Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) Can Tho Urban Development and Resilience (P152851) EAST ASIA AND PACIFIC | Vietnam | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 4 | ARCHIVED on 09-Feb-2018 | ISR31232 | Implementing Agencies: Can Tho City People’s Committee, Can Tho City People's Committee Key Dates Key Project Dates Bank Approval Date:24-Mar-2016 Effectiveness Date:30-Nov-2016 Planned Mid Term Review Date:07-May-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2022 Revised Closing Date:30-Jun-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document)

The Project Development Objective is to reduce flood risk in the urban core area, improve connectivity between the city center and the new low risk urban growth areas, and enhance the capacity of city authorities to manage disaster risk in Can Tho City.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Flood risk management, and environmental sanitation:(Cost $120.90 M) Urban corridor development:(Cost $78.90 M) Spatial planning platform and financial and social protection instruments:(Cost $6.80 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial 2/9/2018 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) Implementation Status and Key Decisions The project is entering its second year of implementation and is picking up implementation progress especially on Component 2 for urban transport improvement. There are still bottlenecks related to institutional and technical capacity, project management issues, slow procurement and slow resettlement. No measurable results are expected until Year 3 of implementation except for some minor training in Year 2 (2017). The next mission is scheduled for April- May, 2018. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  Moderate  Moderate Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  Substantial  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  High  High Fiduciary  Substantial  Substantial  Substantial Environment and Social  Substantial  Substantial  Substantial Stakeholders  Low  Low  Low Other  --  --  -- Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Increase in urban core land area protected from rainfall flooding for a 10-year return period and riverine flooding for 100-year return period (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,675.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  Reduction in travel time between urban core and Cai Rang center (percentage change) (Percentage, Custom) 2/9/2018 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  From NK to IC3 (% change) (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  From NVC-Bus (percent change) (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  Number of Dept. utilized Spatial Planning and RiskInfo Platform (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 7.00 Date 30-Jun-2016 -- 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  Number of direct beneficiaries, defined as people living in Urban Core protected against 10-year return period flood risk ( of which are female (#)) (Number, Custom) 2/9/2018 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 420,000.00 Date 30-Jun-2016 -- 27-Nov-2017 30-Jun-2022 PHINDPDOTBL  Number of direct beneficiaries, of which # are female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 216,000.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 Overall Comments Intermediate Results Indicators PHINDIRITBL  Length of new and upgraded embankment installed (Meter(m), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10,000.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Length of new and upgraded sewers/pipe installed (Meter(m), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 12,000.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 2/9/2018 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) PHINDIRITBL  Length of canals improved (Meter(m), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 14,500.00 Date 30-Jun-2016 -- 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Roads constructed, non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.44 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Number of bridges built which include sidewalks, connecting the urban core and Cai Rang (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Public transport feasibility and strategy completed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Public Transport Value 0.00 not started yet not started yet Feasibility Study Completed Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 2/9/2018 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) PHINDIRITBL  Spatial Planning and Riskinfo Database Established (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Beneficiaries of community-based flood early warning training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50,000.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Participants in consultation activities during project implementation (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,500.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 PHINDIRITBL  Participants in consultation activities during project implementation - female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,250.00 Date 30-Jun-2016 01-Aug-2017 27-Nov-2017 30-Jun-2022 Overall Comments 2/9/2018 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P152851 IBRD-85980 Effective USD 125.00 125.00 0.00 5.31 119.69 4.3% P152851 IDA-57790 Effective USD 125.00 125.00 0.00 7.00 123.26 5.4% P152851 TF-A3723 Effective USD 2.00 2.00 0.00 0.00 2.00 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152851 IBRD-85980 Effective 24-Mar-2016 11-Jul-2016 30-Nov-2016 30-Jun-2022 30-Jun-2022 P152851 IDA-57790 Effective 24-Mar-2016 11-Jul-2016 30-Nov-2016 30-Jun-2022 30-Jun-2022 P152851 TF-A3723 Effective 29-Sep-2017 29-Sep-2017 29-Sep-2017 30-Jun-2021 30-Jun-2021 Cumulative Disbursements Restructuring History 2/9/2018 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Can Tho Urban Development and Resilience (P152851) There has been no restructuring to date. Related Project(s) There are no related projects. 2/9/2018 Page 8 of 8 Public Disclosure Copy