a) Goods Under Parts A and B 2(a) Civil Works Under Parts A P.P for RAP / Works oods 5[Page] Procurement Plan for Consultant Services #REF! In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. No Objection No Objection No No Name, City, RFP Final No by the Bank by the Bank Review Type of Advertising TOR/Shortl Objection Objection Proposal Contract and Country Package/ Draft to be Objection to the (Technical/ Contract Expenditure Phase II Contract Services Expenses Expenditure SL by Bank Consultant Method of for Short ist to be from Bank from Bank RFP Issued Submission Value+ Contract of Reference Description of Services forwarded from Bank Technical #Combined/ Signed incurred Commitment Currenc Completion Incurred to incurred from Remarks No. (Prior/ (Firm/ Selection listing Finalised for for Final (Date) Deadline Addendum No. Contractor No. to the Bank for TOR Evaluation Draft Contract/ (Date) from phase I s y( US$) (Date) Date(US$) phase II Post) Individual) (Date) (Date) Shortlist RFP (Date) (US$) (incl. Zip (Date) (Date)** Report Final Contract) (Date)** (Date)** Code if US) (Date)** (Date)** Yemen P085231: Yemen Rural Access Project-Phase II Cerdit No 4121 First:- RAP Components Planned Prior QCBS NA 1-Jan-06 15-Jan-06 30-Jan-06 5-May-08 1-Mar-07 Training for RAP &PWH in Project Management & Revised 1 Firm 72,944 - 72,944 € CS116/08 ITC- ILO 71,404 71,404 Completed Contract Administration Actual RFP#116-08 CQ 29-Apr-08 28-Jun-08 15-Jul-08 15-Aug-08 31-Aug-08 28-Nov-08 NA 18-Feb-09 12-Mar-09 1-Jul-09 Planned Post NA NA NA NA NA NA NA NA NA NA 1-Aug-06 31-Dec-08 Abdul Hakim Revised 2 Finacial Audits for RAP Individual 9,000 4,500 4,500 US$ CS102/05 15,499 10,999 Completed Al Eryani Actual RFP#102-05 QCBS 28-Aug-05 20-Jul-08 Planned Post NA NA NA NA NA NA NA NA NA NA 1-Aug-06 31-Dec-08 Revised 3 Finacial Audits for RAP Individual 6,500 - 6,500 US$ CS102A/08 KPMG 6,169 6,169 Completed RFP#102A- Actual QCBS 20-Jan-09 08 Planned Post NA NA NA NA NA NA NA NA NA NA 1-Aug-06 31-Dec-08 Revised 4 Finacial Audits for RAP Individual 5,200 5,200 US$ CS102A-09 Ali Al Haj 2,600 2,600 Completed RFP#102A- Actual QCBS 3-Feb-09 09 Planned Post 1-Nov-06 15-Nov-06 1-Dec-06 NA NA 20-Dec-06 15-Sep-06 K. Revised 5 Preparation of ICR Individual CQ 6,250 6,250 US$ CS111/06 4,375 4,375 Completed Arunachalam Actual RFP#111-06 NA 15-Sep-06 1-Oct-06 NA 3-Dec-06 9-Dec-06 15-Dec-06 NA NA 23-Dec-06 Planned Post 1-Jun-07 1-Jun-07 10-Jun-07 15-Jun-07 5-Jul-07 NA NA 15-Jul-07 15-Sep-07 Nasra Salem Revised 6 Preparation of Mid Term Review for Phase II Individual 5,500 5,500 US$ CS115/08 5,500 5,500 Completed Daer Actual RFP#115-06 CQ NA 1-Jan-08 9-Jul-08 NA 13-Jul-08 23-Jul-08 23-Jul-08 NA NA 29-Jul-08 27-Oct-08 Planned Technical Training for RAP Staff & contractors & Prior 1-Jan-07 1-Jan-07 10-Jan-07 15-Jan-07 1-Mar-07 10-Apr-07 5-May-07 25-May-07 20-Jul-07 Revised 7 RFP#117-07 consultants on Supervision of Works Contracts & Firm QCBS 253,792.36 253,792 € CS116/08 ICT+ Rayman 1-Dec-12 63,448 63,448 Ongoing Actual Claim Settlement (Capacity Buillding) 23-Apr-07 1-Nov-07 26-Nov-07 19-Dec-07 8-Mar-08 11-Mar-08 6-May-08 15-Aug-08 6-Dec-08 31-May-09 Planned Prior 1-Jun-06 1-Jun-06 10-Jun-06 15-Jul-06 1-Aug-06 5-Sep-06 30-Sep-06 20-Oct-06 31-Dec-08 Revised 8 Technical Audits of RAP II Firm QCBS 175,753 175,753 £ WSP 105,452 105,452 Ongoing Actual 12-Oct-06 26-Nov-07 NA NA 11-Dec-07 6-Jan-08 20-Feb-08 NA 22-Oct-08 13-Jan-09 Planned NA 1-May-06 10-May-06 10-May-06 15-May-06 1-Jul-06 10-Aug-06 5-Sep-06 1-Nov-06 Revised 9 RFP#112-06 Construction of Industry Review Firm QCBS 14-Dec-08 154,641 154,641 € CS112/08 ICT+ Rayman 86,599 86,599 Ongoing Actual Prior 16-Jul-08 15-Sep-08 1-Oct-08 10-Oct-08 27-Oct-08 24-Dec-08 18-Feb-09 4-Apr-09 12-Sep-09 