75684 GOVERNMENT OF ODISHA Department of Water Resources Orissa Community Tank Development Management Society PROCUREMENT PLAN FOR THE YEAR 2012-13 ( JULY -2012 TO JUNE 2013) ON i) Civil Works ii) Goods and Equipments &+-- iii) Consultancy and Training 8th November, 2012 /January, 2013 Bhubaneswar PROCUREMENT PLAN 2012-13 ORISSA COMMUNITY TANK MANAGEMENT PROJECT (OCTMP) I. General 1. Project information: Country: INDIA Borrower: Government of Orissa through Government of INDIA Project Name: ORISSA COMMUNITY TANK DEVELOPMENT AND MANAGEMENT SOCIETY (OCTDMS) Loan No: 7576 IN Credit No: 4499 IN Project ID P100735 Project Implementing Agency: Orissa Community Tank Management Project Dept. of Water Resources, Govt. of Orissa 2. Bank’s approval Date of the procurement Plan: [Original: ] 3. Date of General Procurement Notice: NA 4. Period covered by this procurement plan: July 2012 to June 2013. II. Procurement of Goods and Works. 1. Procurement Methods: Works and Goods:  ICB, contracts above US $10 million (INR 40 crore approx.) for works and US $ 200,000 (INR 80 lakhs approx.) for goods in each case.  NCB, contracts up to US $ 10 million (INR 40 crore approx.) for works and up to US $ 200,000 (INR 80 lakhs approx.) for goods in each case.  Shopping contracts up to US $ 20,000 (INR 8 lakhs approx.) for works and goods in each case.  Direct Contracting, proprietary items, such as spare parts, software, books, periodicals etc. up to US $ 10,000 (INR 4 lakhs) per contract, meeting requirements stated in the Procurement guideline of the Bank and petty items costing up to US $ 1000 (INR 40000) per contract may be procured through Direct Contracting. Note:- Slicing/ Packaging/ Lots shall be appropriately reviewed to avoid fragmentation to the extent practicable. Whenever bids are invited concurrently for several contracts in a package and cross discounts are invited, the aggregate value of the total package will form the basis to determine the procurement method as well as the review requirement. © Review Requirements: 7. Prior Review: Goods and Works: All ICB contracts and first NCB contracts for goods as well as Works irrespective of value and all contracts valued over US $ 1,000,000 equivalent for works and US $ 100,000 for goods will be subject to prior review of the Bank. In addition, all contracts for goods and works awarded on Direct Contracting method, other than proprietary items, software, books and periodicals, spare parts up to $ 10,000 and petty items of value not exceeding $1,000 , will be subject to prior review by the Bank. Post Review: All contracts not covered under prior review will be subject to post award review. 3. Procurement Packages with Methods and Time Schedule (Requiring Prior Review by the Bank) II. PROCUREMENT of GOODS, WORKS PROCUREMENT PLAN OF OCTDMS FOR 2012-13 (JULY-12 TO JUNE 2013) A. CIVIL WORKS Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date (A) On Going Works Not Post 14-02- 25-04- 25-04- 1 Dhenkanal Angul Ashrubahal M.I.P.(Res) 15.7 YES NCB No Required Review 2011 2011 2011 Not Post 17-03- 31-05- 31-05- 2 Balasore Balasore Khumkote 27.25 YES NCB No Required Review 2011 2011 2011 Not Post 29-01- 19-02- 19-02- 3 Baripada Mayurbhanj Kasipani MIP 78.98 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 17-02- 17-02- 4 Baripada Mayurbhanj Kuliposi MIP (D/W) 38.03 YES NCB No Required Review 2010 2010 2010 Not Post 14-02- 28-10- 28-10- 5 Baripada Mayurbhanj Chhamundia MIP 25.7 YES NCB No Required Review 2011 2011 2011 Not Post 29-03- 19-06- 19-06- 6 Baripada Mayurbhanj Sansialinai MIP 6.1 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 17-02- 17-02- 7 Baripada Mayurbhanj Tangabilla MIP 24.18 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 08-03- 08-03- 8 Baripada Mayurbhanj Pingu MIP 22 YES NCB No Required Review 2010 2010 2010 Not Post 20-08- 21-12- 21-12- 9 Baripada Mayurbhanj Olgadiajhar MIP 22.2 YES NCB No Required Review 2009 2009 2009 Not Post 19-01- 22-02- 22-02- 10 Cuttack Jajpur Haridabahali (Dalki) 15.18 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 19-02- 19-02- 11 Cuttack Jajpur Kabatajharan 15.65 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 22-02- 22-02- 12 Cuttack Jajpur Kaduabandi 14.4 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 22-02- 22-02- 13 Cuttack Jajpur Patapur 15.02 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 24-02- 24-02- 14 Rayagada Rayagada Chakunda 7.23 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 28-04- 28-04- 15 Rayagada Rayagada G.Laxmipur 15.92 YES NCB No Required Review 2010 2010 2010 Not Post 19-03- 27-01- 27-01- 16 Rayagada Rayagada Nalapanka 38.5 YES NCB No Required Review 2010 2011 2011 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 29-01- 05-03- 05-03- 17 Rayagada Rayagada Parikiti 5.77 YES NCB No Required Review 2010 2010 2010 Not post 14-07- 25-09- 15-12- 18 Angul Angul Takua 120 YES NCB No Required Review 2011 2011 2011 Not Post 29-01- 24-02- 24-02- 19 Rayagada Rayagada Patraguda 11.4 YES NCB No Required Review 2010 2010 2010 Not Post 29-01- 05-03- 05-03- 20 Rayagada Rayagada Ramanaguda 8.48 YES NCB No Required Review 2010 2010 2010 Not Post 18-01- 23-02- 23-02- 21 Rayagada Rayagada Derigamguda 11.75 YES NCB No Required Review 2010 2010 2010 Not Post 19-03- 23-05- 23-05- 22 Rayagada Rayagada Dongakota 6.57 YES NCB No Required Review 2010 2010 2010 Not Post 19-03- 24-05- 24-05- 23 Rayagada Rayagada Sardhapur 10.17 YES NCB No Required Review 