Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan Original: February 16, 2017 3. Date of General Procurement Notice: June 16, 2017 4. Period covered by this procurement plan: The procurement period of project covered from year March 2017 to September 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (At or above US$) Works (including turnkey, supply & 5 installation of plant and equipment, and PPP) Goods, information technology and non- 1.5 consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As detailed in the Project Implementation Manual (PIM) dated April 25, 2017. 4. Reference to (if any) Project Operational/Procurement Manual: The Project Implementation Manual (PIM) dated April 25, 2017 issued by the Oromia Environment, Forest and Climate Change Authority (OEFCCA) 5. Any Other Special Procurement Arrangements: None. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packa Domestic Review Comments No. Cost ges Preference by Bank US$ million (yes/no) (Prior / Post) 1 Summary of the 2.5 1 No Prior ICB (Goods) 2 Summary of the 1 No Post 0.17 NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of Procurement Prior Review Threshold (At or above US$) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 0.15 2 Post number of contracts that will be let under QCBS 2 Summary of 1.3 30 Post number of contracts that will be let under other methods July 9, 2010 July 9, 2010 PROCUREMENT Ethiopia : Oromia National Regional State Forested Landscape Program PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2017-06-20 2019-12-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156475 GPN Date: 2017-06-16 Project Name: Oromia National Regional State Forested Landscape Program Loan / Credit No: / , TF / A4442 Executing Agency(ies): Ministry of Environment, Forest Development and Climate Change WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OFLP/ORCU/NCB/02/2017 / Installation of Forest Management Information Pending Single Stage - One System (equipments, TF / A4442 Enabling investments Post Request for Bids Open - National 150,000.00 0.00 Implementati 2017-09-15 2017-09-20 2017-11-01 2017-12-01 2018-01-05 2018-07-04 Envelope software and licenses, and on training of staff) ORCU/OEFCCA OFLP/ORCU/SH/09/2017 / Nursery site materials. (Handtools, Seed, barbed & Pending Request for Single Stage - One mesh wires, Polythene, TF / A4442 Enabling investments Post Limited 63,000.00 0.00 Implementati 2017-08-28 2017-10-23 2018-04-21 Quotations Envelope Nursery soils sand, local and on forest soil) For OEFCCA woredas & OFWE districts OFLP/ORCU/SH/10/2017 / Establishing of forest Pending Request for Single Stage - One community radio, and TF / A4442 Enabling investments Post Limited 22,000.00 0.00 Implementati 2017-11-29 2018-01-24 2018-07-23 Quotations Envelope production of printed, audio on and audio-vidual materials OFLP/ORCU/SH/01/2017 / Pending Supply of 18 Motorcycle 170- Single Stage - One TF / A4442 Enabling investments Post Request for Bids Open - National 77,148.00 0.00 Implementati 2017-06-28 2017-07-03 2017-08-14 2017-09-13 2017-10-18 2018-04-16 185 CC for OFLP woreda Envelope on coordinators OFLP/ORCU/SH/03/2017 / ICT equipment (LS) (3 Desktop computers, 55 Laptops, 58 CDMA, 58 Pending Request for Single Stage - One Internet keys, 58 Priners) TF / A4442 Enabling investments Post Limited 82,000.00 0.00 Implementati 2017-06-20 2017-08-15 2017-08-30 Quotations Envelope for ORCU, Lead facilitators, on Safeguards Coordinators, Woreda Coordinators and accountants OFLP/ORCU/SH/04/2017 / Printing & Marketing Pending Request for Single Stage - One materials for cook stoves TF / A4442 Enabling investments Post Limited 1,808.00 0.00 Implementati 2017-08-21 2017-10-16 2017-10-31 Quotations Envelope and biogas demonstration on (LS) for BoWME Page 1 OFLP/ORCU/SH/06/2017 / Pending Request for Single Stage - One Supply of MRV Software TF / A4442 Enabling investments Post Limited 48,800.00 0.00 Implementati 2017-10-28 2017-12-23 2018-01-22 Quotations Envelope and Licenses on OFLP/ORCU/ICB/01/2017 / Supply of 26 4WD Double Cabin Pick-up Vehicle (Diesel Engine, minimum