Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) Corridor Highway Project (P145361) MIDDLE EAST AND NORTH AFRICA | Yemen, Republic of | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 3 | ARCHIVED on 16-Jun-2015 | ISR19403 | Implementing Agencies: Ministry of Public Works and Highways Key Dates Key Project Dates Board Approval date:02-Jun-2014 Effectiveness Date:30-Oct-2014 Planned Mid Term Review Date:30-Sep-2015 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2019 Revised Closing Date:30-Jun-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is "improved transport connectivity and safety on the targeted section of the transport corridor between Aden and Taiz". Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Highway Construction:(Cost $150.00 M) Institutional Support and Strengthening:(Cost $22.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Unsatisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Unsatisfactory Overall Risk Rating  Substantial  High Implementation Status and Key Decisions 6/16/2015 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) Before the suspension of disbursements by the Bank, the project was progressing reasonably well, despite the difficult operating environment in Yemen. Pre-qualification of contractors for highway construction had been completed. The procurement processes for most other contracts under the project's components (civil works and institutional strengthening activities) were underway. The Grant agreement had been signed and the grant became effective on October 31, 2014. It should be noted that before any construction can take place, the land acquisition process must first be completed. However, even before the suspension of disbursements, the Government did not make any money available for the compensation to be paid to persons affected by land acquisition and resettlement. If this situation persists, the project will be stalled even when the suspension of disbursements is lifted. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  High  High Macroeconomic  --  High  High 6/16/2015 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Low  Low Institutional Capacity for Implementation and Sustainability  --  Moderate  Moderate Fiduciary  --  Moderate  Moderate Environment and Social  --  Substantial  High Stakeholders  --  Moderate  Moderate Other  --  --  -- Overall  --  Substantial  High Results Project Development Objective Indicators PHINDPDOTBL  Decrease in Vehicle Operating Costs for traffic between Aden and Noubat Dokaim. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 100.00 100.00 93.00 Date 26-Dec-2013 10-Dec-2014 03-Jun-2015 30-Jun-2019 PHINDPDOTBL  Traffic fatalities on road corridor between Aden and Noubat Dokaim. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 74.00 -- -- 50.00 Date 26-Dec-2013 10-Dec-2014 03-Jun-2015 30-Jun-2019 PHINDPDOTBL  Decrease in travel time between Aden and Noubat Dokaim. (Minutes, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 60.00 60.00 60.00 40.00 Date 26-Dec-2013 10-Dec-2014 10-Dec-2014 30-Jun-2019 6/16/2015 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) PHINDPDOTBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4000000.00 Date 26-Dec-2013 10-Dec-2014 10-Dec-2014 30-Jun-2019 PHINDPDOTBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Overall Comments Intermediate Results Indicators PHINDIRITBL  Roads constructed, Rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 55.00 Date 26-Dec-2013 10-Dec-2014 10-Dec-2014 30-Jun-2019 PHINDIRITBL  Number of MPWH staff trained. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 12-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 6/16/2015 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) PHINDIRITBL  Earthworks completion rate. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 12-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 PHINDIRITBL  Definition and establishment of an institutional structure for the management, operation and maintenance of the new Corridor Highway. (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 12-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 PHINDIRITBL  No. of person-days of work created. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1280000.00 Date 12-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 PHINDIRITBL  Fiber Optic Duct installed. (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 12-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 6/16/2015 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) PHINDIRITBL  Pavement completion rate (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 25-Feb-2014 10-Dec-2014 10-Dec-2014 30-Jun-2019 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P145361 IDA-H9430 Effective XDR 86.30 86.30 0.00 0.00 86.30 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P145361 IDA-H9430 Effective 02-Jun-2014 31-Aug-2014 30-Oct-2014 30-Jun-2019 30-Jun-2019 Cumulative Disbursements 6/16/2015 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Corridor Highway Project (P145361) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/16/2015 Page 7 of 7 Public Disclosure Copy