Planned Prior 15-Jul-02 15-Oct-02 15-Nov-02 NA NA 20-Feb-03 Engineering Revised 10 RFP#8/02 Design and construction Super.for Seham Bora'a Firm QCBS NA NA NA NA NA NA NA 122,763 112,120 10,643 US$ CS8/03 122,565 10,445 Completed Group Actual Prior NA 1-Oct-02 15-Oct-02 17-Oct-02 29-Oct-02 14-Dec-02 5-Feb-03 1-Apr-03 12-Apr-03 26-Nov-07 Planned Prior 1-May-01 1-Feb-03 15-Mar-03 1-May-03 Support and Technical Assistance for Local TEAM Revised 11 RFP#13/02 Firm QCBS 80,000 69,400 10,600 US$ CS17 /03 79,996 10,596 Completed Consultants International Actual Prior NA NA 24-Dec-02 22-Jan-03 15-Jul-03 6-Aug-03 NA 29-Oct-03 18-Nov-03 30-Jan-07 Planned Prior 15-May-01 1-Jan-03 2-Feb-03 20-Apr-03 Techniplan Revised 12 RFP#15/02 Sectoral Environmental Study Firm QCBS 108,475 68,339 40,136 US$ CS13/03 84,331 15,992 Completed Spa. Actual Prior NA NA 2-Feb-03 5-Feb-03 22-Feb-03 7-Apr-03 14-May-03 2-Jun-03 11-Jun-03 14-Mar-09 Planned Post NA 15-Apr-03 1-May-03 15-May-03 CAT Revised 13 Construction of Web Site for RAP Firm LC 5,183.06 2,788.00 2,395 US$ CS16/03 Computer 5,183 2,395 Completed Actual Post NA NA NA NA NA NA 21-Apr-03 NA NA NA 24-May-03 Grafics 30-Dec-07 Planned Prior NA 15-Aug-03 15-Sep-03 15-Nov-03 Design and Constr Super of Al Bayhan Al Harajh Al Rayman Revised 14 RP#24/03 Firm QCBS 199,016.70 171,428.70 27,588 US$ CS38/04 197,053 25,624 Completed Kura' RP Engineering Actual Prior NA 20-Sep-03 30-Sep-03 10-Oct-03 15-Oct-03 15-Nov-03 20-Apr-04 20-Apr-04 3-May-04 15-Apr-08 Planned Prior NA 15-Aug-03 15-Sep-03 15-Nov-03 Al Masar Eng Revised 15 RP#25/03 Design and Constr Super of 4 Rural Roads in Abyan Firm QCBS 199,123.14 129,566.18 69,557 US$ CS39/04 145,646 16,080 Completed Office Actual Prior 20-Sep-03 28-Sep-03 10-Oct-03 15-Oct-03 15-Nov-03 NA NA 19-Apr-04 31-Dec-08 Planned Prior 1-May-01 15-Jan-04 1-Mar-04 5-Jun-04 Terminated&Fin ARCADIS Revised 16 RP#30/04 Design for 13 Roads in Sana'a Amran for Phase II Firm QCBS 652,000 130,400 521,600 US$ CS300/05 469,440 339,040 al payment has &RENARDET Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 10-May-04 11-Jul-04 31-Aug-05 3-Sep-05 been issued Planned Prior 1-May-01 15-Jan-04 3-Mar-04 15-Jul-04 Consulting Revised 17 RP#31/04 Design for12 Roads in Taiz and Ibb for Phase II Firm QCBS 838,526.50 545,114.24 293,412 US$ CS310/05 Engineering 826,386 281,272 Completed Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 10-May-04 11-Jul-04 31-Aug-05 3-Sep-05 Center 25-Aug-10 Planned Prior 1-May-01 1-Apr-04 15-May-04 1-Sep-04 Arab Design for 9 Roads in Al Hudiedah Al Mahweet and Revised 18 RP#32/04 Firm QCBS 419,210 225,129 194,081 US$ CS320/05 Consulting 416,550 191,421 Completed Hajah for Phase II Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 10-May-04 11-Jul-04 31-Aug-05 3-Sep-05 Engineers MB 1-Jul-09 Planned Prior 1-May-01 16-Jan-04 24-Feb-04 1-Apr-04 Arab Tech Design for 11 Roads in Al Biedah, Ibb and Dhamar Revised 19 RP#34/04 Firm QCBS 554,304.74 115,818.00 438,487 US$ CS340/05 Jardanah 554,305 438,487 Completed for Phase II Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 10-May-04 11-Jul-04 31-Aug-05 3-Sep-05 &…………. 18-Aug-10 Planned Prior 1-May-01 16-Jan-04 24-Feb-04 1-Apr-04 Dar Al Omran Design for 8 Roads in Al Mahwit and Hajah for Revised 20 RP#35/04 Firm QCBS 497,080 109,511 387,569 US$ CS350/05 and Regional 504,760 395,249 Completed Phase II Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 10-May-04 11-Jul-04 31-Aug-05 3-Sep-05 Reef 4-Jan-10 Planned Prior 1-May-01 16-Jan-04 24-Feb-04 1-Apr-04 Al Amedah Consultants Revised 21 RP#36/04 Design for 4 Roads in Lahj and Ad Dale' for Phase II Firm QCBS 127,029 109,596 17,433 US$ CS360/05 126,956 17,360 Completed and Shiban Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 3-May-04 23-Jun-04 