of 130L fuel capacity) for Under Open - Single Stage - One Safegard & woreda TF / A4442 Enabling investments Prior Request for Bids 2,476,185.00 0.00 Implementati 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 International Envelope coordinators and Lead on Facilitators, and One 4WD Hard top Station Wagon Vehicle ( Hard Top Diesel, 8-10 seat) for ORCU OFLP/ORCU/NCB/01/2017 / Office Equipment & Furniture (computers, Tables, chair, filing cabinet, shelf Pending & etc) for 6 Safeguards Single Stage - One TF / A4442 Enabling investments Post Request for Bids Open - National 190,496.00 0.00 Implementati 2017-07-21 2017-07-26 2017-09-06 2017-10-06 2017-11-10 2017-12-25 coordinator & 38 Woreda Envelope on coordinators and 3 Lead Facilitators and 3 Accountants and ORCU's new staff OFLP/ORCU/SH/02/2017 / Stationery Materials (LS) Under for 6 Safegard coordinator & Request for Single Stage - One TF / A4442 Enabling investments Post Limited 17,493.00 0.00 Implementati 2017-07-15 2017-09-09 2017-10-09 38 Woreda coordinators and Quotations Envelope on 3 Lead Facilitators and 3 Accountants OFLP/ORCU/SH/05/2017 / Supply of MRV equipment ( 20 GPS, 20 Relascope, 20 measuring Tape 50m, 20 Pending measuring Tape 30m, 20 Request for Single Stage - One TF / A4442 Enabling investments Post Limited 14,700.00 0.00 Implementati 2018-03-28 2018-04-30 2018-05-15 metal Caliper, 20 fiber Quotations Envelope on diameter tape, 20 Suunto compass, 20 Suunto hypsometer, 20 Suunto clinometers and etc) OFLP/ORCU/SH/13/2018 / Pending ICT equipment (LS) ( 8 high Request for Single Stage - One TF / A4442 Enabling environment Post Limited 16,000.00 0.00 Implementati 2018-09-20 2018-10-18 2018-11-17 spec labtops) for ORCU and Quotations Envelope on Lead facilitators) OFLP/ORCU/SH/14/2018 / Procurement of nursery tools Pending Request for Single Stage - One (Handtools, barbed & mesh TF / A4442 Enabling investments Post Limited 50,000.00 0.00 Implementati 2018-09-20 2018-10-26 2018-11-25 Quotations Envelope wires) For OEFCCA woredas on & OFWE districts Under OFLP/ORCU/SSS/2/2018 / Request for Single Stage - One TF / A4442 Enabling investments Post Limited 20,000.00 0.00 Implementati 2018-09-20 2018-10-19 2018-11-18 Procurement of Tree Seeds Quotations Envelope on OFLP/ORCU/SH/17/2018 / Stationery Materials (LS) Pending for 6 Safegard coordinator & Request for Single Stage - One TF / A4442 Enabling investments Post Limited 25,265.00 0.00 Implementati 2018-09-20 2018-10-19 2018-11-18 38 Woreda coordinators and Quotations Envelope on 3 Lead Facilitators and 3 Accountants and ORCU Page 2 OFLP/ORCU/ICB/02/2017 / Supply of 21 4WD Double Cabin Pick-up Vehicle (Diesel Engine, minimum of 130L fuel capacity) for Under Open - Single Stage - One Safegard & woreda TF / A4442 Enabling investments Prior Request for Bids 2,600,000.00 0.00 Implementati 2018-09-05 2018-09-10 2018-10-22 2018-11-21 2018-12-25 2019-06-23 International Envelope coordinators and Lead on Facilitators, and One 4WD Hard top Station Wagon Vehicle ( Hard Top Diesel, 8-10 seat) for ORCU OFLP/ORCU/SH/05/2018 / Supply of MRV equipment (purchase of ploter and color Pending Request for Single Stage - One printer, digitizing table, TF / A4442 Enabling investments Post Limited 99,000.00 0.00 Implementati 2018-10-03 2018-11-28 2019-01-27 Quotations Envelope GPS, Stationary, Smart on Tablets, soft ware and licenses) OFLP/ORCU/SH/15/2018 / Under Request for Single Stage - One Procurement of Polyethene TF / A4442 Enabling environment Post Limited 36,000.00 0.00 Implementati 2018-09-20 2018-11-15 2018-12-15 Quotations Envelope tube on OFLP/ORCU/16/2018 / Procurement of Auodiovidual Request for Single Stage - One TF / A4442 Enabling environment Post Limited 5,233.00 7,593.93 Completed 2018-10-09 2018-11-13 2018-12-03 Materials for OFLP Quotations Envelope documentation OFLP/ORCU/SH/07/2017 / Forest fire fighting equipment. For PFM Request for Single Stage - One TF / A4442 Enabling investments Post Limited 3,185.00 0.00 Canceled 2017-10-25 2017-12-20 2018-02-03 woredas OEFCCA & OFWE Quotations Envelope (Fire protection suit, Rake, Shovel, Spade) OFLP/ORCU/DC/1/2018 / Supply of 21 4WD Double Cabin Pick-up Vehicle (Diesel Engine, minimum of 130L fuel capacity) for UN Agencies Safeguards & woreda TF / A4442 Enabling investments Prior Direct 2,600,000.00 733,838.06 Signed 2018-12-25 2018-12-30 2019-02-03 2019-08-02 (Direct) coordinators and Lead Facilitators, and One 4WD Hard top Station Wagon Vehicle ( Hard Top Diesel, 8- 10 seat) for ORCU Pending OFLP/ORCU/SH/2/2019 / Request for Single Stage - One TF / A4442 Enabling investments Post Limited 50,000.00 0.00 Implementati 2019-08-10 2019-09-12 2019-10-12 Procurement of tree seeds Quotations Envelope on OFLP/ORCU/SH/21/2019 / Pending Request for Single Stage - One Procurement of polyethene TF / A4442 Enabling investments Post Limited 70,000.00 0.00 Implementati 2019-08-15 2019-09-19 2020-03-17 Quotations Envelope tube for potting medium on OFLP/ORCU/SH/22/2019 / Procurement of basic nursery Pending Request for Single Stage - One tools (watering cans, TF / A4442 Enabling investments Post Limited 24,000.00 0.00 Implementati 2019-08-25 2019-10-03 2019-11-02 Quotations Envelope pruning shears, hoes, spade, on axe, etc) OFLP/ORCU/SH/19/2019 / Pending Request for Single Stage - One Procurement of Stationery TF / A4442 Enabling investments Post Limited 35,500.00 0.00 Implementati 2020-04-11 2020-05-15 2020-06-14 Quotations Envelope materials for Project staff on OFLP/ORCU/SH/06/2019 / Procurement of Ploter, Color Pending Request for Single Stage - One printer, Digitizing table, TF / A4442 Enabling environment Post Limited 45,000.00 0.00 Implementati 2019-10-15 2019-11-30 2019-12-30 Quotations Envelope GPS, Stationery, Smart on Tablets) Page 3 OFLP/ORCU/SH/18/2019 / Procurement of tyres and Pending Request for Single Stage - One inner tube for 7 project TF / A4442 Enabling investments Post Limited 25,000.00 0.00 Implementati 2019-12-22 2020-01-12 2020-01-22 Quotations Envelope vehicle (5 tyres for each on vehicles) and 18 Motorbikes NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OFLP/ORCU/SH//NCS/02/17 Under Request for Single Stage - One / Car rental for Woreda TF / A4442 Enabling investments Post Limited 98,000.00 0.00 Implementati 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Coordinators on OFLP/ORCU/SH/NCS/03/17 / Under Request for Single Stage - One Car rental and transport TF / A4442 Enabling investments Post Limited 10,200.00 72,368.17 Implementati 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope fees for ORCU level on OFLP/ORCU/SH/NCS/01/2017 Under / Car rental for Lead Request for Single Stage - One TF / A4442 Enabling investments Post Limited 25,600.00 0.00 Implementati 2017-08-11 2017-10-13 2018-10-13 Facilitators and Safeguards Quotations Envelope on Coordinators OFLP/ORCU/SH/NCS/05/2018 Pending Request for Single Stage - One / Office rental for Zonal and TF / A4442 Enabling investments Post Limited 50,000.00 0.00 Implementati 2018-09-23 2018-11-17 2019-11-17 Quotations Envelope Woreda Clusters on OFLP/ORCU/SH/NCS/04/2018 / Car rental and Under Request for Single Stage - One transportation fees for LF, TF / A4442 Enabling investments Post Limited 99,000.00 77,977.99 Implementati 2018-09-22 2018-11-11 2019-05-10 Quotations Envelope Safeguards and Woreda on Coordinators OFLP/ORCU/NCB/02/2018 / Pending Installation of Forest Single Stage - One TF / A4442 Enabling environment Post Request for Bids Open - National 135,000.00 0.00 Implementati 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-06 2020-05-05 Management Information Envelope on System OFLP/ORCU/SH/NCS/06/2018 Pending / Promotion of the use of Request for Single Stage - One TF / A4442 Enabling environment Post Limited 1,272.00 0.00 Implementati 2018-08-20 2018-10-15 2018-12-14 ICS through production and Quotations Envelope on broadcasting of Radio Spots OFLP/ORCU/NC/01/2019 / Request for Single Stage - One Vehicle rental services (ten TF / A4442 Enabling investments Post Limited 62,000.00 0.00 Canceled 2019-09-20 2019-10-23 2019-11-22 Quotations Envelope vehicles for three months) OFLP/ORCU/SH/05/2019 / Pending Procurement of satellite TF / A4442 Enabling environment Post