Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) Dedicated Grant Mechanism for Local Communities Project (P145316) AFRICA | Ghana | Environment & Natural Resources Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2017 | Seq No: 2 | ARCHIVED on 02-Mar-2018 | ISR29889 | Implementing Agencies: KASA, Natinal Steering Committee, Solidaridad, Solidaridad Key Dates Key Project Dates Bank Approval Date:26-Apr-2017 Effectiveness Date:-- Planned Mid Term Review Date:13-Nov-2019 Actual Mid-Term Review Date:-- Original Closing Date:-- Revised Closing Date:-- Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to strengthen knowledge and practices of targeted local communities in the Select Regions of the Member Country in REDD+processes and sustainable forest management. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Capacity Building for Local Communities:(Cost $1.00 M) Component 2: Sustainable and Adaptive Community Initiatives:(Cost $3.50 M) Component 3: Project Governance, Monitoring, and Evaluation:(Cost $1.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Satisfactory Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions 3/2/2018 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) The project was effective August 18th, 2017. The project launch was held on February 5th, 2018 in Sunyani, Ghana. The event was attended by 400 guests and included the Government of Ghana (implicated Ministries), Solidaridad (the National Executing Agency), the National Steering Committee (NSC), the World Bank, the DGM's Global Change Ambassador (Okyeame Kwame), NGOs and a large contingent of community members including chiefs and queen mothers from the two project regions (Brong Ahafo and Western Region). Project implementation has already commenced in the regions with community outreach and trainings (Facebook @GhaDGM). Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Substantial  Substantial  Substantial Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Low  Low  Low Technical Design of Project or Program  Substantial  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  Substantial  Substantial Fiduciary  Substantial  Substantial  Substantial Environment and Social  Moderate  Moderate  Moderate Stakeholders  Substantial  Substantial  Substantial Other  --  --  -- Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Change to sustainable practices among community members following basic training sensitization and education on REDD+ and climate change (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  full sun cocoa to shade cocoa (Percentage, Custom Breakdown) 3/2/2018 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  non-renewable energy to sustainable sources (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  increase in tree plantings (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 20.00 Date 02-Mar-2016 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Proportion of grantees who use G-DGM Community grants to implement/practice sub-projects that contribute directly to FIP and REDD+ objectives (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75.00 Date 02-Mar-2016 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Proportion of grantees who use CBO grants to implement/practice sub-projects that contribute directly to FIP and REDD+ objectives (Percentage, Custom Supplement) 3/2/2018 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 PHINDPDOTBL  Proportion of grantees who use G-DGM Individual grants to implement/practice sub-projects that contribute directly to FIP and REDD+ objectives (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 65.00 PHINDPDOTBL  Proportion of grantees who use G-DGM Community grants to implement/practice sub-projects that contribute directly to FIP and REDD+ objectives (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 65.00 PHINDPDOTBL  65 percent of community initiatives are successfully completed and achieve their stated objectives, which are consistent with REDD+ and FIP objectives (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 65.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Project beneficiaries who, without grants, apply knowledge acquired through sensitization/basic training to implement sub- projects that contribute directly to FIP and REDD+ objectives (Percentage, Custom) 3/2/2018 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 02-Apr-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Percentage of grantees that express satisfaction with the project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Percentage of women and migrants (of the total) grantees that execute subprojects (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Grievances registered related to delivery of project benefits addressed (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDPDOTBL  Grievances related to delivery of project benefits that are addressed-(number) (Number, Custom Supplement) 3/2/2018 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Overall Comments The baseline study was just completed and cleared a few days ago. The data will be used to update the results indicators baseline numbers as relevant. This will be reflected in the next ISR as it has not yet been done by the project team. Intermediate Results Indicators PHINDIRITBL  Proportion of selected community members who successfully complete basic training in REDD+/climate change (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDIRITBL  Number of Basic Training Participants (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1,100.00 PHINDIRITBL  Proportion of basic training participants that submit a proposal for funding(percentage) (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 3/2/2018 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) PHINDIRITBL  Total number of community members sensitized (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 11,000.00 PHINDIRITBL  Number of Grants Awarded to Basic Training participants (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 182.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDIRITBL  % of basic training participants exposed to successful REDD+ practices at national, regional or international levels (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 PHINDIRITBL  Number of result stories produced by grant recipients presented during local, regional and global knowledge sharing events (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 3/2/2018 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Dedicated Grant Mechanism for Local Communities Project (P145316) PHINDIRITBL  M&E data system effectively tracks number of trainees, proposals, awards and completion of implementation (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 02-Mar-2017 14-Aug-2017 14-Aug-2017 29-Apr-2022 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 3/2/2018 Page 8 of 8 Public Disclosure Copy