PLAN DE ADQUISICIONES AR Buenos Aires Flood risk management (P145686) Argentina, IBRD/IDA, FY: 2016, Team Leader(s): Maria Catalina Ramirez, Christophe Prevost PROCUREMENT Argentina : AR Flood Risk Management Support Project for the City of Buenos Aires PLAN General Information Country: Argentina Banks Approval Date of the Original Procurement Plan: 2016-11-03 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-05 Project ID: P145686 GPN Date: Project Name: AR Flood Risk Management Support Project for the City of Buenos Aires Loan / Credit No: IBRD / 86280 Executing Agency(ies): Multilateral Credit Organizations Financing Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UFOMC-2871-CW-RFB / Single Stage - One Agua y Cloacas en Nueva IBRD / 86280 Flood Mitigation Infrastructure Post Request for Bids Open - National 520,000.00 0.00 Canceled 2016-05-19 2016-05-24 2016-07-05 2016-08-04 2016-09-08 2017-03-07 Envelope Esperanza AR-UFOMC-2890-CW-RFB / Single Stage - One Obras complementarias de IBRD / 86280 Flood Mitigation Infrastructure Post Request for Bids Open - National 2,912,000.00 0.00 Canceled 2016-08-19 2016-08-24 2016-10-05 2016-11-04 2016-12-09 2017-06-07 Envelope mejoramiento en Lago Soldati AR-UFOMC-3473-CW-RFB / Single Stage - One Under Construcción de ARTEH, ramal IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - International 36,582,000.00 0.00 2014-06-23 2014-06-28 2014-08-09 2014-09-08 2016-11-30 2014-10-13 2015-04-11 Envelope Implementation Asturias Sur, Nágera y Villa 6 AR-UFOMC-3720-CW-RFB / Single Stage - One Pending Construcción segundo emisario IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - International Y 158,080,000.00 0.00 2015-06-02 2015-08-18 2015-08-18 2015-06-07 2015-10-27 2015-11-26 2015-12-31 2017-06-23 Envelope Implementation Aº Vega AR-UFOMC-20566-CW-RFB / Obras de Desagües Pluviales de ñ z - Ramal la Cuenca Cildáe Martí y Castañares-Primera Etapa, mediante la ejecución de Single Stage - One Pending IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - National 20,000,000.00 0.00 2017-11-01 2017-11-06 2017-12-18 2018-01-17 2018-02-21 2018-08-20 conductos rectangulares y Envelope Implementation circulares con sus respectivas cámaras, sumideros, nexos y demás componentes secundarios AR-UFOMC-3474-CW-RFB / Construcción de tres grupos de Single Stage - One IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - International 70,002,400.00 0.00 Canceled 2017-06-01 2017-06-06 2017-09-11 2017-07-18 2017-08-17 2017-09-21 2018-03-20 ramales secundarios Aº Envelope Maldonado AR-UFOMC-28498-CW-RFB / Construcción de tres grupos de Single Stage - One Under IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - International 70,002,400.00 0.00 2017-06-01 2017-06-06 2017-07-18 2017-08-17 2017-09-21 2018-03-20 ramales secundarios A° Envelope Implementation Maldonado AR-UFOMC-40376-CW-RFB / Sub - Componente 2.2 Construcción de tres grupos de ramales C - D - E para la Single Stage - One cuenca del Arroyo Maldonado: IBRD / 86280 Flood Mitigation Infrastructure Prior Request for Bids Open - National 20,000,000.00 0.00 Under Review 2018-01-09 2018-01-14 2018-03-06 2018-04-05 2018-05-10 2018-11-06 Envelope Llamado a LPN para la obra "Construcción de los Ramales Secundarios del Arroyo Maldonado GRUPO C" GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UFOMC-2868-GO-RFQ / Request for Single Stage - One Vehículo aéreo de observación IBRD / 86280 Flood Mitigation Infrastructure Post Open - National 50,000.00 0.00 Canceled 2016-04-27 2016-06-22 2016-12-19 Quotations Envelope no tripulado (Drone) AR-UFOMC-2866-GO-RFQ / Institutional Development for Request for Single Stage - One IBRD / 86280 Post Open - National 20,000.00 0.00 Canceled 2016-08-17 2016-10-12 2017-04-10 Moto triciclo para cargas (x 2) Flood Risk Management Quotations Envelope AR-UFOMC-2869-GO-RFB / Institutional Development for Single Stage - One IBRD / 86280 Post Request for Bids Open - National 480,000.00 0.00 Canceled 