Direct Selection Direct 65,000.00 0.00 Implementati 2020-01-20 2020-01-25 2020-02-29 2020-08-27 imagery and software and on licenses for MRV CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OFLP/ORCU/CF/2/2017 / Least Cost Pending Financial Audit Service TF / A4442 Enabling environment Post Open - National 10,000.00 0.00 2018-03-01 2018-03-15 2018-04-28 2018-05-26 2018-06-25 2018-07-24 2018-08-22 2018-11-20 Selection Implementation (Firm) Page 4 OFLP/ORCU/CF/1/2018 / CONSULTING SERVICES Consultant FOR COMMUNICATIONS Pending TF / A4442 Enabling environment Post Qualification Open - National 44,000.00 0.00 2018-03-21 2018-04-04 2018-05-03 2018-05-18 2018-06-01 2018-11-28 NEEDS ASSESMENT, TOOL Implementation Selection KIT PREPARATION AND ADVISORY SERVICES OFLP/ORCU/CF/2/2018 / Hiring Integrated Land-use Consultant Under Planning Consulting Firm TF / A4442 Enabling investments Post Qualification Open - National 250,000.00 0.00 2018-04-25 2018-10-17 2018-11-30 2018-12-30 2019-02-03 2022-02-02 Implementation (to be attached to Oromia Selection BoRLA) OFLP/ORCU/CF/3/2018 / Integrated Land use Planning Technical Quality And Cost- Under TF / A4442 Enabling investments Post Open - National 250,000.00 0.00 2019-01-21 2019-02-11 2019-03-27 2019-04-24 2019-05-24 2019-06-28 2019-08-02 2022-01-18 assistance, implementation Based Selection Implementation and enforcement advisory services OFLP/ORCU/CF/1/2017 / Least Cost Procurement Audit Service TF / A4442 Enabling environment Post Open - National 10,000.00 0.00 Canceled 2018-03-01 2018-03-22 2018-05-05 2018-06-02 2018-07-02 2018-07-31 2018-08-29 2018-10-28 Selection (Firm) OFLP/ORCU/CF/4/2018 / Independent Procurement Least Cost TF / A4442 Enabling environment Prior Open - National 20,000.00 0.00 Under Review 2019-04-30 2019-05-21 2019-06-12 2019-06-27 2019-07-12 2019-08-10 2019-09-01 2019-12-30 Audit of EFY 2010 and Selection 2011 OFLP/ORCU/CF/04/2019 / Least Cost Pending Recruitment of a Financial TF / A4442 Enabling environment Post Open - National 20,000.00 0.00 2019-12-31 2020-01-21 2020-03-05 2020-04-02 2020-05-02 2020-06-06 2020-07-11 2021-01-07 Selection Implementation Audit Firm INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OFLP/ORCU/IC/06/2017 / Individual Pending Financial Management / Enabling environment Post Consultant Open 18,102.00 0.00 2017-05-23 2017-07-11 2017-08-01 2017-09-05 2018-03-04 Implementation Specialist (based at MEFCC) Selection OFLP/ORCU/IC/11/2017 / Individual Pending Institutional and Policy / Enabling environment Post Consultant Open 17,096.00 0.00 2017-05-23 2017-07-11 2017-08-01 2017-09-05 2018-03-04 Implementation Specialist Selection OFLP/ORCU/IC/07/2017 / Individual Pending Financial Management / Enabling environment Post Consultant Open 15,085.00 0.00 2017-05-25 2017-07-13 2017-08-03 2017-09-07 2018-03-06 Implementation Assistant (based at ORCU) Selection Individual OFLP/ORCU/IC/13/2017 / Pending / Enabling environment Post Consultant Open 17,096.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-03-07 Assistant MRV Specialist Implementation Selection OFLP/ORCU/IC/14/2017 / Individual Pending Private Sector Development / Enabling environment Post Consultant Open 17,096.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-03-07 Implementation Specialist Selection Individual OFLP/ORCU/IC/16-18/2017 / Pending / Enabling environment Post Consultant Open 60,340.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-03-07 Lead Facilitators (#3) Implementation Selection Individual OFLP/ORCU/IC/19-24/2017 / Pending / Enabling environment Post Consultant Open 108,611.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-03-07 Safeguards Coordinators (#6) Implementation Selection Page 5 Individual OFLP/ORCU/IC/63-65/2017 / Pending / Enabling environment Post Consultant Open 39,221.