31-Aug-05 3-Sep-05 Engineering 15-Jul-07 Planned Prior 1-May-01 16-Jan-04 24-Apr-04 1-Apr-04 Terminated but Design for 5 Roads in Hadramout and Abyan for Rayman Final payment Revised 22 RP#37/04 Firm QCBS 201,189.11 53,190.77 147,998 US$ CS370/05 175,318 122,127 Phase II Engineering has not been Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 3-May-04 23-Jun-04 31-Aug-05 3-Sep-05 issued yet Planned Prior 1-May-01 16-Jan-04 24-Apr-04 1-Apr-04 Shiba 25-Dec-00 Design for 6 Roads in Sadah, Al Jouf and Marib for Revised 23 RP#38/04 Firm QCBS 260,937.70 93,070.48 167,867 US$ CS380/05 Engineering 279,037 185,967 Completed Phase II Actual Prior 1-Jan-04 9-Mar-04 10-Mar-04 10-Mar-04 3-May-04 23-Jun-04 31-Aug-05 3-Sep-05 Services 25-Jan-09 Planned Post NA 1-Apr-04 20-Apr-04 20-May-04 30-Apr-06 Construction Supervision for Al Udien Muthykhirah Radman Al Revised 24 RFP#56/04 Individual CQ 65,520 58,968 6,552 US$ CS41/04 65,520 6,552 Completed RE Kubati Actual Post NA 10-Mar-04 14-Mar-04 NA 14-Mar-04 18-Apr-04 9-May-04 29-May-04 4-Feb-07 Planned Post NA 1-Dec-05 10-Dec-05 1-Jan-06 Computer 30-Oct-07 Revised 25 RFP#28/04 Installation of MIS Firm SSS 10,000 8,000 2,000 US$ CS42/04 Engineering 8,000 0 Ongoing Actual Post 10-Dec-04 16-Dec-04 24-Dec-04 NA NA 24-May-04 World Planned Post Individual 15-Jul-02 20-Jun-04 25-Jun-04 29-Jun-04 31-Jul-06 Construction Supervision for Akamat Al Agoud Revised 26 RFP#59/04 CQ 28,800 17,280 11,520 US$ CS44/04 Adel Al Namir 28,800 11,520 Completed Muthykhirah- R E Actual Post NA 15-Jun-04 21-Jun-04 23-Jun-04 NA NA 26-Jun-04 30-Jun-04 NA NA 4-Jul-04 2-Mar-09 Planned Post Individual 15-Jul-02 20-Jun-04 25-Jun-04 29-Jun-04 31-Mar-06 Construction Supervision for Akamat Al Agoud Mahmoud Ali Revised 27 RFP#60/04 CQ 49,450 44,393 5,058 US$ CS45/04 49,325 4,933 Completed Muthykhirah- Surveyor Qasim Actual Post NA 15-Jun-04 21-Jun-04 23-Jun-04 NA NA 26-Jun-04 30-Jun-04 NA NA 4-Jul-04 5-Aug-07 Planned Post Individual 15-Jul-02 20-Jun-04 25-Jun-04 29-Jun-04 30-Apr-06 Hassan Revised 28 RFP#67/04 Construction Supervision of Jabal Ad Dar RE CQ 42,950.50 38,655.32 4,295 US$ CS67/04 38,655 0 Completed Mansour Actual Post NA 7-Aug-04 11-Aug-04 14-Aug-04 NA NA 9-Oct-04 NA NA 1-Dec-04 6-Dec-06 P.P for RAP/ Consultans 6 Procurement Plan for Consultant Services #REF! In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. No Objection No Objection No No Name, City, RFP Final No by the Bank by the Bank Review Type of Advertising TOR/Shortl Objection Objection Proposal Contract and Country Package/ Draft to be Objection to the (Technical/ Contract Expenditure Phase II Contract Services Expenses Expenditure SL by Bank Consultant Method of for Short ist to be from Bank from Bank RFP Issued Submission Value+ Contract of Reference Description of Services forwarded from Bank Technical #Combined/ Signed incurred Commitment Currenc Completion Incurred to incurred from Remarks No. (Prior/ (Firm/ Selection listing Finalised for for Final (Date) Deadline Addendum No. Contractor No. to the Bank for TOR Evaluation Draft Contract/ (Date) from phase I s y( US$) (Date) Date(US$) phase II Post) Individual) (Date) (Date) Shortlist RFP (Date) (US$) (incl. Zip (Date) (Date)** Report Final Contract) (Date)** (Date)** Code if US) (Date)** (Date)** Planned Post Individual 15-Jul-02 20-Jun-04 25-Jun-04 29-Jun-04 30-Apr-06 Yemen P085231: Yemen Rural Access Project-Phase II Cerdit No 4121 Abdul Hakim Revised 29 RFP#68/04 Construction Supervision of Jabal Ad Dar Surveyor CQ 43,915.50 39,523.95 4,392 US$ CS48/04 39,524 0 Completed Al Madhajee Actual Post NA 7-Aug-04 11-Aug-04 14-Aug-04 NA NA 18-Aug-04 NA NA NA 9-Sep-04 6-Aug-06 Planned Post 15-Jul-02 20-Jun-04 25-Jun-04 29-Jun-04 30-Aug-06 Construction Supervision of An Nadirah and Khawal