2016-04-11 2016-04-16 2016-05-28 2016-06-27 2016-08-01 2017-01-28 Vehículos anfibio (x 4) Flood Risk Management Envelope AR-UFOMC-2874-GO-RFB / Institutional Development for Single Stage - One IBRD / 86280 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2016-09-11 2016-09-16 2016-10-28 2016-11-27 2017-01-01 2017-06-30 Trailer para carga general (x 3) Flood Risk Management Envelope AR-UFOMC-2870-GO-RFB / Equipamiento p/emergencias Institutional Development for Single Stage - One (varios lotes): Grupos IBRD / 86280 Post Request for Bids Open - National 670,000.00 0.00 Canceled 2016-05-11 2016-05-16 2016-06-27 2016-07-27 2016-08-31 2017-02-27 Flood Risk Management Envelope electrógenos x 12 y Grupos portátiles de iluminación x 4. AR-UFOMC-2881-GO-RFB / Institutional Development for Single Stage - One Pending Equipo p/inspección de IBRD / 86280 Post Request for Bids Open - National 170,000.00 0.00 2016-05-11 2016-05-16 2016-06-27 2016-07-27 2016-08-31 2017-02-27 Flood Risk Management Envelope Implementation conductos AR-UFOMC-2873-GO-RFB / Institutional Development for Single Stage - One IBRD / 86280 Post Request for Bids Open - National 480,000.00 0.00 Canceled 2016-05-21 2016-05-26 2016-07-07 2016-08-06 2016-09-10 2017-03-09 Maquinaria pesada Flood Risk Management Envelope AR-UFOMC-2897-GO-RFB / Institutional Development for Single Stage - One Pending IBRD / 86280 Post Request for Bids Open - National 290,000.00 0.00 2016-05-21 2016-05-26 2016-07-07 2016-08-06 2016-09-10 2017-03-09 Equipo desobstructor de tuberías Flood Risk Management Envelope Implementation AR-UFOMC-3470-GO-RFB / Camiones (4 lotes): camión de salvataje (de vadeo), camión Institutional Development for Single Stage - One IBRD / 86280 Post Request for Bids Open - National 1,452,000.00 0.00 Canceled 2016-04-13 2016-04-18 2016-05-30 2016-06-29 2016-08-03 2017-01-30 furgón, camión de rescate con Flood Risk Management Envelope plataforma, pick uo 4x4 doble cabina (x4) Page 1 AR-UFOMC-20563-GO-RFQ / Institutional Development for Request for Single Stage - One Pending IBRD / 86280 Post Open - National 50,000.00 0.00 2017-01-20 2017-03-17 2017-09-13 Equipamiento (varios) Flood Risk Management Quotations Envelope Implementation AR-UFOMC-23766-GO-RFQ / Institutional Development for Single Stage - One Pending IBRD / 86280 Post Request for Bids Open - National 300,000.00 0.00 2017-06-01 2017-06-06 2017-07-18 2017-08-17 2017-09-21 2018-03-20 Software Science on sphere Flood Risk Management Envelope Implementation AR-UFOMC-23762-GO-RFB / Institutional Development for Single Stage - One Pending VEHICULOS TERRESTRES IBRD / 86280 Post Request for Bids Open - National 997,000.00 0.00 2017-09-18 2017-09-23 2017-11-04 2017-12-04 2018-01-08 2018-07-07 Flood Risk Management Envelope Implementation PARA DEFENSA CIVIL AR-UFOMC-30883-GO-RFB / ADQUISICIÓN EQUIPOS Institutional Development for Single Stage - One Pending NÁUTICOS PARA LA IBRD / 86280 Post Request for Bids Open - National 369,000.00 0.00 2017-10-17 2017-10-22 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Flood Risk Management Envelope Implementation EMERGENCIA DE DEFENSA CIVIL NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UFOMC-2885-NC-RFQ / Institutional Development for Request for Single Stage - One Pending Logística para el seminario IBRD / 86280 Post Open - National 100,000.00 0.00 2017-04-25 2017-06-20 2017-12-17 Flood Risk Management Quotations Envelope Implementation internacional CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UFOMC-2894-CS-QCBS / Quality And Cost- Pending Plan de monitoreo y operación IBRD / 86280 Flood Mitigation Infrastructure Post Open - National 400,000.00 0.00 2016-08-15 2016-09-05 2016-10-19 2016-11-16 2016-12-16 2017-01-20 2017-02-24 2018-02-24 Based Selection Implementation de aguas pluviales AR-UFOMC-2888-CS-QCBS / Quality And Cost- Pending IBRD / 86280 Project Management Post Open - National 250,000.00 0.00 2018-07-15 2018-08-05 2018-09-18 2018-10-16 2018-11-15 