2010 2010 2010 Not Post 28-01- 30-03- 30-03- 24 Rayagada Rayagada Binishpur 74.2 YES NCB No Required Review 2010 2010 2010 Not Post 08-06- 27-11- 27-11- 25 Rayagada Rayagada Champikota 77.9 YES NCB No Required Review 2010 2010 2010 Not Post 18-01- 13-05- 13-05- 26 Gajapati Gajapati Gumma D/W 36 YES NCB No Required Review 2010 2011 2011 Not Post 19-01- 04-03- 04-03- 27 Gajapati Gajapati Gummanala, Anukunda 29.25 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 02-03- 02-03- 28 Gajapati Gajapati Kaluanalla-III,Adanguda 35.38 YES NCB No Required Review 2010 2010 2010 Not Post 19-03- 31-05- 31-05- 29 Gajapati Gajapati Kaluanalla-I,Parida 42 YES NCB No Required Review 2010 2010 2010 Not Post 29-03- 29-05- 29-05- 30 Gajapati Gajapati Akramtank,Allada 24 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 04-03- 04-03- 31 Gajapati Gajapati Polli Naidu tank, 37.19 YES NCB No Required Review 2010 2010 2010 Not Post 29-03- 31-05- 31-05- 32 Gajapati Gajapati Markadanalla, Anarada 26 YES NCB No Required Review 2010 2010 2010 Not Post 18-02- 18-02- 18-02- 33 Gajapati Gajapati Sabarpalli MIP 4.69 YES NCB No Required Review 2012 2012 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 29-01- 22-02- 22-02- 34 Ganjam-I Ganjam Belamabandha 28.92 YES NCB No Required Review 2010 2010 2010 Not Post 20-03- 22-01- 22-01- 35 Ganjam-I Ganjam KeshpurBandha,Amundi 44.41 YES NCB No Required Review 2010 2011 2011 Not Post 29-01- 22-02- 22-02- 36 Ganjam-I Ganjam RajaghaiS.Ch.Pur 27.5 YES NCB No Required Review 2010 2010 2010 Not Post 19-01- 22-02- 22-02- 37 Ganjam-II Ganjam Adiabandha 25.1 YES NCB No Required Review 2010 2010 2010 Not Post 01-05- 14-08- 20-08- 38 Boudh Boudh Bijapadar 18 YES NCB No Required Review 2012 2012 2012 Not post 01-05- 13-08- 20-08- 39 Boudh Boudh Lakrapata 56 YES NCB No Required Review 2012 2012 2012 Not Post 13-07- 12-10- 12-10- 40 Khurda Khurda Hatianalla 29.41 YES NCB No Required Review 2011 2011 2011 Not Post 13-07- 18-10- 18-10- 41 Khurda Khurda Charikhunti 39.04 YES NCB No Required Review 2011 2011 2011 Not Post 18-08- 15-10- 15-10- 42 Khurda Khurda Mendhasala 46.8 YES NCB No Required Review 2011 2011 2011 Not Post 13-07- 20-10- 20-10- 43 Khurda Khurda Bhalumundia 14.67 YES NCB No Required Review 2011 2011 2011 Not Post 17-08- 15-10- 15-10- 44 Khurda Khurda Gadadwarabandha 37.86 YES NCB No Required Review 2011 2011 2011 Not post 15-10- 12-01- 20-01- 45 Khurda Khurda Lausingh Tank 15 YES NCB No Required Review 2011 2012 2012 Not Post 13-07- 12-10- 12-10- 46 Khurda Khurda Indrajhili 21.64 YES NCB No Required Review 2011 2011 2011 Not Post 29-04- 47 Sambalpur Jharsuguda. Tumbadihi 24.73 YES NCB No 22.08.11 22.08.11 Required Review 2011 Not Post 29-04- 48 Sambalpur Jharsuguda. Sagarkata 15.9 YES NCB No 12.09.11 12.09.11 Required Review 2011 Not Post 17-08- 49 Balasore Balasore Begunia 13.7 YES NCB No 23.12.11 23.12.11 Required Review 2011 Not Post 17-08- 50 Balasore Balasore Kantapada 22.52 YES NCB No 19.12.11 19.12.11 Required Review 2011 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 17-08- 51 Balasore Balasore Chheliabandha 18.84 YES NCB No 19.12.11 19.12.11 Required Review 2011 Not Post 17-08- 52 Balasore Balasore Kaliabandha 18.03 YES NCB No 17.12.11 17.12.11 Required Review 2011 Not Post 17-08- 53 Balasore Balasore Rajabandha 36.08 YES NCB No 09.12.11 09.12.11 Required Review 2011 Not Post 17-08- 25-11- 25-11- 54 Balasore Balasore Subandha 25.01 YES NCB No Required Review 2011 2011 2011 Not Post 17-03- 26-05- 26-05- 55 Padampur Bargarh Baddhara 17.75 YES NCB No Required Review 2011 2011 2011 Not Post 12-07- 25-09- 25-09- 56 Padampur Bargarh Lakhanpurkata 23.9 YES NCB No Required Review 2011 2011 2011 Not Post 12-07- 25-09- 25-09- 57 Padampur Bargarh Raisobha 16.96 YES NCB No Required Review 2011 2011 2011 Not Post 12-07- 25-09- 25-09- 58 Padampur Bargarh Routpara 36.65 YES NCB No Required Review 2011 2011 2011 Not Post 12-07- 25-09- 25-09- 59 Padampur Bargarh Beniapali 9.23 YES NCB No Required Review 2011 2011 2011 Not Post 12-07- 25-09- 25-09- 60 Padampur Bargarh Kanakbinakata 25.41 YES NCB No Required Review 2011 2011 2011 Not Post 17-03- 31-05- 31-05- 61 Padampur Bargarh Masinakata 15.8 YES NCB No Required Review 2011 2011 2011 Not Post 15-09- 14-12- 14-12- 62 Baripada Mayurbhanj Arikul MIP 171 YES NCB No Required Review 2011 2011 2011 Not Post 29-04- 20-08- 20-08- 63 Cuttack Jajpur Dhanjaypur 21.54 YES NCB No Required Review 2011 2011 2011 Not Post 29-04- 11-10- 11-10- 64 Rayagada Rayagada Jangidi 70.51 YES NCB No Required Review 2011 2011 2011 BadabandhaSidhipalma Not Post 15-10- 65 Gajapati Gajapati 10.86 YES NCB No 23.12.11 23.12.11 MIP Required Review 2011 Gopnathghai Not Post 29-04- 10-12- 10-12- 66 Ganjam-I Ganjam 62.47 YES NCB No ,Khamarigoan Required Review 2011 2011 2011 Not Post 29-04- 10-12- 10-12- 67 Ganjam-I Ganjam Sarathisagar Srirampur 49.99 YES NCB No Required Review 2011 2011 2011 Not Post 20-03- 15-02- 15-02- 68 Cuttack Cuttack Banakhandi 25 YES NCB No Required Review 2010 2011 2011 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 18-01- 24-03- 24-03- 69 Cuttack Cuttack Mahalaxmipur 24.5 YES NCB No Required Review 2010 2011 2011 Not Post 15-10- 12-01- 12-01- 70 Khurda Khurda Chanakhia MIP 36 YES NCB No Required Review 2011 2011 2011 Not Post 15-10- 20-12- 20-12- 71 Balasore Balasore Natapada 27.73.00 YES NCB No Required Review 2011 2011 2011 Not Post 15-10- 09-12- 09-12- 72 Balasore Balasore Palasa 40.86 YES NCB No Required Review 