Summarized Procurement Plan I. GENERAL Project information: Borrower: CCARDESA Project Name: Agricultural Productivity Program for Southern Africa Project ID No: P164486 Grant No.: Project Implementing Agency: CCARDESA Bank’s approval Date of the Procurement Plan: February 13, 2019 Date of General Procurement Notice: Period covered by this procurement plan: February 13, 2019 to September 2020 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Thresholds for Procurement Methods and Prior Review Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category (US$ millions) Open International Open National Request for Quotation (RfQ) Works ≥ 15 ≥7 < 0.2 ≤ 0.2 Goods, IT, and non-consulting ≥6 ≥1 < 0.1 ≤ 0.1 services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 3. Procurement Packages with Methods and Time Schedule 1 Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB (Works) NIL NIL NIL NIL NIL Summary of the NCB NIL NIL NIL NIL NIL (Works) Summary of the ICB (Goods) NIL NIL No NIL No major goods Summary of the NCB (Goods) NIL NIL NIL NIL NIL Summary of the RfQ (Goods 0.03 6 No Post Request for Quotations & Non-Consulting Services) Summary of the DC (Non- 0.2million 2 No Post consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines: Selection and Employment of Consultants: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ millions) Consulting Services Engineering and Construction Supervision Consultants (Firms) ≥4 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.5 NA. NA. 2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Guidelines: Selection and Employment of Consultants. 3. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank (Prior / Post) US$ million Summary of contracts NIL NIL NIL NIL through CQS Summary of contracts 0.2 million 26 Post Individual Consultants (mostly peer through IC reviewers) 3 PROCUREMENT Africa : Agricultural Productivity Program for Southern Africa - Angola & Lesotho PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2019-10-09 2019-10-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164486 GPN Date: Project Name: Agricultural Productivity Program for Southern Africa - Angola & Lesotho Loan / Credit No: IDA / 63580 Executing Agency(ies): Department of Agricultural Research WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening the Pending LS-DAR-136504-CW-RFQ / Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 13,333.00 0.00 Implementati 2020-04-01 2020-05-27 2020-11-23 Community seed bank Environment for Technology Quotations Envelope on Adoption Strengthening the LS-DAR-136510-CW-RFB / Pending Institutional and Enabling Single Stage - One Construction of tissue IDA / 63580 Post Request for Bids Open - National 166,667.00 0.00 Implementati 2020-02-28 2020-03-04 2020-04-15 2020-05-15 2020-06-19 2020-12-16 Environment for Technology Envelope laboratory Maseru on Adoption Strengthening the LS-DAR-136506-CW-RFB / Pending Institutional and Enabling Single Stage - One Construction of Mini culture IDA / 63580 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2020-02-28 2020-03-04 2020-04-15 2020-05-15 2020-06-19 2020-12-16 Environment for Technology Envelope laboratory in Mokhotlong on Adoption Strengthening the LS-DAR-136512-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Rehabilitation of DAR IDA / 63580 Post Open - National 12,500.00 0.00 Implementati 2020-03-04 2020-04-29 2020-10-26 Environment for Technology Quotations Envelope workshop on Adoption LS-DAR-136548-CW-RFQ / Strengthening the Pending Construction of DAR station Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 20,000.00 0.00 Implementati 2020-02-25 2020-04-21 2020-10-18 workshop using sheeting Environment for Technology Quotations Envelope on materials Adoption Strengthening the LS-DAR-136515-CW-RFB / Pending Institutional and Enabling Single Stage - One Rehabilitation of access IDA / 63580 Post Request for Bids Open - National 416,666.00 0.00 Implementati 