Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) LATIN AMERICA AND CARIBBEAN | Belize | Energy & Extractives Global Practice | Global Environment Project | Investment Project Financing | FY 2017 | Seq No: 1 | ARCHIVED on 28-Dec-2016 | ISR26121 | Implementing Agencies: Ministry of Finance, Public Service, Energy and Public Utilities, Belize Electricity Limited (BEL) Key Dates Key Project Dates Bank Approval Date:12-Sep-2016 Effectiveness Date:06-Dec-2016 Planned Mid Term Review Date:17-Dec-2018 Actual Mid-Term Review Date:-- Original Closing Date:31-Jul-2020 Revised Closing Date:31-Jul-2020 Global Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the proposed Energy Resilience for Climate Adaptation Project is to demonstrate solutions that enhance the resilience of the energy system to adverse weather and climate change impacts. This will be collectively achieved by implementing a wide- ranging and complementary set of activities that include pilot initiatives, infrastructure hardening, and analytical and planning efforts. Has the Global Environmental Objective been changed since Board Approval of the Project Objective? No Components Name Component 1: Long-Term Planning and Capacity Building for Adaptation:(Cost $2.79 M) Component 2: Demonstration Measures to Enhance Resilience of Energy Sector:(Cost $8.44 M) Component 3: Project Implementation Support and Information Dissemination for Knowledge Sharing:(Cost $0.59 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Satisfactory Overall Implementation Progress (IP)  --  Satisfactory Overall Risk Rating  --  Moderate 12/28/2016 Public Disclosure Copy Page 1 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) Implementation Status and Key Decisions The GEF Grants to Belize and Belize Electricity Limited became effective on December 6, 2016. Implementation of the project will be starting soon. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  --  Moderate Macroeconomic  Low  --  Low Sector Strategies and Policies  Moderate  --  Moderate Technical Design of Project or Program  Moderate  --  Moderate Institutional Capacity for Implementation and Sustainability  Substantial  --  Substantial Fiduciary  Moderate  --  Moderate Environment and Social  Low  --  Low Stakeholders  Moderate  --  Moderate Other  --  --  -- Overall  Moderate  --  Moderate Results Global Environmental Objective Indicators PHINDGEOTBL  Methodologies and procedures to incorporate climate resilience in long-term planning of energy infrastructure and systems developed and adopted(Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 12/28/2016 Public Disclosure Copy Page 2 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) PHINDGEOTBL  Transmission network segmented and protected against cascading line faults(Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 PHINDGEOTBL  Generation sources available for dispatch despite line faults(Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 -- 5.00 7.00 PHINDGEOTBL  Consumers with enhanced security of electricity supply (reduced outages) due to weather events(Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value -- -- 0.00 274,000.00 PHINDGEOTBL  Generation capacity available for dispatch despite line faults(Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 82.50 -- 82.50 110.00 12/28/2016 Public Disclosure Copy Page 3 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) PHINDGEOTBL  Weak transmission sections in the system reinforced to be more resilient(Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 160.00 Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 Overall Comments Intermediate Results Indicators PHINDIRITBL  Strengthened long-term planning capabilities for the energy sector (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.00 Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 PHINDIRITBL  Improved availability of weather and hydrological information (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 29.00 Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 PHINDIRITBL  Appropriate technologies identified to be used for transmission line design for different terrain types (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 12/28/2016 Public Disclosure Copy Page 4 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) PHINDIRITBL  Options for improving BEL's vegetation managment practices identified (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 PHINDIRITBL  Regional stakeholder and citizen engagement conferences held to evaluate and disseminate lessons learned and results achieved in project for enhancing energy resilience (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2.00 Date 01-Nov-2016 -- 27-Dec-2016 31-Jul-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P149522 TF-A2887 Effective USD 5.62 5.62 0.00 0.00 5.62 0% P149522 TF-A2888 Effective USD 2.38 2.38 0.00 0.00 2.38 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P149522 TF-A2887 Effective 12-Sep-2016 22-Sep-2016 06-Dec-2016 31-Jul-2020 31-Jul-2020 P149522 TF-A2888 Effective 12-Sep-2016 22-Sep-2016 06-Dec-2016 31-Jul-2020 31-Jul-2020 Cumulative Disbursements 12/28/2016 Public Disclosure Copy Page 5 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Energy Resilience for Climate Adaptation (GEF/SCCF) (P149522) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/28/2016 Public Disclosure Copy Page 6 of 6