Ahmed Al Revised 30 RFP#70/04 Individual CQ 47,300 44,903 2,397 US$ CS49/05 46,334 1,431 Completed Surveyor Thowaily Actual Post NA 7-Aug-04 11-Aug-04 14-Aug-04 NA NA 18-Aug-04 NA NA NA 20-Sep-04 4-Dec-08 Planned Post 15-Jul-02 15-Sep-04 15-Oct-04 20-Nov-04 30-Jun-07 Abdul Hakim Revised 31 RFP#71/04 Selection of Resident Engineer for Orud+Al Dhabab Individual CQ 59,280 38,134 21,146 US$ CS71/05 57,971 19,837 Completed Al Asbahi Actual Post NA 1-Oct-04 5-Oct-04 NA 28-Oct-04 19-Feb-05 NA NA NA 9-Mar-05 1-Oct-09 Planned Post 15-Jul-02 15-Sep-04 15-Oct-04 20-Nov-04 30-Oct-07 Selection of Surveyor Engineer for Orud+ Al Mohammed Revised 32 RFP#72/04 Individual CQ 70,000 34,984 35,016 US$ CS72/05 69,998 35,015 Completed Dhabab Al Hada Actual Post NA 1-Oct-04 5-Oct-04 NA 28-Oct-04 19-Feb-05 NA NA NA 9-Mar-05 6-Nov-08 Planned Post 15-Jul-02 15-Sep-04 15-Oct-04 20-Nov-04 30-Mar-07 Selection of Resident Engineer for Al Madn Al Mohammed Revised 33 RFP#73/04 Individual CQ 48,780 34,004 14,776 US$ CS73/05 48,131 14,127 Completed Mawqer Al Ahsab Actual Post NA 1-Oct-04 5-Oct-04 NA 15-Oct-04 19-Feb-05 NA NA NA 9-Mar-05 1-May-09 Planned Post 15-Jul-02 15-Sep-04 15-Oct-04 20-Nov-04 30-Mar-07 Selection of Surveyor Engineer for Al Madn Al Mohammed Revised 34 RFP#74/04 Individual CQ 43,200 30,115 13,085 US$ CS74/05 42,626 12,511 Completed Mawqer Mahfood Actual Post NA 1-Oct-04 5-Oct-04 NA 15-Oct-04 19-Feb-05 NA NA NA 9-Mar-05 16-Dec-08 Planned Prior 15-Jul-02 15-Mar-05 15-Apr-05 15-Nov-05 Engineering 30-Jul-08 Construction Supervision of Al Mesqah Al Haqlain Revised 35 RFP#77/04 Firm QCBS 284,026 99,445 184,581 US$ CS77/05 Bureau for 258,760 159,315 Completed and Alkadan Malhan Actual Prior 20-Mar-05 11-Apr-05 26-Apr-05 26-Apr-05 30-Apr-05 7-Jun-05 NA 17-Feb-06 18-Feb-06 Studies 26-Jan-09 Planned Post NA 1-Sep-05 15-Oct-05 20-Dec-05 Al Broog 30-Mar-08 Bureau Revised 36 RFP#99/05 Design of 4 RR in Taiz Under MPWH Financing Firm QCBS 91,640 31,088 60,552 US$ CS99/05 76,974 45,886 Terminated Consultant Actual Post 3-Nov-05 4-Nov-05 11-Aug-05 8-Nov-05 20-Aug-05 17-Oct-05 NA NA 22-Jan-06 Engineering Planned Post NA 15-Apr-05 25-Apr-05 10-May-05 10-Jul-06 Selection of Resident Engineer for An Nadirah Damt Revised 37 RFP#101/05 Individual CQ 35,750 32,175 3,575 US$ CS101/05 Fadhel Abbas 35,750 3,575 Completed and Khawal Ash Shair RP Actual Post NA 12-Apr-05 15-Apr-05 NA 17-Apr-05 20-Apr-05 NA NA NA 6-Jul-05 12-Apr-07 Planned Prior NA 15-Dec-05 30-Jan-06 15-Apr-06 7-Apr-08 Construction Supervision for Maswar and Kuhlan Engineering Revised 38 RFP#105-06 Firm QCBS 207,306 207,306 US$ CS105/06 179,384 179,384 Completed RR Group Actual Prior 15-Dec-05 21-Dec-05 4-Jan-06 8-Jan-06 7-Mar-06 25-Apr-06 24-Aug-06 8-Nov-06 16-Feb-09 Planned Post NA 15-Jan-09 30-Jan-09 15-Feb-09 30-Mar-09 Nasra Salem Revised 39 RFP#106-06 Preparation of Manual of Procedures for RAPCMO Individual SSS 7,250 7,250 US$ CS106/08 7,250 7,250 Completed Daer Actual Post NA 15-Dec-08 30-Dec-08 NA 27-Jan-09 1-Feb-09 8-Feb-09 NA NA 24-Feb-09 13-Jul-09 Planned Prior NA 15-May-06 20-Jun-06 5-Aug-06 Shiba 30-Jul-08 Revised 40 RFP#107-06 Construction Supervision of Assadah Ar Rada`ai RR Firm QCBS 217,883 217,883 US$ CS107/06 Engineering 185,967 185,967 Completed Actual Prior 1-Apr-06 2-May-06 12-May-06 16-May-06 20-May-06 27-Jun-06 20-Jul-06 24-Aug-06 29-Oct-06 Services 12-Oct-09 Planned Post 15-Jul-02 30-Apr-06 20-May-06 15-Jun-06 31-Jul-08 Review of Detailed Desings for Phase II Road Eng,Yahya Al Revised 41 RFP#66-06 Individual CQ 15,556 15,556 US$ CS 66A/06 13,322 13,322 Completed Projects Ja`adi Actual Post NA 2-May-06 18-May-06 9-Jun-06 18-Jun-06 NA NA NA 10-Jul-06 9-Jan-07 Planned Post 15-Jul-02 30-Apr-06 20-May-06 15-Jun-06 31-Jul-08 Review of Detailed Desings for Phase II