2020-02-23 2020-02-28 2020-04-10 2020-05-10 2020-06-14 2020-12-11 Environment for Technology Envelope roads to DAR main station on Adoption LS-DAR-136551-CW-RFQ / Strengthening the Pending Rehabilitation of access Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 166,666.00 0.00 Implementati 2020-03-09 2020-05-04 2020-10-31 roads to DAR on station Environment for Technology Quotations Envelope on fields Adoption LS-DAR-136517-CW-RFB / Strengthening the Pending Construction of three storey Institutional and Enabling Single Stage - One IDA / 63580 Post Request for Bids Open - National 500,000.00 0.00 Implementati 2020-02-28 2020-03-04 2020-04-15 2020-05-15 2020-06-19 2020-12-16 building ( conference Environment for Technology Envelope on alls,laboratory and offices) Adoption LS-DAR-136550-CW-RFQ / Strengthening the Pending Construction of storage Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 50,000.00 0.00 Implementati 2020-03-08 2020-05-03 2020-10-30 facilities for field crops and Environment for Technology Quotations Envelope on horticultural crops Adoption Strengthening the LS-DAR-136549-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Rehabilitation of irrigation IDA / 63580 Post Open - National 62,500.00 0.00 Implementati 2020-03-07 2020-05-02 2020-10-29 Environment for Technology Quotations Envelope system on Adoption Page 1 Strengthening the LS-DAR-136531-CW-RFB / Pending Institutional and Enabling Single Stage - One Rehabilitation of existing IDA / 63580 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-02-20 2020-02-25 2020-04-07 2020-05-07 2020-06-11 2020-12-08 Environment for Technology Envelope structure into guest rooms on Adoption LS-DAR-136536-CW-RFQ / Strengthening the Pending Construction of Dormitories Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 83,333.00 0.00 Implementati 2020-03-01 2020-04-26 2020-10-23 with kitchenette for Environment for Technology Quotations Envelope on Researchers (4-8 ) Adoption Strengthening the LS-DAR-136540-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Construction of a 4 flat IDA / 63580 Post Open - National 100,000.00 0.00 Implementati 2020-03-02 2020-04-27 2020-10-24 Environment for Technology Quotations Envelope residence for field staff on Adoption Strengthening the LS-DAR-136542-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Wire fencing for DAR Main IDA / 63580 Post Open - National 83,333.00 0.00 Implementati 2020-02-25 2020-04-21 2020-10-18 Environment for Technology Quotations Envelope station on Adoption Strengthening the Pending LS-DAR-136543-CW-RFQ / Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 4,166.00 0.00 Implementati 2020-03-04 2020-04-29 2020-10-26 Guard house construction Environment for Technology Quotations Envelope on Adoption Strengthening the LS-DAR-136545-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Construction of shade and IDA / 63580 Post Open - National 66,666.00 0.00 Implementati 2020-03-04 2020-04-29 2020-10-26 Environment for Technology Quotations Envelope seed nursery on Adoption Strengthening the LS-DAR-136547-CW-RFQ / Pending Institutional and Enabling Request for Single Stage - One Renewable energy power IDA / 63580 Post Open - National 25,000.00 0.00 Implementati 2020-02-21 2020-04-17 2020-10-14 Environment for Technology Quotations Envelope structure on Adoption GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-DAR-136200-GO-RFQ / Pending Technology Generation and Request for Single Stage - One Packaging Materials for IDA / 63580 Post Open - National 3,000.00 0.00 Implementati 2019-11-05 2019-12-31 2020-06-28 Dissemination Quotations Envelope germplasm on LS-DAR-136204-GO-RFB / Pending Technology Generation and Single Stage - One Farm Inputs IDA / 63580 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-01-06 2020-01-11 2020-02-22 2020-03-23 2020-04-27 2020-05-15 Dissemination Envelope (Fertilizers,seed,pesticides) on LS-DAR-136206-GO-RFB / Pending Technology