Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). General 1. Bank’s approval Date of the procurement Plan March 28, 2019: [N/A] 2. Date of General Procurement Notice: February 26, 2019 3. Period covered by this procurement plan: March to December, 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] No. Procurement Method Prior Review Threshold Comments US$ 1. NCB (Consultancy) Above US$ 1,350,000 N/A 2. Requalification. Bidders N/A_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project no. P166539 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimated Domestic Review Ref. Description Cost Packages Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of the NCB (Consulting services) 1.35 12 1 None Prior July 9, 2010 2 Summary of the NCB 0.378 9 None Post (Consulting services) Summary of the NCB 3 (Goods) 0.2 1 No Post Summary of the 4 Shopping (Goods) 0.22 4 None Post Summary of the NCB 5 (Non-Consultant 0.05 1 None Post Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) US$ 620,000.00 2. Single Source (Firms) N/A 3. Individual US$ 730,000.00 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Review No. Cost Packages by Bank Comments US$ million (Prior / Post) Summary of number of 1 contracts that will be let 0.15 2 Post under CQS Summary of number of 2 contracts that will be let 0.62 4 Prior under CQS Summary of number of 0.228 7 contracts that will be let Post under IC Summary of number of 0.73 8 contracts that will be let Prior under IC July 9, 2010 PROCUREMENT Ghana : Ghana Economic Transformation Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2019-03-18 2019-10-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166539 GPN Date: Project Name: Ghana Economic Transformation Project Loan / Credit No: / , IDA / 64650 Executing Agency(ies): Ministry of Finance - Economic Transformation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-106990-CS-CQS / Restructuring of National Accelerating Consultant Pending Entrepreneurship and / entrepreneurship and MSME Prior Qualification Open - National 0.00 2019-04-30 2019-05-21 2019-06-18 2019-07-02 2019-08-06 2019-12-04 Implementation Innovation Plan (NEIP) growth Selection Secretariat GH-MOFEP-106994-CS-CQS / Stakeholder Engagements Consultant and activities relating to the Pending / Enabling investments Prior Qualification Open - National 0.00 2019-05-14 2019-06-04 2019-07-18 2019-08-17 2019-09-21 2020-03-19 development and finalization Implementation Selection of the National Entrepreneurship Policy GH-MOFEP-133825-CS-CQS / CONSULTANCY Consultant SERVICES TO DEVELOP Pending IDA / 64650 Enabling investments Post Qualification Open - National 0.00 2019-09-19 2019-10-03 2019-10-31 2019-11-21 2019-12-26 2020-06-23 A STRATEGY AND Implementation Selection BUSINESS PLAN FOR GIPC Page 1 GH-MOFEP-134074-CS-CQS / CONSULTANCY Accelerating Consultant SERVICES FOR A Pending IDA / 64650 entrepreneurship and MSME Post Qualification Open - National 0.00 2019-09-18 2019-10-02 2019-10-30 2019-11-20 2019-12-25 2020-02-23 STRATEGIC REVIEW OF Implementation growth Selection VENTURE CAPITAL TRUST FUND (VCTF) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOFEP-103063-CS- INDV / Consultancy for the Preparation of Environmental Individual Project management and and Social Management / Prior Consultant Limited 0.00 Under Review 2019-02-26 2019-03-03 2019-03-24 2019-04-28 2019-06-27 evaluation Framework (ESMF) and Selection Resettlement Policy Framework (RPF) GH-MOFEP-106986-CS- INDV / Review of National Board for Small Scale Accelerating Individual Industry (NBSSI) ACT Pending / entrepreneurship and MSME Prior Consultant Limited 0.00 2019-04-25 2019-04-30 2019-05-21 2019-06-25 2019-10-23 To tailor the functions and Implementation growth Selection objects of the ACT to the vision of conversion of NBSSI into an Authority GH-MOFEP-106989-CS- INDV / Project Management Accelerating Individual Pending Training of the core team / entrepreneurship and MSME Prior Consultant Limited 0.00 2019-04-25 2019-04-30 2019-05-21 2019-06-25 2019-12-22 Implementation that will manage and report growth Selection on the activities. GH-MOFEP-106993-CS- INDV / Review of NEIP and NBSS Current training manuals, operating Individual procedures for business Pending / Enabling investments Prior Consultant Open 0.00 2019-05-06 2019-06-24 2019-07-15 2019-08-19 2020-02-15 advisory centres and Implementation Selection business resource centres and development of revised curriculum and training content GH-MOFEP-106995-CS- Individual INDV / Implementation Plan Pending / Enabling investments Post Consultant Limited 0.00 2019-05-07 2019-05-12 2019-06-02 2019-07-07 2020-01-03 and Road Map for the Implementation Selection National Entrepreneurship policy GH-MOFEP-106996-CS- INDV / Review of National Enterpreneurship and Individual Pending Innovation Plan (NEIP) and / Enabling investments Post Consultant Limited 0.00 2019-05-13 2019-05-18 2019-06-08 2019-07-13 2020-01-09 Implementation National Board for Small Selection Scale Industry (NBSSI) M&E systems GH-MOFEP-106999-CS- INDV / Review of Service Individual Delivery Processes of core Pending / Enabling investments Post Consultant Open 0.00 2019-05-21 2019-07-09 2019-07-30 2019-09-03 2020-03-01 Service Departments and Implementation Selection develop revised Processes to enhance efficiency. GH-MOFEP-107003-CS- Individual INDV / Consultancy services Project management and Pending / Post Consultant Open 0.00 2019-04-16 2019-06-04 2019-06-25 2019-07-30 2020-01-26 for the Procurement of M&E evaluation Implementation Selection Expert Page 2 GH-MOFEP-107004-CS- INDV / Consultancy services Individual for the Setting up of the Project management and Pending / Post Consultant Limited 0.00 2019-06-11 2019-06-16 2019-07-07 2019-08-11 2019-11-09 Economic Transformation evaluation Implementation Selection Project (ETP) Project Cordinating Unit (PCU) GH-MOFEP-133800-CS- INDV / Consultancy Services to Provide Technical Support for Project Component One: Enabling Investment- Accelerating Individual Pending Improving the enabling IDA / 64650 entrepreneurship and MSME Post Consultant Open 0.00 2019-09-19 2019-10-14 2019-10-28 2019-12-02 2021-11-21 Implementation business environment, growth Selection investment promotion capacity and quality infrastructure support system. GH-MOFEP-133813-CS- INDV / Consultancy Service to Provide Technical Support Crowding-in investments: Individual for Project Component Two: Promoting spatial and Pending IDA / 64650 Post Consultant Open 0.00 2019-09-19 2019-10-22 2019-11-12 2019-12-10 2021-11-29 Crowding-in Investments- industrial planning and Implementation Selection Promoting spatial and development industrial planning and development. GH-MOFEP-133819-CS- INDV / Consultancy Services to Provide Technical Support Individual Pending for Project Component Three: IDA / 64650 Enabling investments Post Consultant Open 0.00 2019-09-19 2019-10-22 2019-11-05 2019-12-10 2021-11-29 Implementation Accelerating Selection Entrepreneurship and SME Growth. GH-MOFEP-128155-CS- INDV / Consultancy Services for the development of Individual Project management and Pending Project Implementation IDA / 64650 Post Consultant Limited 0.00 2019-09-19 2019-09-24 2019-10-15 2019-11-19 2020-05-17 evaluation Implementation Manual (PIM) of the Ghana Selection Economic Transformation (GET) Project Page 3