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-03-07 Accountants (#3) Implementation Selection OFLP/ORCU/IC/68/07 / Individual Pending International M&E / Enabling environment Post Consultant Open 50,000.00 0.00 2017-06-28 2017-08-16 2017-09-06 2017-10-11 2018-04-09 Implementation consultant Selection OFLP/ORCU/IC/72/2017 / Individual Preparation of a strategic Pending TF / A4442 Enabling environment Post Consultant Open 30,000.00 0.00 2017-06-30 2017-08-18 2017-09-08 2017-10-13 2018-04-11 action plan for private sector Implementation Selection investment OFLP/ORCU/IC/02/2017 / Pending TF / A4442 Enabling environment Post Direct Selection Direct 22,125.00 0.00 2017-06-27 2017-07-07 2017-09-10 2018-09-10 Forest Resource Specialist Implementation OFLP/ORCU/IC/04/2017 / Pending TF / A4442 Enabling environment Post Direct Selection Direct 22,125.00 0.00 2017-06-27 2017-07-07 2017-09-10 2018-09-10 Social Safeguards Specialist Implementation Individual OFLP/ORCU/IC/08/2017 / Pending TF / A4442 Enabling environment Post Consultant Open 17,096.00 0.00 2017-06-27 2017-08-15 2017-09-05 2017-10-10 2018-10-10 Procurement Specialist Implementation Selection Individual OFLP/ORCU/IC/09/2017 / Pending TF / A4442 Enabling environment Post Consultant Open 17,096.00 0.00 2017-05-23 2017-07-11 2017-08-01 2017-09-05 2018-09-05 M&E Specialist Implementation Selection OFLP/ORCU/IC/10/2017 / Pending TF / A4442 Enabling environment Post Direct Selection Direct 18,102.00 0.00 2017-06-27 2017-07-07 2017-09-10 2018-09-10 Communication Specialist Implementation OFLP/ORCU/IC/03/2017 / Pending Environmental Safeguards TF / A4442 Enabling environment Post Direct Selection Direct 22,125.00 0.00 2017-06-27 2017-07-07 2017-09-10 2018-09-10 Implementation Specilaist OFLP/ORCU/IC/05/2017 / Pending Financial Management TF / A4442 Enabling environment Post Direct Selection Direct 17,096.00 0.00 2017-06-27 2017-07-07 2017-09-10 2018-09-10 Implementation Specialist (based at ORCU) Individual OFLP/ORCU/IC/12/2017 / Pending TF / A4442 Enabling environment Post Consultant Open 20,113.00 0.00 2017-05-25 2017-07-13 2017-08-03 2017-09-07 2018-09-07 MRV Specialist Implementation Selection OFLP/ORCU/IC/70/2017 / Translation of extension Individual Pending guidelines & manuals into TF / A4442 Enabling environment Post Consultant Open 5,000.00 0.00 2017-08-30 2017-10-18 2017-11-08 2017-12-13 2018-06-11 Implementation Afaan Oromo and Amharic Selection languages OFLP/ORCU/IC/75/2017 / Gender Analysis and Action Individual Pending Plan Development to TF / A4442 Enabling environment Post Consultant Open 16,000.00 0.00 2017-11-15 2018-01-03 2018-01-24 2018-02-28 2018-08-27 Implementation mainstream gender in the Selection OFLP Implementation OFLP/ORCU/IC/69/2017 / Individual Pending Development of extension TF / A4442 Enabling environment Post Consultant Open 10,000.00 0.00 2017-08-10 2017-09-28 2017-10-19 2017-11-23 2018-05-22 Implementation guidelines & manuals Selection OFLP/ORCU/IC/78/2017 / Individual Pending Environmental & Social TF / A4442 Enabling environment Post Consultant Open 16,000.00 0.00 2018-05-28 2018-07-16 2018-08-06 2018-09-10 2019-03-09 Implementation Audit Selection Individual OFLP/ORCU/IC/66/2017 / Pending TF / A4442 Enabling environment Post Consultant Open 12,068.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-09-08 Audiovisual technician Implementation Selection Page 6 Individual OFLP/ORCU/IC/25-62/2017 / Pending TF / A4442 Enabling environment Prior Consultant Open 496,796.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-09-08 Woreda Coordinators (#38) Implementation Selection OFLP/ORCU/IC/01/2017 / Pending TF / A4442 Enabling environment Post Direct Selection Direct 30,170.00 0.00 2017-06-30 2017-07-10 2017-07-31 2018-07-31 Program Coordinator Implementation Individual OFLP/ORCU/IC/15/2017 / Pending TF / A4442 Enabling environment Post Consultant Open 15,085.00 0.00 2017-05-26 2017-07-14 2017-08-04 2017-09-08 2018-09-08 Administrative Assistant Implementation Selection OFLP/ORCU/IC/71/2017 / ASSESMENT OF THE LEGAL AND POLICY FRAMEWORK GOVERNING Individual RIGHTS TO FOREST Under TF / A4442 Enabling environment Post Consultant Open 30,000.00 17,835.45 2017-09-15 2017-11-03 2017-11-24 2017-12-29 2018-12-24 TENURE, ACCESS AND Implementation Selection USE AND ITS APPLICATION, IN THE REGIONAL STATE OF ORMIA OFLP/ORCU/78/2018 / Pending TF / A4442 Enabling environment Post