Generation and Single Stage - One Banking material for seed IDA / 63580 Post Request for Bids Open - National 10,000.00 0.00 Implementati 2019-11-04 2019-11-09 2019-12-21 2020-01-20 2020-02-24 2020-03-27 Dissemination Envelope packaging on Strengthening the Pending LS-DAR-136209-GO-RFB / Institutional and Enabling Single Stage - One IDA / 63580 Post Request for Bids Open - National 107,499.00 0.00 Implementati 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 Fencing Material Environment for Technology Envelope on Adoption Strengthening the Pending LS-DAR-136211-GO-RFQ / Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 93,749.00 0.00 Implementati 2019-11-09 2020-01-04 2020-02-07 Irrigation system equipment Environment for Technology Quotations Envelope on Adoption Page 2 LS-DAR-136212-GO-RFB / Strengthening the Pending Protected cultivation Institutional and Enabling Open - Single Stage - One IDA / 63580 Post Request for Bids 185,833.00 0.00 Implementati 2020-01-15 2020-01-20 2020-03-02 2020-04-01 2020-05-06 2020-11-02 structures (shade Environment for Technology International Envelope on screen,greenhouses) Adoption Strengthening the Pending LS-DAR-136215-GO-RFQ / Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 23,332.00 0.00 Implementati 2019-11-27 2020-01-22 2020-07-20 Refrigerators and freezers Environment for Technology Quotations Envelope on Adoption Strengthening the Pending LS-DAR-136218-GO-RFB / Institutional and Enabling Open - Single Stage - One IDA / 63580 Post Request for Bids 258,332.00 0.00 Implementati 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 2020-06-19 Cold storage facility Environment for Technology International Envelope on Adoption Strengthening the Pending LS-DAR-136219-GO-RFB / Institutional and Enabling Open - Single Stage - One IDA / 63580 Post Request for Bids 512,923.00 0.00 Implementati 2019-11-28 2019-12-03 2020-01-14 2020-02-13 2020-03-19 2020-04-30 Lab Equipment Environment for Technology International Envelope on Adoption Strengthening the Pending LS-DAR-136225-GO-RFQ / Institutional and Enabling Request for Open - Single Stage - One IDA / 63580 Post 1,500.00 0.00 Implementati 2019-12-04 2020-01-29 2020-02-28 Refinery Machine Environment for Technology Quotations International Envelope on Adoption Strengthening the Pending LS-DAR-136227-GO-RFQ / Institutional and Enabling Request for Open - Single Stage - One IDA / 63580 Post 12,500.00 0.00 Implementati 2019-11-26 2020-01-21 2020-02-21 Walk in seed dryer Environment for Technology Quotations International Envelope on Adoption Strengthening the LS-DAR-136228-GO-RFQ / Pending Institutional and Enabling Request for Open - Single Stage - One Tractors (2 *4x4 and 2 * IDA / 63580 Post 216,666.00 0.00 Implementati 2020-01-24 2020-01-29 2020-02-28 2020-03-29 2020-05-03 2020-07-31 Environment for Technology Quotations International Envelope 4x2) on Adoption LS-DAR-136230-GO-RFB / Strengthening the Pending Field machinery ( Planter Institutional and Enabling Open - Single Stage - One IDA / 63580 Post Request for Bids 295,541.00 0.00 Implementati 2019-11-29 2019-12-04 2020-01-15 2020-02-14 2020-03-20 2020-06-30 conventional and no Environment for Technology International Envelope on till,plough ,rotavator) Adoption Strengthening the LS-DAR-136238-GO-RFQ / Pending Institutional and Enabling Request for Open - Single Stage - One Water flow meters,soils IDA / 63580 Post 100,000.00 0.00 Implementati 2019-12-04 2020-01-29 2020-04-01 Environment for Technology Quotations International Envelope sensors,drones on Adoption Strengthening the LS-DAR-136245-GO-RFB / Pending Institutional and Enabling Single Stage - One Kitchen utensils IDA / 63580 Post Request for Bids Open - National 369,242.00 0.00 Implementati 2020-02-28 2020-03-04 2020-04-15 2020-05-15 2020-06-19 2020-09-18 Environment for Technology Envelope (chopper,food press etc) on Adoption Strengthening the Pending LS-DAR-136248-GO-RFQ / Institutional