Road Hamzah Al Revised 42 RFP#66-06 Individual CQ 17,516 17,516 US$ CS 66B/06 17,768 17,768 Completed Projects Ashwal Actual Post NA 2-May-06 18-May-06 9-Jun-06 18-Jun-06 NA NA NA 10-Jul-06 1-Mar-09 Planned Post 15-Jul-02 30-Apr-06 20-May-06 15-Jun-06 31-Jul-08 Review of Feasibility Studies (Environmental and Khalid Al Revised 43 RFP#66-06 Individual CQ 9,240 9,240 US$ CS 66C/06 12,380 12,380 Completed Social ) for RAP II Road Projects Subai Actual Post NA 2-May-06 18-May-06 9-Jun-06 18-Jun-06 NA NA NA 10-Jul-06 11-Jun-07 Planned Post 15-Jul-02 30-Apr-06 20-May-06 15-Jun-06 30-Mar-07 Review of Feasibility Studies (Environmental and Abdul Razak Revised 44 RFP#66-06 Individual CQ 9,240 9,240 US$ CS 66D/06 9,240 9,240 Completed Social ) for RAP II Road Projects Badi Actual Post NA 2-May-06 18-May-06 9-Jun-06 18-Jun-06 NA NA NA 10-Jul-06 23-Oct-07 Planned Post NA 30-Jun-06 20-Jul-06 5-Aug-06 30-Mar-07 Abdul Naser Revised 45 RFP#108-06 Prepration of Socico- Economic indicaotor Study Individual LCSB 9,385 9,385 US$ CS 108/06 4,250 4,250 Completed Almowada' Actual Post 1-May-06 15-May-06 14-Jun-06 NA NA NA 4-Sep-06 7-Jul-09 Planned Post 15-Jul-02 30-Apr-06 15-Jun-06 31-Jul-08 Review of Detailed Desings for Phase II Road Revised 46 RFP#66-06 Individual CQ 9,384.90 9,385 US$ CS 66E/06 Adel Musleh 9,367 9,367 Completed Projects Actual Post NA 1-Sep-06 5-Oct-04 NA 15-Oct-04 NA NA NA 1-Oct-06 2-Nov-08 Planned Post 15-Jul-02 30-Apr-06 20-May-06 15-Jun-06 31-Jul-08 Review of Detailed Desings for Phase II Road Revised 47 RFP#66-06 Individual CQ 11,000 11,000 US$ CS 66F/06 Shoaib Faroq 10,671 10,671 Completed Projects Actual Post NA 1-Sep-06 5-Sep-06 NA 9-Sep-06 17-Oct-06 NA NA NA 3-Nov-06 7-Oct-07 Planned Post 1-Dec-06 25-Jan-07 5-Feb-07 1-Mar-07 30-Nov-07 Naser Hadi Revised 48 RFP#113-06 Resident Engineer for Orud and Aldhabab Individual LCSB 25,757.78 25,758 US$ CS113/07 25,758 25,758 Completed Naser Actual Post 20-Dec-06 26-Dec-06 24-Jan-07 31-Jan-07 NA 3-Mar-07 19-May-08 Planned Post 1-Dec-06 25-Jan-07 5-Feb-07 1-Mar-07 30-Nov-07 Engrineerig Revised 49 RFP#114-06 Preparation of Traffic Count for 8 Rural Roads Firm LCSB 14,800 14,800 US$ CS114/07 14,800 14,800 Completed Grpoup Actual Post 10-Jan-07 23-Jan-07 6-Feb-07 7-Feb-07 24-Feb-07 NA NA 6-Mar-07 7-Jan-07 Planned Post NA 1-Feb-07 6-Feb-07 12-Feb-07 11-Jun-07 Sultan Al Revised 50 RFP#125-07 Selection Legal Expert for PPP Study Individual SSS 2,000 2,000 US$ CS125/07 1,922 1,922 Completed Jradi Actual Post 15-Feb-07 1-Feb-07 9-Feb-07 10-Feb-07 NA NA NA 12-Feb-07 7-Oct-07 Planned Prior 1-Jul-09 15-Jul-09 21-Jul-09 30-Jul-09 NA NA 15-Aug-09 15-Jan-11 Construction Supervision for Akmat Hubish Anbyan RFP#126- Techno Revised 51 RFP#126-09 Prior Firm QCBS 113,294 113,294 US$ 1-Sep-12 66,843 66,843 Completed RR 09 Center Actual Prior 27-Jul-09 5-Sep-09 5-Sep-09 20-Oct-09 23-Feb-10 30-Apr-10 29-Jun-10 Planned Prior 27-Sep-09 17-Oct-09 27-Oct-09 10-Nov-09 14-Nov-09 29-Dec-09 27-Feb-10 13-Mar-10 12-Apr-10 1-Apr-12 Revised 52 RFP#127-09 supervision of 4 Roads projects in Hajjah Gov. Firm QCBS 1-Nov-10 15-Nov-10 19-Nov-10 3-Jan-11 4-Mar-11 18-Mar-11 17-Apr-11 6-Apr-13 Cancelled Actual 26-Aug-09 Cancelled Planned Prior NA 15-Nov-10 22-Nov-10 2-Dec-10 5-Dec-10 4-Jan-11 NA 3-Feb-11 10-Feb-11 10-Feb-12 RFP#127-A- Revised 53 Supervision of 3 Road Projects in Al Bayda Gov. Firm CQ 1-Apr-12 1-May-12 15-Jun-12 14-Aug-12 13-Sep-12 13-Oct-12 13-Oct-13 0 Cancelled 10 Actual 10-Jan-11 Planned Prior NA 15-Nov-10 NA 22-Nov-10 NA 25-Nov-10 25-Dec-10 NA NA 24-Jan-11 20-Nov-11 RFP#127-B- Supervision of 3 Road Projects (2 in Sana’a Gov. and Revised 54 Firm CQ 1-Apr-12 1-May-12 15-Jun-12 14-Aug-12 13-Sep-12 13-Oct-12 13-Oct-13 Cancelled 10 1 in Marib Gov) Actual 10-Jan-11 Planned Prior NA 15-Nov-10 