2018-12-20 2019-01-24 2020-01-24 Evaluación de medio término Based Selection Implementation AR-UFOMC-2891-CS-QCBS / Quality And Cost- Pending IBRD / 86280 Flood Mitigation Infrastructure Post Open - National 260,000.00 0.00 2020-06-15 2020-07-06 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 Evaluación final Based Selection Implementation AR-UFOMC-2876-CS-LCS / Pending IBRD / 86280 Project Management Prior Least Cost Selection Open - National 650,000.00 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-05-23 Auditoría 2da etapa Implementation AR-UFOMC-2872-CS-QCBS / Institutional Development for Quality And Cost- Pending IBRD / 86280 Post Open - National 550,000.00 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-15 2017-07-15 2017-08-19 2017-09-23 2018-09-23 Campaña publicitaria (diseño) Flood Risk Management Based Selection Implementation AR-UFOMC-3471-CS-LCS / Pending Auditoría 1ra etapa (es una IBRD / 86280 Project Management Post Least Cost Selection Open - National 50,000.00 0.00 2015-03-02 2015-03-23 2015-05-06 2015-06-03 2015-07-03 2015-08-07 2015-09-11 2016-03-09 Implementation auditoría financiera). AR-UFOMC-20569-CS-QCBS / Institutional Development for Quality And Cost- IBRD / 86280 Post Open - National 450,000.00 0.00 Canceled 2016-10-15 2016-11-05 2016-12-19 2017-01-16 2017-02-15 2017-03-22 2017-04-26 2018-04-26 Modelo Probabilístico de Riesgo Flood Risk Management Based Selection AR-UFOMC-20771-CS-QCBS / Institutional Development for Quality And Cost- Pending Mecanismo de financiamiento del IBRD / 86280 Prior Open - International 2,700,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-04 2017-12-04 2018-01-08 2018-02-12 2019-02-12 Flood Risk Management Based Selection Implementation riesgo AR-UFOMC-28316-CS-QBS / Revisión del Proyecto Ejecutivo Quality Based IBRD / 86280 Project Management Prior Open - National 1,500,000.00 0.00 Under Review 2017-09-01 2017-09-22 2017-09-14 2017-11-05 2017-12-03 2018-01-02 2018-02-01 2018-03-08 2019-03-08 de los Grupos D y E + Ramales Selection Vega AR-UFOMC-20564-CS-QCBS / Institutional Development for Quality And Cost- Pending Inspección segundo emisario Aº IBRD / 86280 Prior Open - International 7,332,000.00 0.00 2013-07-20 2013-08-10 2013-09-23 2013-10-21 2013-11-20 2013-12-25 2014-01-29 2015-01-29 Flood Risk Management Based Selection Implementation Vega AR-UFOMC-47959-CS-QCBS / SERVICIOS DE CONSULTORÍA PARA LA ELABORACIÓN DEL DISEÑO DE OBRAS DE Quality And Cost- Pending IBRD / 86280 Flood Mitigation Infrastructure Post Open - National 981,572.00 0.00 2018-02-14 2018-03-20 2018-05-03 2018-05-31 2018-06-30 2018-08-04 2018-09-08 2019-09-08 EVACUACIÓN DE DESAGÜES Based Selection Implementation DE LAS CUENCAS ALTAS DE LOS ARROYOS MALDONADO Y CILDAÑEZ INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UFOMC-2878-CS-INDV / Contratación de consultores p/ Institutional Development for Individual Consultant Pending IBRD / 86280 Post Open 65,000.00 0.00 2017-01-15 2017-03-05 2017-03-26 2017-04-30 2017-10-27 talleres de concientización a la Flood Risk Management Selection Implementation sociedad civil AR-UFOMC-2879-CS-INDV / Contratación de consultores p/ Institutional Development for Individual Consultant Pending IBRD / 86280 Post Open 65,000.00 0.00 2017-01-15 2017-03-05 2017-03-26 2017-04-30 2017-10-27 talleres de concientización a los Flood Risk Management Selection Implementation profesionales del rubro. AR-UFOMC-20568-CS-INDV / Institutional Development for Individual Consultant Pending Fortalecimiento del Programa IBRD / 86280 Post Open 10,000.00 0.00 2017-01-15 2017-03-05 2017-03-26 2017-04-30 2017-10-27 Flood Risk Management Selection Implementation Primeros Respondedores AR-UFOMC-2883-CS-INDV / Institutional Development for Individual Consultant Pending Consultorías varias (x 14) para la IBRD / 86280 Post Open 1,920,000.00 0.00 2016-01-02 2016-02-20 2016-03-12 2016-04-16 2016-10-13 Flood Risk Management Selection Implementation UEP Page 2