2011 2011 2011 Not Post 15-10- 29-11- 29-11- 73 Ganjam Ganjam Khandiabandha,Desari 29.66 YES NCB No Required Review 2011 2011 2011 Not Post 15-10- 16-12- 16-12- 74 Boudh Boudh Nuapalli 38.13 YES NCB No Required Review 2011 2011 2011 Not Post 16-01- 15-03- 15-03- 75 Phulbani Boudh Laxminalla MIP 285 YES NCB No Required Review 2012 2012 2012 Not Post 16-01- 15-03- 15-03- 76 Phulbani Boudh Laxminalla MIP 285 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 77 Khurda Khurda Nahargadia 35.86 YES NCB No Mar' 12 Mar' 12 Required Review 2012 Not Post 78 Khurda Khurda Hariguru 81 YES NCB No Jan, 12 Mar ' 12 Mar ' 12 Required Review Not Post 01-05- 25-07- 06-08- 79 Angul Chhendipada Jhintipal MIP (Res) 162 YES NCB No Required Review 2012 2012 2012 Not Post 03-07- 03-10- 10-10- 80 Angul Kishorenagar Garuda M.I.P. (Res) 41 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 25-07- 31-07- 81 Angul Angul Jaganathpur MIP 101 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 01-08- 06-09- 82 Boudh Kantamal Parhel MIP 38.25 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 30-07- 10-08- 83 Boudh Kantamal Narayana Prasad 38.36 YES NCB No Required Review 2012 2012 2012 Tangi- Not Post 16-12- 10-03- 15-03- 84 Cuttack Badabandha 182 YES NCB No Choudwar Required Review 2011 2012 2012 Not Post 16-12- 10-03- 15-03- 85 Cuttack Tigiria Jamunabandha 243 YES NCB No Required Review 2011 2012 2012 Not Post 24-01- 20-04- 27-04- 86 Khurda Banapur Jogiabandha 53 YES NCB No Required Review 2012 2012 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 24-01- 20-04- 27-04- 87 Khurda Banapur Kaithanalla 72 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 20-04- 27-04- 88 Khurda Chilika Khaingabandha 194 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 20-04- 27-04- 89 Khurda Chilika Raghunathpur 41 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 20-04- 27-04- 90 Khurda Jatani Rangia 49 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 20-04- 27-04- 91 Khurda Khurda Bhaunribandha 28.89 YES NCB No Required Review 2012 2012 2012 Not Post 24-01- 20-04- 27-04- 92 Khurda Tangi Kulapada 81 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 31-07- 14-08- 93 Balasore Oupada Solabhauni 121 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 01-08- 16-08- 94 Balasore Nilagiri Chasunikula 80 YES NCB No Required Review 2012 2012 2012 Not Post 01-05- 01-08- 10-08- 95 Baragarh Ambabhona Dwari 263 YES NCB No Required Review 2012 2012 2012 Not Post 03-07- 29-09- 04-10- 96 Baragarh Bhatli Karlajori kata 41 YES NCB No Required Review 2012 2012 2012 Not Post 15-10- 10-01- 18-01- 97 Khurda Khurda Pandurama 13.76 YES NCB No Required Review 2011 2012 2012 Not Post 16-12- 25-02- 15-03- 98 Cuttack Cuttack Paloghosara 39.71 YES NCB No Required Review 2011 2012 2012 Improvement to Not Post 03-07- 99 Angul Angul 13.63 YES NCB No 03.10.12 01.11.12 Kalamati MIP Required Review 2012 Improvement to Not Post 03-07- 100 Angul Angul 12.63 YES NCB No 03.10.12 01.11.12 Podapadar MIP Required Review 2012 Renovation to Not Post 03-07- 101 Angul Angul Chhendipada Jungle 29.58 YES NCB No 03.10.12 01.11.12 Required Review 2012 MIP Not Post 16-12- 10-03- 15-03- 102 Cuttack Cuttack Tailamala 50 YES NCB No Required Review 2011 2012 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 16-12- 08-03- 12-03- 103 Cuttack Cuttack Tarding 48 YES NCB No Required Review 2011 2012 2012 Not Post 16-12- 12-03- 18-03- 104 Cuttack Cuttack Baramana 40 YES NCB No Required Review 2011 2012 2012 Not Post 16-12- 09-03- 16-03- 105 Cuttack Cuttack Nukurigadia 30 YES NCB No Required Review 2011 2012 2012 Renovation to Post 03-07- 106 Jharsuguda Jharsuguda 10.11 YES NCB NA No 03.10.12 01.11.12 Jhapurmunda MIP Review 2012 Improvement to Post 03-07- 107 Jharsuguda Jharsuguda 32.06 YES NCB NA No 03.10.12 01.11.12 Teleimal MIP Review 2012 Rehabilitation to Post 25-09- 108 Ganjam Ganjam Niladrichandra Sagar 45.17 YES NCB NA No 24.12.12 15.01.13 Review 2012 MIP Not Post 16-12- 02-03- 02-03- 109 Gajapati Gajapati Balijhalnalla-V (PP) 20.64 YES NCB No Required Review 2011 2012 2012 (B) BIDS INVITED Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 30-03- Re- Re- Under 1 Rayagada Rayagada Badabankily 32.7 YES NCB No Required Review 2010 Bidding Bidding evaluation Not Post 13-07- 12-10- 12-10- Under 2 Khurda Khurda Talabandha 15.64 YES NCB No Required Review 2011 2011 2011 evaluation Under Not Post 13-07- 13-10- 13-10- 3 Khurda Khurda Kuaput Channel 38.28 YES NCB No evaluation Required Review 2011 2011 2011 Under Not Post 29-04- Re- Re- 4 Gajapati Gajapati BadabandhaPuduni MIP 30 YES NCB No evaluation Required Review 2011 Bidding Bidding Not Post 5 Dhenkanal Angul Kukurpetta MIP 60 YES NCB No Feb, 12 Mar'12 Mar'12 Required Review Not Post 6 Khurda Khurda Kenduli 160 YES NCB No Jan, 12 April'12 April'12 Required Review Not Post 7 Khurda Khurda Kumarkhunti 120 YES NCB No Jan, 12 April'12 April'12 Required Review Not Post 8 Khurda Khurda Hada 150 YES NCB No Nov, 12 Feb' 12 Feb' 12 Required Review Not Post 28-03- Under 9 Angul Banarpal Kuio MIP (D/W) 142 YES NCB No Required Review 2012 Evaluation GauduninallaMIP Not Post 17-12- Under 10 Angul Chhendipada 81 YES NCB No (Res) Required Review 2011 Evaluation Padiabandhupali Not Post 28-03- Under 11 Angul Kishorenagar 80 YES NCB No M.I.P. Required Review 2012 Evaluation Not Post 28-03- Under 12 Angul Athamallik Khajurijodi MIP (Res) 81 YES NCB No Required Review 2012 Evaluation Mandarbahal Not Post 