NA 22-Nov-10 NA 25-Nov-10 25-Dec-10 NA NA 24-Jan-11 20-Nov-11 RFP#127-C- Supervision of 3 Road Projects (2 in Dhamr Gov. Revised 55 Firm CQ 1-Apr-12 1-May-12 15-Jun-12 14-Aug-12 13-Sep-12 13-Oct-12 13-Oct-13 0 Cancelled 10 and 1 in Ibb Gov) Actual 10-Jan-11 Planned Prior NA 15-Nov-10 NA 22-Nov-10 NA 25-Nov-10 25-Dec-10 NA NA 24-Jan-11 20-Nov-11 RFP#127-D- Revised 56 Supervision of 4 Roads projects in Hajjah Gov. Firm CQ 1-Apr-12 1-May-12 15-Jun-12 14-Aug-12 13-Sep-12 13-Oct-12 13-Oct-13 0 Cancelled 10 Actual 10-Jan-11 P.P for RAP/ Consultans 7 Procurement Plan for Consultant Services #REF! In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. No Objection No Objection No No Name, City, RFP Final No by the Bank by the Bank Review Type of Advertising TOR/Shortl Objection Objection Proposal Contract and Country Package/ Draft to be Objection to the (Technical/ Contract Expenditure Phase II Contract Services Expenses Expenditure SL by Bank Consultant Method of for Short ist to be from Bank from Bank RFP Issued Submission Value+ Contract of Reference Description of Services forwarded from Bank Technical #Combined/ Signed incurred Commitment Currenc Completion Incurred to incurred from Remarks No. (Prior/ (Firm/ Selection listing Finalised for for Final (Date) Deadline Addendum No. Contractor No. to the Bank for TOR Evaluation Draft Contract/ (Date) from phase I s y( US$) (Date) Date(US$) phase II Post) Individual) (Date) (Date) Shortlist RFP (Date) (US$) (incl. Zip (Date) (Date)** Report Final Contract) (Date)** (Date)** Code if US) (Date)** (Date)** Yemen Yemen P0117408: P085231: Yemen Yemen Additional Rural Access Financing Project-Phase for Rural II Cerdit No 4121 Access Project-Phase II Grant No H-543 First:- RAP Components Works Supervision for 3 sub-projects (i) ICB Planned Prior 1-Mar-12 21-Mar-12 28-Mar-12 4-Apr-12 11-Apr-12 26-May-12 25-Jun-12 25-Jul-12 24-Aug-12 14-Aug-14 Maghrb Ans - Manar A'ans Road Project Revised 1 RFP#130 (35.974km) in Dhamar Gov.IFB# 40/CW/12], (ii) Prior Firm QCBS 1-Mar-12 7-Jun-12 7-Jun-12 20-Nov-12 20-Dec-12 3-Feb-13 15-May-13 1-Nov-13 16-Nov-13 6-Nov-15 Actual NCB [IFB# 44/CW/13 and (iii) NCB IFB#38CW (b) Prior 28-Feb-12 1-Nov-12 9-Dec-12 27-Jan-13 19-Mar-13 24-Jun-13 12-Dec-15 /12] Jouzy Planned Prior 1-Mar-12 21-Mar-12 19-Jun-12 26-Jun-12 3-Jul-12 17-Aug-12 16-Sep-12 16-Oct-12 15-Nov-12 5-Nov-14 Design update & Works Supervision for Two sub Consulting Revised 2 RFP#131 Prior Firm QCBS 1-Mar-12 7-Jun-12 7-Jun-12 20-Nov-12 20-Dec-12 3-Feb-13 15-May-13 15-Oct-13 30-Oct-13 757,609 - - US$ 131-12 20-Oct-15 Ongoing Rural Road Projects in Taiz & Ibb (61km) 1 ICB Engineers in Actual 28-Feb-12 1-Nov-12 9-Dec-12 27-Jan-13 20-Mar-13 24-Jun-13 2-Dec-13 16-Dec-13 Association Planned Prior 1-Mar-12 21-Mar-12 19-Jun-12 26-Jun-12 3-Jul-12 17-Aug-12 16-Sep-12 16-Oct-12 15-Nov-12 Newtech 9-May-14 Design update & Works Supervision for Four sub- Consulting Revised 3 RFP#155 rural road projects located in Mareb and Al Prior Firm QCBS 1-Mar-12 7-Jun-12 7-Jun-12 20-Nov-12 20-Dec-12 3-Feb-13 15-May-13 15-Feb-14 2-Mar-14 809,902 - 809,902 US$ 130-12 24-Aug-15 - Group in Actual Baydha Gov. (55 km) 1 ICB and 1 NCB 28-Feb-12 1-Nov-12 9-Dec-12 27-Jan-13 20-Mar-13 24-Jun-13 association Planned Prior 1-Mar-12 21-Mar-12 3-Jul-12 17-Jul-12 24-Jul-12 7-Sep-12 6-Nov-12 30-Apr-14 Works Supervision for Jablarrabwah-Aldhanabah Revised 4 RFP#157 Post Firm QCBS 1-Mar-12 1-Dec-13 8-Dec-13 22-Dec-13 21-Jan-14 7-Mar-14 6-May-14 - - - 28-Oct-15 RR (8km) in Lahej Gov Actual 28-Feb-12 Planned Prior 1-May-12 22-May-12 1-Jun-12 15-Jun-12 30-Jun-12 14-Aug-12 28-Sep-12 18-Oct-12 2-Nov-12 26-Apr-14 Revised 5 RFP#132 (a) Preparation of Feasibility and Preliminary Design Prior Firm QCBS 15-Jun-12 15-Dec-12 25-Dec-12 12-Apr-13 