Direct Selection Direct 6,500.00 0.00 2018-03-22 2018-04-01 2018-06-05 2018-12-02 OFLP/ORCU/78/2018 Implementation OFLP/ORCU/IC/144/2018 / Feasibility assessment of options for introducing Individual payments for ecosystem TF / A4442 Enabling environment Post Consultant Open 50,000.00 0.00 Canceled 2019-09-07 2019-10-26 2019-11-16 2019-12-22 2020-06-19 services (PES) for non-carbon Selection markets through engaging an international IC OFLP/ORCU/IC/145/2018 / Individual Forest Mangement Under TF / A4442 Enabling environment Post Consultant Open 15,000.00 0.00 2017-12-13 2018-01-01 2018-01-08 2018-01-23 2018-07-22 Information needs Implementation Selection Assessment RPPR/IC- 10/17 / Preparation of Oromia ER- Individual PD by the support of Pending TF / A4442 Enabling environment Post Consultant Open 20,000.00 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Individual Consultant Partly Implementation Selection financed by Additional Finance until June 20, 2018 RPPR/IC- 6/15 / Preparation of Benefit Individual Sharing Mechanism (BSM) Pending TF / A4442 Enabling environment Post Consultant Open 10,000.00 0.00 2015-10-05 2015-11-23 2015-12-14 2016-01-19 2018-01-18 for OFLP partly finaced by Implementation Selection Additonal Finance until June 20, 2018 Individual OFLP/ORCU/IC/89/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 18,000.00 0.00 2019-05-13 2019-05-23 2019-06-13 2019-07-18 2020-01-14 Assistant MRV Specialist Implementation Selection Individual OFLP/ORCU/IC/78/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 26,400.00 0.00 2018-10-18 2018-10-28 2018-11-18 2018-12-23 2020-12-22 Forest Resource Specialist Implementation Selection OFLP/ORCU/IC/81/2018 / Individual Pending Financial Management TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-09-27 2018-10-07 2018-10-21 2018-11-11 2020-11-10 Implementation Specialist (based at ORCU) Selection OFLP/ORCU/IC/82/2018 / Individual Pending Financial Management TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-02 2018-10-12 2018-10-26 2018-11-16 2020-11-15 Implementation Specialist (based at MEFCC) Selection Page 7 OFLP/ORCU/IC/83/2018 / Individual Pending Financial Management TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2019-06-10 2019-06-20 2019-07-11 2019-08-15 2021-08-14 Implementation Assistant (based at ORCU) Selection Individual OFLP/ORCU/IC/85/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-09-27 2018-10-07 2018-10-21 2018-11-11 2020-11-10 M&E Specialist Implementation Selection Individual OFLP/ORCU/IC/88/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 26,400.00 0.00 2019-05-14 2019-05-24 2019-06-14 2019-07-19 2021-07-18 MRV Specialist Implementation Selection OFLP/ORCU/IC/90/2018 / Individual Pending Private Sector Development TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-09-20 2018-09-30 2018-10-14 2018-11-01 2020-10-31 Implementation Specialist Selection Individual OFLP/ORCU/IC/91/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-09-17 2018-09-27 2018-10-04 2018-10-25 2020-10-24 Adminsitrative Assistant Implementation Selection Individual OFLP/ORCU/IC/92-94/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 72,000.00 0.00 2018-09-20 2018-09-30 2018-10-21 2018-11-25 2020-11-24 Lead Facilitators (#3)* Implementation Selection Individual OFLP/ORCU/IC/139-141/2018 Pending TF / A4442 Enabling investments Post Consultant Direct 46,800.00 0.00 2019-02-05 2019-02-15 2019-03-08 2019-04-12 2021-04-11 / Accountants (#3)**** Implementation Selection Individual OFLP/ORCU/IC/142/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 14,400.00 0.00 2019-06-12 2019-06-22 2019-07-13 2019-08-17 2021-08-16 Audiovidual technician Implementation Selection Individual OFLP/ORCU/IC/143/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 15,600.00 0.00 2018-09-21 2018-10-01 2018-10-22 2018-11-26 2020-11-25 ICT Specialist Implementation Selection OFLP/ORCU/IC/79/2018 / Individual Pending Environmental Safeguards TF / A4442 Enabling environment Post Consultant Direct 26,400.00 0.00 2018-09-28 2018-10-08 2018-10-29 2018-12-03 2020-12-02 Implementation Specialist Selection