PROCUREMENT PLAN DISTRIBUTION EFFICIENCY PROJECT 90529 HO CHI MINH CITY POWER CORPORATION Subproject: 22kV marine underground cable for Thanh An Commune, Can Gio district Date July 30, 2014 Design and Pre-bid cost Estimate Bidding Document Bidding Process Bid Evaluation Review by Contract Packages Source of Cost Procurement Bank Contract Description completi Notes No. fund Complete Approved Cost Estimate Estimate Method (Prior/ Complete Approved Bank no- Bid Complete Approved Bank no- signed Bid issued on d date date (billion VND) (million Post) d date date objection opened d date date objection USD) Survey, preparation of performance drawing design, cost estimate , supply of WB International DEP-CG- equipment & fund for 08/2014 08/2014 132.797 6.324 Competitive Prior 08/2014 08/2014 08/2014 08/2014 10/2014 12/2014 12/2014 12/2014 12/2014 04/2015 P1 technology and DEP Bidding construction of 22kV undersea cable supplying power for Thanh An commune, Can Gio district Based on National the EVNHC Package 2 Work insurance 0.589 0.028 Competitive progress MC Bidding of the project Detecting and Based on destroying the EVNHC Package 3 landmines, bomb 3.411 0.162 Appointment progress MC and explosive of the objects project Based on Monitoring National the EVNHC Package 4 consultant for 2.085 0.099 Competitive progress MC construction Bidding of the project Based on National the EVNHC Package 5 Auditing 0.392 0.019 Competitive progress MC Bidding of the project Total fund from WB 132.797 6.324 Total fund from EVNHCMC 6.478 0.308 Grand Total 139.274 6.632 1/2 Exchange rate: 1 USD = 21,000 VND 2/2