12-May-13 26-Jun-13 15-Jan-14 14-Feb-14 16-Mar-14 11-Mar-15 Actual for First Package (330 km) 10-Jul-12 14-Feb-13 24-Jun-13 9-Jul-13 10-Sep-13 Planned Prior 1-May-12 22-May-12 1-Jun-12 15-Jun-12 15-Jul-12 29-Aug-12 28-Oct-12 27-Nov-12 27-Dec-12 20-Jun-14 Revised 6 RFP#132 (b) Preparation of Feasibility and Preliminary Design Prior Firm QCBS 15-Jun-12 15-Dec-12 25-Dec-12 12-Apr-13 12-May-13 26-Jun-13 20-Jan-14 19-Feb-14 21-Mar-14 16-Mar-15 Actual for Second Package (367 km) 10-Jul-12 14-Feb-13 24-Jun-13 9-Jul-13 10-Sep-13 Planned Prior 1-May-13 22-May-13 1-Jun-13 15-Jun-13 15-Jul-13 29-Aug-13 28-Oct-13 17-Nov-13 2-Dec-13 27-Nov-14 RFP#132 Preparation of Environmental Studies for First Revised 7 Prior Firm QCBS 12-Apr-13 1-Mar-14 16-Mar-14 30-Mar-14 29-Apr-14 13-Jun-14 12-Aug-14 1-Sep-14 16-Sep-14 11-Sep-15 (c1) Package (330 km) Actual 20-Apr-13 Planned Prior 1-May-13 22-May-13 1-Jun-13 15-Jun-13 15-Jul-13 29-Aug-13 28-Oct-13 17-Nov-13 2-Dec-13 27-Nov-14 RFP#132 Preparation of Environmental Studies for Second Revised 8 Prior Firm QCBS 12-Apr-13 1-Mar-14 16-Mar-14 30-Mar-14 29-Apr-14 13-Jun-14 12-Aug-14 1-Sep-14 16-Sep-14 11-Sep-15 (c2) Package (367 km) Actual 20-Apr-13 Planned Prior 1-Dec-13 22-Dec-13 1-Jan-14 15-Jan-14 30-Jan-14 16-Mar-14 30-Apr-14 20-May-14 4-Jun-14 30-May-15 Revised 9 RFP#132 (d) Preparation of Survey and Detailed Design for Prior Firm QCBS Cancelled Actual First Package (330 km) Planned Prior 1-Dec-13 22-Dec-13 1-Jan-14 15-Jan-14 30-Jan-14 16-Mar-14 30-Apr-14 20-May-14 4-Jun-14 30-May-15 Revised 10 RFP#132 (e) Preparation ofSurvey and Detailed Design for Prior Firm QCBS Cancelled Actual Second Package (367 km) Planned Value Engineering Study for Detailed Engineering Prior 1-May-12 22-May-12 1-Jun-12 29-May-12 15-Jun-12 30-Jun-12 14-Aug-12 28-Sep-12 18-Oct-12 2-Nov-12 26-Apr-14 Revised 11 RFP#132 (f) Designs of several Rural Roads with a total length Prior Firm QCBS Cancelled Actual of 697 Km 20-Apr-13 13-Oct-13 20-Dec-13 Planned Prior 15-Dec-09 14-Jan-10 24-Jan-10 7-Feb-10 22-Feb-10 8-Apr-10 23-May-10 12-Jun-10 27-Jun-10 25-Oct-10 Preparation of Sana’a Urban Transport Project- Revised 12 RFP#139-a Prior Firm QCBS 22-Aug-13 26-Sep-13 6-Oct-13 26-Jan-14 10-Feb-14 27-Mar-14 11-May-14 31-May-14 15-Jun-14 13-Oct-14 Traffic Control Center TCC Actual 24-Aug-13 12-Dec-13 Planned Prior 15-Dec-09 14-Jan-10 24-Jan-10 7-Feb-10 22-Feb-10 8-Apr-10 23-May-10 12-Jun-10 27-Jun-10 22-Jun-11 Preparation of Sana’a Urban Transport Project- Revised 13 RFP#139-b Prior Firm QCBS 22-Aug-13 30-Jan-14 6-Feb-14 20-Feb-14 7-Mar-14 21-Apr-14 5-Jun-14 25-Jun-14 10-Jul-14 5-Jul-15 Bus Rapid Transit System-BRTS Actual 24-Aug-13 Planned Prior QCBS 30-Jun-10 21-Jul-10 28-Jul-10 NA 29-Aug-10 13-Oct-10 NA NA 11-Jan-11 31-Dec-12 Revised 14 RFP#141 Technical Audit for RAP2AF ( 2 missions) Post Firm CQS 1-Jan-13 20-Jan-14 27-Jan-14 NA 3-Feb-14 20-Mar-14 NA NA 18-Jun-14 7-Jun-16 Actual 11-Dec-13 Planned Post NA 1-Dec-09 NA 11-Dec-09 NA NA NA NA NA 9-Feb-10 Yahya 4-Feb-11 Revised 15 RFP#143 Recruitment of Procurement Expert to assist RAP Post Individual IC NA 1-Oct-13 NA 11-Oct-13 NA NA NA NA NA 10-Dec-13 41,400 US$ 143-13 Mohammed 5-Dec-14 Ongoing Actual Post NA 1-Oct-13 NA 4-Oct-13 NA NA 4-Oct-13 27-Oct-13 NA NA 31-Oct-13 Ali Alshwal Planned Prepration of Socico- Economic indicaotor Study Prior NA 1-Jan-13 NA 11-Jan-13 11-Jan-13 NA 18-Jan-13 28-Jan-13 NA NA 7-Feb-13 8-Apr-13 Revised 16 RFP#148 [use of SSS only after clearance of IDA, otherwise Individual SSS NA 1-Aug-14 NA 11-Aug-14 11-Aug-14 NA 18-Aug-14 28-Aug-14 NA NA 7-Sep-14 6-Nov-14 Actual competitive selection] Planned Post NA 1-Jan-13 NA 11-Jan-13 NA 12-Mar-13 26-Apr-13 NA NA 26-May-13 25-Jul-13 Revised 17 RFP#149 Traffic Count Survey Firm LCS NA 2-Nov-14 NA 12-Nov-14 NA 