OFLP/ORCU/IC/87/2018 / Individual Pending Intitutional and Policy TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-01 2018-10-11 2018-11-01 2018-12-06 2020-12-05 Implementation Specialist Selection OFLP/ORCU/IC/77/2018 / Individual Pending Oromia REDD+ Program TF / A4442 Enabling environment Post Consultant Direct 36,000.00 0.00 2018-05-02 2018-05-12 2018-06-02 2018-07-07 2020-07-06 Implementation Coordinator Selection Individual OFLP/ORCU/IC/80/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 26,400.00 0.00 2018-05-03 2018-05-13 2018-06-03 2018-07-08 2020-07-07 Social Safegurds Specialist Implementation Selection Individual OFLP/ORCU/IC/86/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-02-04 2018-02-14 2018-03-07 2018-04-11 2020-04-10 Communications Specialist Implementation Selection OFLP/ORCU/101/2018 / Individual Pending Woreda Coordinator (Dalle TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Wabara) Selection OFLP/ORCU/102/2018 / Individual Pending Woreda Coordinator (Yama TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Logi Walal) Selection Page 8 Individual OFLP/ORCU/103/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Gimbi) Implementation Selection OFLP/ORCU/104/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Gullisso) Selection Individual OFLP/ORCU/105/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Nejo) Implementation Selection OFLP/ORCU/106/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Nekemte) Selection OFLP/ORCU/107/2018 / Individual Pending Woreda Coordinator (Gida TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Ayana) Selection OFLP/ORCU/108/2018 / Individual Pending Woreda Coordinator (Abayi TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Choman) Selection OFLP/ORCU/109/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Shambu) Selection OFLP/ORCU/110/2018 / Individual Pending Woreda Coordinator (Seka TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Chekorsa) Selection OFLP/ORCU/111/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Asendabo) Selection Individual OFLP/ORCU/112/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-12 2018-10-19 2018-11-02 2020-11-01 Woreda Coordinator (Agaro) Implementation Selection OFLP/ORCU/113/2018 / Individual Pending Woreda Coordinator (Limu TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Genet) Selection Individual OFLP/ORCU/114/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Chora) Implementation Selection Individual OFLP/ORCU/115/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Bedele) Implementation Selection OFLP/ORCU/116/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Hurrumu) Selection Individual OFLP/ORCU/117/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Alle) Implementation Selection OFLP/ORCU/118/2018 / Individual Pending Woreda Coordinator (Nono TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-12 2018-10-19 2018-11-02 2020-11-01 Implementation Sale) Selection Page 9 OFLP/ORCU/119/2018 / Individual Pending Woreda Coordinator (Bule TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Hora) Selection Individual OFLP/ORCU/120/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Adola) Implementation Selection Individual OFLP/ORCU/121/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Bore) Implementation Selection Individual OFLP/ORCU/122/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Nagele) Implementation Selection Individual OFLP/ORCU/123/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Yaballo) Implementation Selection Individual OFLP/ORCU/124/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Ginir) Implementation Selection Individual OFLP/ORCU/125/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-12 2018-10-19 2018-11-02 2020-11-01 Woreda Coordinator (Goba) Implementation Selection Individual OFLP/ORCU/126/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Tiyo) Implementation Selection Individual OFLP/ORCU/127/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Guna) Implementation Selection OFLP/ORCU/128/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Shashamane) Selection