28-03- Under 13 Angul Athamallik 41 YES NCB No MIP(D/W) Required Review 2012 Evaluation Not Post 28-03- Under 14 Boudh Harabhanga Baisipada MIP 35.51 YES NCB No Required Review 2012 Evaluation Not Post 28-03- Under 15 Khurda Jatani Bhangia 41 YES NCB No Required Review 2012 Evaluation Not Post 28-03- Under 16 Khurda Khurda Gotota 57 YES NCB No Required Review 2012 Evaluation Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Not Post 28-03- Under 17 Khurda Khurda Sankhuabundha 41 YES NCB No Required Review 2012 Evaluation Not Post 28-03- Under 18 Balasore Oupada Pidhakata 89 YES NCB No Required Review 2012 Evaluation Not Post 15-09- 19 Boudh Boudh Chhatranga 91 YES NCB No 15.12.12 15.12.12 Required Review 2012 Not Post 01-08- Under 20 Khurda Khurda Charakhia 35.93 YES NCB No Required Review 2011 Evaluation Post 03-06- Under 21 Cuttack Cuttack Kapursing 21.8 YES NCB NA No Review 2012 Evaluation Improvement to Post 03-07- Under 22 Angul Angul 11.21 YES NCB NA No 03.10.12 01.11.12 Mangalpur MIP Review 2012 Evaluation Renovation to Post 03-07- Under 23 Angul Angul 116.68 YES NCB NA No 03.10.12 01.11.12 Gandijore MIP Review 2012 Evaluation Renovation to Post 03-07- Under 24 Angul Angul 63.72 YES NCB NA No 03.10.12 01.11.12 Dalimura MIP Review 2012 Evaluation Renovation to Post 03-07- Under 25 Khurda Khurda 13.75 YES NCB NA No 03.10.12 01.11.12 Pandarmana MIP Review 2012 Evaluation Improvement to Post 03-07- Under 26 Jharsuguda Jharsuguda 11.08 YES NCB NA No 03.10.12 01.11.12 M.Katapalli MIP Review 2012 Evaluation Renovation to Post 03-07- Under 27 Rayagada Rayagada 86.86 YES NCB NA No 03.10.12 01.11.12 Jaganathpur MIP Review 2012 Evaluation Renovation to Post 25-09- 28 Angul Angul 13.1 YES NCB NA No 24.12.12 15.01.13 Ranibandha MIP Review 2012 Renovation to Post 25-09- 29 Angul Angul 18.56 YES NCB NA No 24.12.12 15.01.13 Madanpur MIP Review 2012 Renovation to Post 25-09- 30 Angul Angul 33.26 YES NCB NA No 24.12.12 15.01.13 Jhilimunda MIP Review 2012 Renovation to Post 25-09- 31 Angul Angul 19.71 YES NCB NA No 24.12.12 15.01.13 Gangapani MIP Review 2012 Renovation to Post 25-09- 32 Angul Angul 26.6 YES NCB NA No 24.12.12 15.01.13 Sargipalli MIP Review 2012 Renovation to Matelia Post 25-09- 33 Angul Angul 112.85 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Renovation to Magura Post 25-09- 34 Khurda Khurda 124.6 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Renovation to Post 25-09- 35 Khurda Khurda 40.36 YES NCB NA No 24.12.12 15.01.13 Daruthenga MIP Review 2012 Renovation to Kenduli Post 25-09- 36 Khurda Khurda 34.61 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Renovation to Post 25-09- 37 Khurda Khurda 14.98 YES NCB NA No 24.12.12 15.01.13 Athabati MIP Review 2012 Renovation to Post 25-09- 38 Rayagada Rayagada 46.34 YES NCB NA No 24.12.12 15.01.13 Narayanpur MIP Review 2012 Renovation to Post 25-09- 39 Balasore Balasore 34.1 YES NCB NA No 24.12.12 15.01.13 Atashbandha MIP Review 2012 Renovation to Post 25-09- 40 Balasore Balasore 30.57 YES NCB NA No 24.12.12 15.01.13 Raghabpur MIP Review 2012 Renovation to Post 25-09- 41 Balasore Balasore 37.78 YES NCB NA No 24.12.12 15.01.13 Gohirakhal MIP Review 2012 Rehalitation to Post 25-09- 42 Gajapati Gajapati 12.19 YES NCB NA No 24.12.12 15.01.13 Jogulutank MIP Review 2012 Rehalitation to Post 25-09- 43 Gajapati Gajapati Badabandha ,Puduni 14.1 YES NCB NA No 24.12.12 15.01.13 Review 2012 MIP Rehabilitation to Post 25-09- 44 Ganjam Ganjam 16.65 YES NCB NA No 24.12.12 15.01.13 Khajuribandha MIP Review 2012 Renovation to Dhodei Post 25-09- 45 Cuttack Cuttack 25 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Renovation to Post 25-09- 46 Cuttack Cuttack 11.74 YES NCB NA No 24.12.12 15.01.13 Nakhapadanalla MIP Review 2012 Renovation to Post 25-09- 47 Cuttack Cuttack 11.02 YES NCB NA No 24.12.12 15.01.13 Mahalaxmipur MIP Review 2012 Renovation to Post 25-09- 48 Cuttack Cuttack 21.96 YES NCB NA No 24.12.12 15.01.13 Mahantabandha MIP Review 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Renovation to Post 25-09- 49 Cuttack Cuttack 16.99 YES NCB NA No 24.12.12 15.01.13 Tantichipa MIP Review 2012 Renovation to Post 25-09- 50 Baragarh Baragarh 23.5 YES NCB NA No 24.12.12 15.01.13 Rujhhenmal MIP Review 2012 Renovation to Post 25-09- 51 Angul Angul 15.65 YES NCB NA No 24.12.12 15.01.13 Chhotokoi MIP Review 2012 Renovation to Post 25-09- 52 Angul Angul 11.04 YES NCB NA No 24.12.12 15.01.13 Kothabhuin MIP Review 2012 Renovation to Anladia Post 25-09- 53 Khurda Khurda 12.43 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Renovation to Batadia Post 25-09- 54 Khurda Khurda 13.61 YES NCB NA No 24.12.12 15.01.13 MIP Review 2012 Renovation to Post 25-09- 55 Khurda Khurda 13.09 YES NCB NA No 24.12.12 15.01.13 Deshbandha MIP Review 2012 Renovation to Post 25-09- 56 Khurda Khurda 14.62 YES NCB NA No 24.12.12 15.01.13 Godarbandha MIP Review 2012 Renovation to Post 25-09- 57 Khurda Khurda 13.62 YES NCB NA No 24.12.12 15.01.13 Kundabandha MIP Review 2012 Renovation to Post 25-09- 58 Khurda Khurda 14.1 YES NCB NA No 24.12.12 15.01.13 Maulabibandha MIP Review 2012 Renovation to Post 25-09- 59 Rayagada Rayagada Bainabasa MIP (Head 43.77 YES NCB NA No 24.12.12 15.01.13 Review 2012 works) Package-A Renovation to Bainabasa MIP Post 25-09- 60 Rayagada Rayagada 47.36 YES NCB NA No 24.12.12 15.01.13 (LMC) Review 2012 Package-B Reno159vation to Bainabasa MIP (LMC Post 25-09- 61 Rayagada Rayagada 36.1 YES NCB NA No 24.12.12 15.01.13 & RMC Branch canal) Review 2012 Package-C Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Renovation to Post 25-09- 62 Balasore Balasore 21.68 YES NCB NA No 24.12.12 15.01.13 Brundadeipur MIP Review 2012 Renovation to Post 25-09- 63 Balasore Balasore 25.65 YES NCB NA No 24.12.12 15.01.13 Dhobadhobani MIP Review 2012 Renovation to Post 25-09- 64 Cuttack Cuttack 20.5 YES NCB NA No 24.12.12 15.01.13 Khambeswari MIP Review 2012 Renovation to Post 08-11- 65 Khurda Khurda 38.4 YES NCB NA No 08.02.13 25.02.13 Tamando MIP Review 2012 Renovation to Post 08-11- 66 Khurda Khurda 11.91 YES NCB NA No 08.02.13 25.02.13 Dhihakhala MIP Review 2012 Renovation to Post 08-11- 67 Khurda Khurda 13.54 YES NCB NA No 08.02.13 25.02.13 Kochilaganda MIP Review 2012 Renovation to Post 08-11- 68 Balasore Balasore 17.96 YES NCB NA No 08.02.13 25.02.13 Badapokhari MIP Review 2012 Renovation to Alipur Post 08-11- 69 Balasore Balasore 24.59 YES NCB NA No 08.02.13 25.02.13 MIP Review 2012 Renovation to Post 08-11- 70 Cuttack Cuttack 27.22 YES NCB NA No 08.02.13 25.02.13 Jharianala MIP Review 2012 Renovation to Post 08-11- 71 Cuttack Cuttack 25.1 YES NCB NA No 08.02.13 25.02.13 Sambarpat MIP Review 2012 Rehabilitation to Post 08-11- 72 Gajapati Gajapati 18.15 YES NCB NA No 08.02.13 25.02.13 Ukhura MIP Review 2012 Rehabilitation to Post 08-11- 73 Gajapati Gajapati 16.41 YES NCB NA No 08.02.13 25.02.13 Ramagiri (DW-II) MIP Review 2012 Renovation to Post 08-11- 74 Boudh boudh 16.34 YES NCB NA No 08.02.13 25.02.13 Sadanandapur MIP Review 2012 Renovation to Post 21-11- 75 Angul Angul 47.98 YES NCB NA No 20.02.13 05.03.13 Gopalpur MIP Review 2012 Renovation to Post 21-11- 76 Baragarh Baragarh 20.96 YES NCB NA No 20.02.13 05.03.13 Bhoinatora MIP Review 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Improvement to Post 21-11- 77 Boudh Boudh 38.78 YES NCB NA No 20.02.13 05.03.13 Dumduma MIP Review 2012 Improvement to Post 21-11- 78 Boudh Boudh 27.82 YES NCB NA No 20.02.13 05.03.13 Panchukipathar MIP Review 2012 Improvement to Post 21-11- 79 Boudh Boudh 39.51 YES NCB NA No 20.02.13 05.03.13 Ranisagar MIP Review 2012 Renovation to Post 21-11- 80 Cuttack Cuttack 15.6 YES NCB NA No 20.02.13 05.03.13 Purunapani MIP Review 2012 Renovation to Post 21-11- 81 Cuttack Cuttack 20.2 YES NCB NA No 20.02.13 05.03.13 Ranijharan MIP Review 2012 Renovation to Post 21-11- 82 Cuttack Cuttack 26.6 YES NCB NA No 20.02.13 05.03.13 Sunamuhi MIP Review 2012 Renovation to Post 21-11- 83 Cuttack Cuttack 18.01 YES NCB NA No 20.02.13 05.03.13 Baghakhianalla MIP Review 2012 Renovation to Asuary Post 21-11- 84 Khurda Khurda 10.67 YES NCB NA No 20.02.13 05.03.13 MIP Review 2012 Renovation to Post 21-11- 85 Khurda Khurda 9.27 YES NCB NA No 20.02.13 05.03.13 Jaragaranalla MIP Review 2012 Renovation to Kalajhar Post 21-11- 86 Khurda Khurda 29.35 YES NCB NA No 20.02.13 05.03.13 MIP Review 2012 Renovation to Kasia Post 21-11- 87 Khurda Khurda 5.89 YES NCB NA No 20.02.13 05.03.13 MIP Review 2012 Renovation to Post 21-11- 88 Khurda Khurda 14.29 YES NCB NA No 20.02.13 05.03.13 Khajuribandha MIP Review 2012 Renovation to Post 21-11- 89 Khurda Khurda 11.25 YES NCB NA No 20.02.13 05.03.13 Majhibandha MIP Review 2012 Renovation to Post 21-11- 90 Khurda Khurda 12.78 YES NCB NA No 20.02.13 05.03.13 SunamuhiMIP Review 2012 Renovation to Post 21-11- 91 Khurda Khurda 10.81 YES NCB NA No 20.02.13 05.03.13 Tentuliabandha MIP Review 2012 Expected Expected Expected Estimated Bid Review by procurement Pre- Domestic Bid Contract Contract Sl.no Division District Name of Projects cost in Document bank Comments method qualification preference opening Award Signature lakh completed (prior/post) date Date date Post Re- 92 Mayurbhanj Mayurbhanj Arikul MIP 171 YES NCB NA No Review bidding Improvement to Dadar Post 25-12- 93 Angul Angul 11.00 YES NCB NA No 25-02-12 15-03-13 MIP Review 2012 Renovation to Dahimal Post 25-12- 94 Angul Angul 25.05 YES NCB NA No 25-02-12 15-03-13 MIP Review 2012 Improvement to Post 25-12- 95 Angul Angul 21.25 YES NCB NA No 25-02-12 15-03-13 Kaliadarh MIP Review 2012 Improvement to Post 25-12- 96 Angul Angul 26.53 YES NCB NA No 25-02-12 15-03-13 Kishoresagar MIP Review 2012 Improvement to Post 25-12- 97 Boudh Boudh 43.59 YES NCB NA No 25-02-12 15-03-13 Badabandha MIP Review 2012 Boudh Boudh Improvement to Post 25-12- 98 23.15 YES NCB NA No 25-02-12 15-03-13 Bijamari MIP Review 2012 Renovation to Post 25-12- 99 Khurda Khurda 11.00 YES NCB NA No 25-02-12 15-03-13 Ambakhol MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 100 20.60 YES NCB NA No 25-02-12 15-03-13 Baisnabbandha MIP Review 2012 Khurda Khurda Renovation to Balisara Post 25-12- 101 32.60 YES NCB NA No 25-02-12 15-03-13 MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 102 14.55 YES NCB NA No 25-02-12 15-03-13 Chandipokhori MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 103 12.37 YES NCB NA No 25-02-12 15-03-13 Dhobagadia MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 104 34.23 YES NCB NA No 25-02-12 15-03-13 Gobarbandha MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 105 18.23 YES NCB NA No 25-02-12 15-03-13 Hadinalla MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 106 Halandabadabandha 14.04 YES NCB NA No 25-02-12 15-03-13 Review 2012 MIP Khurda Khurda Renovation to Post 25-12- 107 14.52 YES NCB NA No 25-02-12 15-03-13 Koradabhanga MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 108 19.72 YES NCB NA No 25-02-12 15-03-13 Krushnapur MIP