11-Jan-15 25-Feb-15 NA NA 27-Mar-15 26-May-15 Actual Planned Post NA 1-May-13 NA 11-May-13 NA NA NA 10-Jul-13 24-Aug-13 Revised 18 RFP#151 Preparation of ICR Individual IC NA 2-Jun-15 NA 12-Jun-15 NA NA NA 11-Aug-15 25-Sep-15 Actual Planned Post NA NA NA NA NA NA NA NA NA 1-May-10 8-May-10 Al Raed for 30-Oct-13 Selection will Revised 19 RFP#152 Finacial Audits for 3 years Firm LCS 4,600 US$ Accounting 31-Oct-13 be conducted Dr. Ali by COCA Actual 1-Jan-11 Mohsen Planned Technical assistant for RAP in field of contract Prior 1-Nov-10 5-Jan-10 24-Jan-10 7-Feb-10 22-Feb-10 8-Apr-10 7-Jun-10 6-Aug-10 5-Sep-10 22-Jun-11 Revised 20 RFP#153 managemnet, claims and Dispute Procedures Firm SSS NA 12-Nov-14 12-Nov-14 26-Nov-14 3-Dec-14 17-Jan-15 18-Mar-15 17-May-15 16-Jun-15 14-Oct-15 Actual [ILO} Planned Post NA 30-Dec-12 NA 6-Jan-13 NA NA NA NA NA 7-Mar-13 3-Sep-13 Technical Assistance for MPWH in Supervision Revised 21 RFP#154 Individual IC NA 1-May-14 NA 8-May-14 NA NA NA NA NA 7-Jul-14 and Quality Control Actual Planned Post NA 30-Dec-12 NA 6-Jan-13 NA NA NA NA NA 7-Mar-13 3-Sep-13 Technical Assistance for MPWH in contact Revised 22 RFP#156 Individual IC NA 1-May-14 NA 8-May-14 NA NA NA NA NA 7-Jul-14 managemnt and claims processing Actual Planned Post NA 30-Dec-13 NA 6-Jan-14 NA NA NA NA NA 7-Mar-14 3-Sep-14 Revised 23 RFP#157 Recruitment of Enviromental Expert to assist RAP Individual IC 1-Mar-14 31-Mar-14 Actual 20-Dec-13 Planned Post NA 30-Dec-13 NA 6-Jan-14 NA NA NA NA NA 7-Mar-14 3-Sep-14 Revised 24 RFP#158 Recruitment of Social Expert to assist RAP Individual IC 1-Mar-14 31-Mar-14 Actual 20-Dec-13 P.P for RAP/ Consultans 8 Procurement Plan for Consultant Services #REF! In some contracts, one or more of these approvals may be ** Applicable in case of Bank's prior review contained in one Bank communication. No Objection No Objection No No Name, City, RFP Final No by the Bank by the Bank Review Type of Advertising TOR/Shortl Objection Objection Proposal Contract and Country Package/ Draft to be Objection to the (Technical/ Contract Expenditure Phase II Contract Services Expenses Expenditure SL by Bank Consultant Method of for Short ist to be from Bank from Bank RFP Issued Submission Value+ Contract of Reference Description of Services forwarded from Bank Technical #Combined/ Signed incurred Commitment Currenc Completion Incurred to incurred from Remarks No. (Prior/ (Firm/ Selection listing Finalised for for Final (Date) Deadline Addendum No. Contractor No. to the Bank for TOR Evaluation Draft Contract/ (Date) from phase I s y( US$) (Date) Date(US$) phase II Post) Individual) (Date) (Date) Shortlist RFP (Date) (US$) (incl. Zip (Date) (Date)** Report Final Contract) (Date)** (Date)** Code if US) (Date)** (Date)** Yemen P085231: Yemen Rural Access Project-Phase II Cerdit No 4121 RAP Original Allocation in Additional Financing to Credit No 4121 Category Category Description 3(a) Consultant Services under Part A and B P.P for RAP/ Consultans 9 Capacity Building Activities SL Expected Outcome/ Activity Description Estimated Duration Start Date Completion Date Comments No. Yemen P085231: Yemen Rural Access Project-Phase II Cerdit No 4121 First:- RAP Components Technical Training for RAP Staff & contractors & consultants on 1.5 Years 1 Supervision of Works Contracts & Claim Settlement (Capacity Buillding) 1-Jul-09 1-Mar-10 Training for RAP &PWH in Project Management & Contract 2 Weeks Administration( Procerment Training) 2 20-Jun-09 4-Jul-09 Yemen P0117408: Yemen Additional Financing for Rural Access Project-Phase II Cerdit No 4121 RAP and RMF Components 1st Group (2 Weeks) 15-Oct-13 29-Oct-13 1 Training Abroad for Senior MPWH's and RAP's and RMF's Staff 2nd Group (2 Weeks) 15-Oct-14 29-Oct-14 ######## ######## ########