and Enabling Request for Open - Single Stage - One IDA / 63580 Post 27,083.00 0.00 Implementati 2020-02-29 2020-04-25 2020-07-31 Fork lift Environment for Technology Quotations International Envelope on Adoption Strengthening the LS-DAR-136252-GO-RFB / Pending Institutional and Enabling Single Stage - One Nursery Equipment ( IDA / 63580 Post Request for Bids Open - National 118,917.00 0.00 Implementati 2020-04-23 2020-04-28 2020-06-09 2020-07-09 2020-08-13 2021-02-09 Environment for Technology Envelope nursery established) on Adoption Strengthening the LS-DAR-136258-GO-RFQ / Pending Institutional and Enabling Request for Single Stage - One Data Analysis equipment IDA / 63580 Post Open - National 93,500.00 0.00 Implementati 2019-12-04 2020-01-29 2020-03-31 Environment for Technology Quotations Envelope and soft ware on Adoption Strengthening the Pending LS-DAR-136277-GO-RFQ / Institutional and Enabling Request for Single Stage - One IDA / 63580 Post Open - National 10,000.00 0.00 Implementati 2020-03-13 2020-05-29 Construction Material Environment for Technology Quotations Envelope on Adoption Page 3 LS-DAR-136424-GO-RFQ / Strengthening the Pending Development of a web based Institutional and Enabling Request for Open - Single Stage - One IDA / 63580 Post 45,000.00 0.00 Implementati 2019-12-04 2020-01-29 2020-02-28 Management information Environment for Technology Quotations International Envelope on System Adoption LS-DAR-136428-GO-RFB / Project management, Pending Motor vehicles ( 4*4 D/Cab Single Stage - One IDA / 63580 monitoring and evaluation, Post Request for Bids Open - National 558,333.00 0.00 Implementati 2019-12-08 2019-12-13 2020-01-24 2020-02-23 2020-03-29 2020-05-29 *6, 4*4 S/cab* 2, SUV's *2, Envelope and regional coordination on alf ton truck*1) LS-DAR-136437-GO-RFB / Project management, Pending Furniture ( guest Single Stage - One IDA / 63580 monitoring and evaluation, Post Request for Bids Open - National 683,333.00 0.00 Implementati 2019-12-10 2019-12-15 2020-01-26 2020-02-25 2020-03-31 2020-05-29 houses,conference halls and Envelope and regional coordination on office) LS-DAR-136440-GO-RFQ / Project management, Pending Office equipment ( Request for Single Stage - One IDA / 63580 monitoring and evaluation, Post Open - National 66,918.00 0.00 Implementati 2020-01-24 2020-03-20 2020-04-20 computers,printers,photocopier Quotations Envelope and regional coordination on s,laptops) Project management, Pending LS-DAR-136446-GO-RFQ / Request for Single Stage - One IDA / 63580 monitoring and evaluation, Post Open - National 16,666.00 0.00 Implementati 2020-01-28 2020-03-24 2020-04-23 Motor bikes Quotations Envelope and regional coordination on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-DAR-136453-CS-INDV / Individual Development of market value Technology Generation and Pending IDA / 63580 Post Consultant Open 50,000.00 0.00 2020-01-12 2020-02-14 2020-03-06 2020-04-10 2020-10-07 chains profile for the five Dissemination Implementation Selection crops. LS-DAR-136455-CS-INDV / Facilitator for workshop for farmers, extension workers Individual Technology Generation and Pending and scientists capacity to IDA / 63580 Post Consultant Open 3,000.00 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2020-12-01 Dissemination Implementation climate change through Selection gravity fed micro irrigation system LS-DAR-136457-CS-INDV / Conduct and supervise study Individual Technology Generation and Pending on farmers needs and IDA / 63580 Post Consultant Open 5,000.00 0.00 2020-01-23 2020-03-12 2020-04-02 2020-05-07 2020-07-31 Dissemination Implementation inventory of different Selection status/level of farmers. Page 4 LS-DAR-136458-CS-INDV / Implement work done under Individual Technology Generation and Pending FAO-TCP on development of IDA / 63580 Post Consultant Open 15,000.00 0.00 2020-01-23 2020-03-12 2020-04-02 2020-05-07 2020-11-03 Dissemination Implementation Research and Extension