Review 2012 Khurda Khurda Renovation to Post 25-12- 109 34.37 YES NCB NA No 25-02-12 15-03-13 Sanamahura MIP Review 2012 (C) Bid to be Invited Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 30-12- 1 Angul Angul Bauli MIP 354 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 2 Angul Angul Chanaghai MIP 42.6 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 3 Angul Angul Talapada MIP 15.9 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 4 Angul Angul Aida 40.8 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 5 Angul Angul Hatasimili MIP 97.2 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 6 Angul Angul Kadapada 12.3 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 7 Angul Angul Laupal MIP 97.2 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 12-01- 8 Angul Angul Lunahandisagar 48.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 9 Angul Angul Durgapur MIP 24.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 10 Angul Angul Kansabansa MIP 291.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 11 Angul Angul Kukurpetta MIP 176.1 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 12 Angul Angul Kumbhira MIP 80.1 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 13 Angul Angul Balijodi MIP 57.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 14 Angul Angul Jaigarh MIP 218.7 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 15 Angul Angul Sureswari 235.5 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 16 Angul Angul Susab 74.7 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 17 Angul Angul Dalo 39.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 18 Angul Angul Khuntaposi MIP 48.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 12-01- 19 Angul Angul Mankada MIP 607.2 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 20 Balasore Balasore Jalaka 600 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 30-12- 21 Balasore Balasore Gohirakhal 246.9 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 22 Balasore Balasore Kalyani 72 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 23 Balasore Balasore Jamudihi MIP 20.1 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 24 Balasore Balasore Sitapatipur MIP 29.7 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 25 Balasore Balasore Dhadhaya 23.4 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 12-01- 26 Balasore Balasore Meghamadhab 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 27 Balasore Balasore Sindhua 66 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 30-12- 28 Bargarh Bargarh Jampali Kata 21.9 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 30-12- 29 Bargarh Bargarh Chourasianallah 19.5 Preparation NCB NA No 2012 15-03-13 25-03-13 Review Under Post 20-12- 30 Bargarh Bargarh Bardol Nuakata 12.3 Preparation NCB NA No 2012 28-02-13 15-03-13 Review Under Post 20-12- 31 Bargarh Bargarh Birmal Kata 12.3 Preparation NCB NA No 2012 28-02-13 15-03-13 Review Under Post 05-01- 32 Bargarh Bargarh Gopalpur Kata 12.3 Preparation NCB NA No 2013 25-02-13 10-03-13 Review Under Post 05-01- 33 Bargarh Bargarh Nangal Kata 12 Preparation NCB NA No 2013 25-02-13 10-03-13 Review Under Post 20-12- 34 Bargarh Bargarh Batterma 30 Preparation NCB NA No 2012 28-02-13 15-03-13 Review Under Post 20-12- 35 Bargarh Bargarh Jhagadjhal 60.6 Preparation NCB NA No 2012 28-02-13 15-03-13 Review Under Post 10-01- 36 Boudh Boudh Ainthapada MIP 231.9 Preparation NCB NA No 2013 25-02-13 10-03-13 Review Under Post 05-01- 37 Boudh Boudh Birigada MIP 120 Preparation NCB NA No 2013 02-03-13 15-03-13 Review Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 20-01- 38 Boudh Boudh Chhataranga MIP 78 Preparation NCB NA No 2013 25-02-13 10-03-13 Review Under Post 10-01- 39 Boudh Boudh Domkutch MIP 120 Preparation NCB NA No 2013 25-02-13 15-03-13 Review Under Post 15-01- 40 Boudh Boudh Kukuteswar MIP 171.6 Preparation NCB NA No 2013 25-02-13 15-03-13 Review Under Post 30-01- 41 Boudh Boudh Laigaon MIP 309 Preparation NCB NA No 2013 15-03-13 28-03-13 Review Under Post 42 Boudh Boudh Laxmanpur MIP 91.2 Preparation NCB NA No 10-01-13 05-03-13 15-03-13 Review Under Post 30-12- 43 Boudh Boudh Baragochha 133.5 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 15-12- 44 Boudh Boudh Goipitha MIP 18 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-01- 45 Boudh Boudh Penajore MIP 121.2 Preparation NCB NA No 2013 15-03-13 18-03-13 Review Under Post 30-12- 46 Cuttack Cuttack Bishibandha 78.9 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 47 Cuttack Cuttack Champia 72.9 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 48 Cuttack Cuttack Laxmibandha 255 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 49 Cuttack Cuttack Sankha 72.9 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 50 Cuttack Cuttack Brahmanidei 36.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 51 Cuttack Cuttack Kelibandha 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 52 Cuttack Cuttack Goda Gauduni 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 53 Cuttack Cuttack Gangajal 48.6 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 54 Cuttack Cuttack Badabil 18.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 55 Cuttack Cuttack Jharananalla 36.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 12-01- 56 Cuttack Cuttack Karada 68.1 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 12-01- 57 Cuttack Cuttack Nareijani 133.5 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 58 Cuttack Cuttack Chamundapali 18.