Individual OFLP/ORCU/129/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Dodola) Implementation Selection OFLP/ORCU/130/2018 / Individual Pending Woreda Coordinator (Liban TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Jawi) Selection Individual OFLP/ORCU/131/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Dendi) Implementation Selection OFLP/ORCU/132/2018 / Individual Pending Woreda Coordinator (Walisso TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation ) Selection Individual OFLP/ORCU/133/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Lume) Implementation Selection OFLP/ORCU/134/2018 / Individual Pending Woreda Coordinator TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Chancho) Selection Page 10 Individual OFLP/ORCU/135/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Chiro ) Implementation Selection OFLP/ORCU/136/2018 / Individual Pending Woreda Coordinator (Oda TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Bultum) Selection Individual OFLP/ORCU/137/2018 / Pending TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Woreda Coordinator (Deder) Implementation Selection OFLP/ORCU/138/2018 / Individual Pending Woreda Coordinator (Kurfa TF / A4442 Enabling investments Post Consultant Direct 15,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Chale) Selection OFLP/ORCU/95/2018 / Individual Pending Safeguards Coordinator TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Bedele) Selection OFLP/ORCU/96/2018 / Individual Pending Safeguards Coordinator TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Nekemte) Selection OFLP/ORCU/97/2018 / Individual Pending Safegards Coordinator TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Ambo) Selection OFLP/ORCU/98/2018 / Individual Pending Safegards Coordinator TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation (Shashamane) Selection OFLP/ORCU/99/2018 / Individual Pending Safegards Coordinator (Bule TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Implementation Hora) Selection Individual OFLP/ORCU/100/2018 / Pending TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 2018-10-05 2018-10-15 2018-10-22 2018-11-05 2020-11-04 Safegards Coordinator (Chiro) Implementation Selection Individual OFLP/ORCU/IC/84/2018 / TF / A4442 Enabling environment Post Consultant Direct 21,600.00 0.00 Canceled 2018-09-17 2018-09-27 2018-10-11 2018-11-01 2020-10-31 Procurement Specialist Selection OFLP/ORCU/IC/77/2017 / Individual Preparation of / Enabling environment Post Consultant Open 24,000.00 0.00 Canceled 2017-07-05 2017-08-23 2017-09-13 2017-10-18 2018-04-16 communication toolkit Selection OFLP/ORCU/IC/21/2017 / Individual Hiring an international / Enabling environment Post Consultant Open 50,000.00 0.00 Canceled 2017-07-10 2017-08-28 2017-09-18 2017-10-23 2018-04-21 ILUP Specialist (to be Selection attached to Oromia BoRLA) OFLP/ORCU/77/2018 / Consulting services to assess Individual policies related to renewable TF / A4442 Enabling environment Post Consultant Open 20,000.00 0.00 Canceled 2018-03-21 2018-05-09 2018-05-30 2018-07-04 2018-12-31 energy and distribution of Selection improved cook stoves OFLP/ORCU/IC/76/2017 / Individual Gap analysis/communication TF / A4442 Enabling environment Post Consultant Open 20,000.00 0.00 Canceled 2017-05-28 2017-07-16 2017-08-06 2017-09-10 2018-03-09 based assessment Selection Individual OFLP/ORCU/IC/84B/2018 / TF / A4442 Enabling environment Prior Consultant Open 21,600.00 7,419.95 Signed 2018-09-17 2018-10-06 2018-10-13 2018-10-27 2020-10-26 Procurement Specialist Selection Page 11 OFLP/ORCU/IC/02/2019 / Individual Independent Environmental Under TF / A4442 Enabling environment Post Consultant Open 12,000.00 0.00 2019-07-09 2019-08-27 2019-09-17 2019-10-22 2020-04-19 Audit of OFLP, RIP and Implementation Selection other relevant initiatives OFLP/ORCU/IC01/2019 / Individual Independent Social Audit of Under TF / A4442 Enabling environment Post Consultant Open 12,000.00 0.00 2019-07-09 2019-08-27 2019-09-17 2019-10-22 2020-04-19 OFLP, RIP and Other Implementation Selection relevant initiatives Page 12