Selection policy Strengthening the LS-DAR-136459-CS-INDV / Individual Institutional and Enabling Pending Service provider for internet IDA / 63580 Post Consultant Open 8,333.00 0.00 2020-01-23 2020-03-12 2020-04-02 2020-05-07 2020-06-25 Environment for Technology Implementation and intranet ,WiFi,broadband Selection Adoption Strengthening the Individual LS-DAR-136460-CS-INDV / Institutional and Enabling Pending IDA / 63580 Post Consultant Open 20,000.00 0.00 2020-01-30 2020-03-19 2020-04-09 2020-05-14 2020-11-10 Research policy development Environment for Technology Implementation Selection Adoption Strengthening the Individual LS-DAR-136474-CS-INDV / Institutional and Enabling Pending IDA / 63580 Post Consultant Open 60,000.00 0.00 2019-11-28 2020-01-16 2020-02-06 2020-03-12 2020-05-08 Baseline study Consultancy Environment for Technology Implementation Selection Adoption Strengthening the LS-DAR-136475-CS-INDV / Individual Institutional and Enabling Pending Institutional Assessment IDA / 63580 Post Consultant Open 50,000.00 0.00 2020-01-12 2020-03-01 2020-03-22 2020-04-26 2020-10-23 Environment for Technology Implementation Consultancy Selection Adoption Strengthening the LS-DAR-136476-CS-INDV / Individual Institutional and Enabling Pending Development of Science Plan IDA / 63580 Post Consultant Open 50,000.00 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2020-12-01 Environment for Technology Implementation Consultancy Selection Adoption Strengthening the LS-DAR-136477-CS-INDV / Individual Institutional and Enabling Pending Seed policy harmonization IDA / 63580 Post Consultant Open 50,000.00 0.00 2019-11-29 2020-01-17 2020-02-07 2020-03-13 2020-09-09 Environment for Technology Implementation and regulation consultancy Selection Adoption Strengthening the LS-DAR-136478-CS-INDV / Individual Institutional and Enabling Pending Architectural designs and IDA / 63580 Post Consultant Open 25,000.00 0.00 2019-11-29 2020-01-17 2020-02-07 2020-03-13 2020-09-09 Environment for Technology Implementation supervision Selection Adoption Project management, Individual LS-DAR-136502-CS-INDV / Pending IDA / 63580 monitoring and evaluation, Post Consultant Open 30,000.00 0.00 2020-01-31 2020-03-20 2020-04-01 2020-05-06 2020-11-02 External Audit Services Implementation and regional coordination Selection Project management, Individual LS-DAR-136480-CS-INDV / Pending IDA / 63580 monitoring and evaluation, Post Consultant Open 197,890.00 0.00 2019-11-04 2019-12-23 2020-01-13 2020-02-03 2023-03-31 Project Manager Implementation and regional coordination Selection Project management, Individual LS-DAR-136492-CS-INDV / Pending IDA / 63580 monitoring and evaluation, Post Consultant Open 207,558.00 0.00 2019-11-08 2019-12-27 2020-01-17 2020-02-11 2023-04-08 Project Accountant Implementation and regional coordination Selection Project management, Individual LS-DAR-136493-CS-INDV / Pending IDA / 63580 monitoring and evaluation, Post Consultant Open 160,278.00 0.00 2019-10-04 2019-11-22 2019-12-13 2020-01-06 2023-03-31 Project Procurement Officer Implementation and regional coordination Selection LS-DAR-136495-CS-INDV / Project management, Individual Pending Project Monitoring and IDA / 63580 monitoring and evaluation, Post Consultant Open 118,624.00 0.00 2019-11-04 2019-12-23 2020-01-13 2020-02-03 2023-03-17 Implementation Evaluation Officer and regional coordination Selection LS-DAR-136497-CS-INDV / Project management, Individual Pending Technology Dissemination IDA / 63580 monitoring and evaluation, Post Consultant Open 118,624.00 0.00 2019-11-04 2019-12-23 2020-01-13 2020-02-17 2023-03-31 Implementation Officer and regional coordination Selection Project management, Individual LS-DAR-136501-CS-INDV / Pending IDA / 63580 monitoring and evaluation, Post Consultant Open 160,278.00 0.00 2019-11-04 2019-12-23 2020-01-13 2020-02-17 2023-03-31 Safeguard Officer Implementation and regional coordination Selection Page 5