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 59 Cuttack Cuttack Kusunpur 267 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 60 Cuttack Cuttack Sunamunhin 43.8 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 05-01- 61 Ganjam Ganjam Chhamunda 308.4 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 20-12- 62 Jharsuguda Jharsuguda Bhoimunda 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 20-12- 63 Jharsuguda Jharsuguda Jharkata 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 20-12- 64 Jharsuguda Jharsuguda Jamboonnalla 97.2 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 05-01- 65 Jharsuguda Jharsuguda Palasada 24 Preparation NCB NA No 2013 28-02-13 15-03-13 Review Under Post 05-01- 66 Jharsuguda Jharsuguda Attabira 24 Preparation NCB NA No 2013 28-02-13 15-03-13 Review Under Post 12-01- 67 Jharsuguda Jharsuguda Bhangamunda Kata 22.2 Preparation NCB NA No 2013 10-03-13 20-03-13 Review Under Post 12-01- 68 Jharsuguda Jharsuguda Chandinimal 28.5 Preparation NCB NA No 2013 10-03-13 20-03-13 Review Under Post 30-01- 69 Jharsuguda Jharsuguda Hatianalla 642.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 30-12- 70 Khurda Khurda Gandhinalla 46.8 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 71 Khurda Khurda Biradiabundha 45.9 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 72 Khurda Khurda Biswalibundha 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 73 Khurda Khurda Jogibandha (Godi) 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 74 Khurda Khurda Katinakhunti 18 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 75 Khurda Khurda Khuntabandha 14.1 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 30-12- 76 Khurda Khurda Nachhiberini 12.3 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 77 Khurda Khurda Siko 97.2 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 30-12- 78 Khurda Khurda Kumarkhunti 115.5 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Badabandha Under Post 30-12- 79 Khurda Khurda 13.5 Preparation NCB NA No 2012 25-02-13 15-03-13 (Mardabadi) Review Under Post 12-01- 80 Khurda Khurda Hada 185.4 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 30-12- 81 Khurda Khurda Kochilabandha 26.1 Preparation NCB NA No 2012 25-02-13 15-03-13 Review Under Post 12-01- 82 Khurda Khurda Manibandha 24.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 83 Khurda Khurda Pata bundha 85.8 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 84 Khurda Khurda Jayamangal 182.1 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 85 Khurda Khurda Balibundha 12.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Bijipur Under Post 12-01- 86 Khurda Khurda 77.7 Preparation NCB NA No 2013 15-03-13 25-03-13 (Panchapalli) Review Under Post 12-01- 87 Khurda Khurda Hadabandha 18 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 88 Khurda Khurda Kajalganda 156 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 89 Khurda Khurda Pallabundha 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 90 Khurda Khurda Badjore 15.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 91 Khurda Khurda Hanumantia 72.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 92 Khurda Khurda Orabarsingh 34.2 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 12-01- 93 Khurda Khurda Bhogara 12.3 Preparation NCB NA No 2013 28-02-13 15-03-13 Review Under Post 25-01- 94 Khurda Khurda Chhamania 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Expected Expected Estimated Bid Review by Expected procurement Pre- Domestic Bid Contract Sl.no Division District Name of Projects cost in Document bank Contract Comments method qualification preference opening Signature lakh completed (prior/post) Award Date date date Under Post 25-01- 95 Khurda Khurda Haribhakta 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 96 Khurda Khurda Jhullagada 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 97 Khurda Khurda Kalukha-adia 12.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 98 Khurda Khurda Khajuri-adia 12.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 99 Khurda Khurda Kochilaganda 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 100 Khurda Khurda Malaguni 607.5 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 101 Khurda Khurda Mangaljit 109.2 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 102 Khurda Khurda Niyamakhir 12.6 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 103 Khurda Khurda paikabundha 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 104 Khurda Khurda Sahadajoda 12.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 105 Khurda Khurda Sarabadiha 12.9 Preparation NCB NA No 2013 15-03-13 25-03-13 Review Under Post 25-01- 106 Khurda Khurda Teli Pokhari 12.3 Preparation NCB NA No 2013 15-03-13 25-03-13 Review OFD Works (several packages Direct Post Continuous 107 and each Ha 30,000 0.15 30000 0.12 360.00 31.03.2014 Contracting Review 15.02.2013 package will not exceed Rs. 8 lakhs) Annual Procurement Plan for OCTMP B. Procurement of Goods and Equipments i) SPU Description of Goods /Civil Estimated Unit Sl. Method of Quantity to be Estimated total Review By Expected Bid Works / Non consulting Unit Cost in (Rs.) in No. procurement procured(No) cost (Rs.) in Lakhs Bank Opening Services/ Lakhs 1 2 3 4 5 6 7 8 9 Furnishing of learning center, storage cabinets, workstations and one cabin in SPU. (several 1 packages and each package Shopping LS -- --- 10 Post Review Continues will not exceed Rs. 8 lakhs) including purchase of furniture’s Projector screen , white board, 2 plasma TV for mini and main Shopping LS -- --- 4 Post Review Continues conference room Desktop Computer including 3 Shopping(DGS&D) Nos. 3 0.5 1.5 Post Review January, 2012 Printer 4 Purchase of Coffee machine Local Shopping Nos. 2 0.25 0.5 Post Review December, 2012 Procurement Software for 5 Shopping Nos. --- --- 1 Post Review Continuous server 7 Procurement Tall Software Shopping Nos. --- --- 0.5 Post Review Continuous Procurement of Measurement 8 NCB Nos. 50 Post Review Continuous Devices 9 Procurement Ipad Local shopping Nos. 0.5 Post Review February, 2013 10 Procurement of LCD Projector Local shopping Nos. 0.5 Post Review February, 2013 Procurement equipment for ALSS activitie (Procurement of 11 Shopping/National. Nos. 800.00 Post Review Continues different equipment in separate NCB/Shopping Procurement of Softwares Shopping Nos. 5 Post Review Continues 12 Annual Procurement Plan for OCTMP Procurement of Goods and Equipments ii) DPU Unit Quantity to be Estimated Unit Description of Goods /Civil Works Method of Estimated total Review By Expected Bid Sl. No. procured(No) Cost in (Rs.) in / Non consulting Services/ procurement cost (Rs.) in Lakhs Bank Opening Lakhs 1 2 3 4 5 6 7 8 9 Furniture and fixtures procured at District level (several packages Continuous 1 Shopping/ DGS&D Nos. 12 2.00 24.00 Post Review and each package will not exceed Process Rs. 8 lakhs) Shopping Continuous 2 Procurement of Desktop Nos. 6 0.50 3.00 Post Review (DGS&D) Process 3 Procurement Software for server Shopping Nos. --- --- 1.00 Post Review Continuous Procurement of Goods for ALSS 4 Shopping Nos. --- --- 10.00 Post Review Continuous Unit 5 Selection of Consultants 1. Methods of procurement: Consultancy Services: The following methods of selection will be adopted depending upon size and complexity of assignment, as defined in the Consultancy Guidelines:  Quality and Cost Based Selection (QCBS)  Quality Based Selection (QBS)  Selection under Fixed Budget (FBS)  Least Cost Selection (LCS)  Selection based on Consultant’s Qualifications (CQS)  Single Source Selection (SSS)  Individuals Individual Consultants < US $50,000 Very Small Consultancies [SSS] including NGO services < US $ 100,000 Small Consultancies [CQS] < US $ 200,000 Prior Review:  Consultancy Services: All contracts valued over US $ 100,000 equivalent for firms including NGO services and above US $ 50,000 equivalent for individuals. All contracts to be awarded on Sole Source Selection basis will be subject to prior review. Additionally, prior clearance for TOR and in-principle clearance for following this method, irrespective of value will be required for all contracts, irrespective of value. The Terms of Reference for the independent Auditors, external audit, procurement consultant to be engaged by the OCTMP, would be prior reviewed. The Bank on its part will review the reports of the Auditors in addition to conducting its own post review on sample basis. Post Review: All contracts not covered under prior review will be subject to post award review. Annual Procurement Plan for OCTMP i) Consultancy Services & Training Estimated Estimated Description of Goods Sl. Method of Contract Unit Cost total cost Review By Expected Bid /Civil Works / Non Nos. No. procurement Type in (Rs.) in (Rs.) in Bank Opening consulting Services/ Lakhs Lakhs A: 1 2 3 4 5 6 7 8 District Project Prior 1 CQS TB 3 0.30 10.80 Completed Manager Review District Level Individual Post 2 Engineering TB 4 0.25 12 Continuous Consultant Review Consultant 3 Third Party QA QC Agreement Prior A Central Zone QCBS TB --- --- 348 signed in June, Review 2012 Agreement Prior B North Zone QCBS TB --- --- 268.00 signed on 1st Review Sept, 2012 Survey Design & Post Taken up 4 SSS TB --- --- 30.00 Drawing Review departmentally Creation of GIS Post Continuous 5 QCBS LS -- --- 28.00 Database Review Process Assessment of Affected area & Post Continuous 6 CQS LS --- --- 10.00 preparation of Review Process inundation Engagement of Staff Individual Post 7 TB 48 1.20 57.60 Feb, 2013 at Cluster level Consultant Review 4.80 Prior 8 Technical Consultant SSS TB 1 4.80 In position Review Manager Prior 9 SSS TB 1 4.20 4.2 In position Procurement Review Capacity Building Individual Prior 10 TB 1 7.20 7.2 In position Consultant Consultant Review Capacity Building Prior 11 Personnel for Pani CQS LS 1 ----- 161.00 Completed Review Panchayat Post Bids to be 12 ASO CQBS TB 3 12 36.00 Review invited Prior 13 Internal Audit Lump Sum LS 2 7 14.00 Completed Review Post 14 External Audit Lump Sum LS 1 6.00 6.00 Completed Review Crop Water Post 15 SSS LS ---- ---- 5.00 April, May 2013 Management Review Capacity Building of Prior Entrusted to IIT, 16 Engineers of MI SSS LS --- --- 50.00 Review Roorkee Organization Entrusted to Capacity Building of Prior 18 SSS LS ---- ----- 44.00 XIMB since Feb, Project Personnel Review 2012 Ground Water Prior 19 Individual Nos. 20 1.20 24.00 To be taken up Monitoring Review Volumetric Measurement & Prior To be taken 20 SSS LS 1 5.00 5.00 Pricing of Irrigation Review up Water Technical back- stopping for Prior December, 21 SSS LS 1 30.00 30.00 development of Review 2012 Market event Conceptualizing as well as implementing of Prior December, 22 CQS LS 1 50.00 50.00 value-chain Review 2012 development initiative