Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: April 29]: Revision 1 of Updated Procurement Plan, April 2017] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year April 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,000,000 All 2. NCB (Goods) Above US$ 100,000 No prior review 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million ICB prior review 5. (Non-Consultant Services) Below US$ 100,000 First contract 6. Sole Source selection (Works) Above US$ 100,000 All contracts 6. Request for Quotation (Works) No prior review 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: TBD July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 67.436 2 yes Prior the ICB (Works) Summary of No Prior the ICB (Goods) Summary of 8.843 10 No Post the NCB (Works) Summary of No Post 1st the NCB contract (Goods) for Prior Review Summary of No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 8.14 19 Prior for The number of one remaining contracts that package 18 are will be let of 2.3 under post under QCBS million review US Summary of 0.95 12 Post CQS and number of review INDV contracts that will be let under other methods July 9, 2010 PROCUREMENT Burkina Faso : Transport and Urban Infrastructure Development Project PLAN General Information Country: Burkina Faso Bank’s Approval Date of the Original Procurement Plan: 2017-05-16 2020-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151832 GPN Date: 2017-04-23 Project Name: Transport and Urban Infrastructure Development Project Loan / Credit No: IDA / 58590 Executing Agency(ies): Deuxieme Programme Sectoriel des Transports et du Tourisme WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-12319-CW-RFB / Travaux de bitumage du Component A: Inter-urban Open - Single Stage - One IDA / 58590 A priori Appel d'offres 51,000,000.00 51,182,006.42 Signé 2016-12-27 2017-01-16 2017-03-02 2017-05-22 2017-08-10 2019-07-31 tronçon Manga-Zabré (79km) Infrastructure International Envelope et voirie urbaine a Manga BF-PST2-9852-CW-RFB / Component B: Urban Aménagement de canaux Single Stage - One En attente IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 1,200,000.00 0.00 2018-12-04 2018-12-09 2019-01-20 2019-02-19 2019-05-04 2019-11-30 d'assainissement pluvial à Envelope d'exécution Regional Capitals Koudougou (2,5km) BF-PST2-9325-CW-RFB / Component A: Inter-urban Single Stage - One En attente IDA / 58590 A posteriori Appel d'offres Open - National 622,000.00 0.00 2018-02-20 2018-02-21 2018-04-04 2018-05-04 2018-06-08 2018-12-05 Travaux Dindeogo zonse Infrastructure Envelope d'exécution BF-PST2-9841-CW-RFB / Component B: Urban Single Stage - One En attente Aménagement d'une zone de IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 820,000.00 0.00 2018-12-12 2018-12-13 2019-01-24 2019-02-23 2019-03-13 2019-09-09 Envelope d'exécution maraichage à Ouahigouya Regional Capitals BF-PST2-9848-CW-RFB / Component B: Urban Single Stage - One En attente Aménagement d'une zone de IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 820,000.00 0.00 2018-04-19 2018-04-24 2018-05-24 2018-06-23 2018-08-06 2018-12-04 Envelope d'exécution maraichage à Manga Regional Capitals BF-PST2-123786-CW-RFB / Component B: Urban Single Stage - One En attente Construction du village IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 558,000.00 0.00 2019-10-29 2019-11-03 2019-12-03 2019-12-10 2019-12-30 2020-06-07 Envelope d'exécution artisanal de Ouahigouya Regional Capitals BF-PST2-9857-CW-RFB / Component B: Urban Single Stage - One En attente Construction de la gare IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 910,000.00 0.00 2019-10-29 2019-11-03 2019-12-03 2019-12-13 2019-12-30 2020-06-07 Envelope d'exécution routière de Manga Regional Capitals BF-PST2-9858-CW-RFB / Component B: Urban Single Stage - One En attente Construction d'un marché à IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 910,000.00 0.00 2019-10-29 2019-11-03 2019-12-03 2019-12-13 2019-12-30 2020-06-07 Envelope d'exécution bétail à Manga Regional Capitals BF-PST2-9856-CW-RFQ / Component B: Urban Single Stage - One En attente Construction du marché du IDA / 58590 Infrastructure in Targeted A posteriori Demande de prix Limited 180,000.00 0.00 2018-11-17 2019-01-12 2019-07-11 Envelope d'exécution secteur 6 de Dédougou Regional Capitals BF-PST2-9859-CW-RFB / Component B: Urban Single Stage - One En attente Mise à niveau de l'abattoir IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 910,000.00 0.00 2019-10-29 2019-11-03 2019-12-03 2019-12-13 2019-12-30 2020-07-07 Envelope d'exécution de Manga Regional Capitals BF-PST2-9854-CW-RFB / Component B: Urban Single Stage - One En attente Construction de la gare IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 1,270,700.00 0.00 2019-10-29 2019-11-03 2019-12-03 2019-12-13 2019-12-29 2020-07-06 Envelope d'exécution routière de Dédougou Regional Capitals Page 1 BF-PST2-9850-CW-RFB / Travaux d’aménagement d'un Component B: Urban Single Stage - One En cours canal de drainage des eaux IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 1,200,000.00 0.00 2019-08-06 2019-08-19 2019-09-18 2019-09-25 2019-10-10 2020-04-07 Envelope d'exécution pluviales à Koudougou d’un Regional Capitals linéaire de 2,5 km BF-PST2-126039-CW-RFB / Component B: Urban Single Stage - One En attente Construction marché du IDA / 58590 Infrastructure in Targeted A posteriori Demande de prix Limited 182,000.00 0.00 2019-11-19 2020-01-14 2020-07-12 Envelope d'exécution secteur 6 de Dédougou Regional Capitals BF-PST2-125608-CW-RFB / Travaux d’aménagement de Component B: Urban Single Stage - One En attente voiries urbaines et IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 4,400,000.00 0.00 2019-08-07 2019-08-19 2019-09-18 2019-09-25 2019-10-10 2020-03-06 Envelope d'exécution d'éclairage public dans la Regional Capitals commune de Tenkodogo BF-PST2-126435-CW-RFB / Travaux d’aménagement de Component B: Urban Open - Single Stage - One En cours voiries urbaines et IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres 6,110,000.00 0.00 2019-11-28 2019-12-03 2020-01-14 2020-02-13 2020-03-19 2020-09-15 International Envelope d'exécution d’éclairage public dans les Regional Capitals communes de Ouahigouya BF-PST2-126440-CW-RFB / Travaux d’aménagement de Component B: Urban Open - Single Stage - One En cours voiries urbaines et IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres 5,964,000.00 0.00 2019-11-21 2019-11-26 2020-01-07 2020-02-06 2020-03-12 2020-09-08 International Envelope d'exécution d’éclairage public dans les Regional Capitals communes de Koudougou GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-43142-GO-RFB / Acquisition d'équipements de bureau et matériels Component A: Inter-urban Single Stage - One IDA / 58590 A posteriori Appel d'offres Open - National 1,090,909.00 314,250.25 Signé 2018-01-22 2018-02-05 2018-03-19 2018-04-18 2018-06-06 2018-09-04 informatiques pour les Infrastructure Envelope structures impliquées dans le projet BF-PST2-43500-GO-RFB / Component D: Project Single Stage - One Acquisition d’un logiciel de IDA / 58590 A posteriori Appel d'offres Limited 40,000.00 41,023.68 Achevé 2016-12-27 2017-01-10 2017-02-21 2017-03-23 2017-06-05 2017-08-04 Management Envelope comptabilité BF-PST2-64631-GO-RFQ / Acquisition de mobilier et Component D: Project Single Stage - One IDA / 58590 A posteriori Demande de prix Limited 90,000.00 12,788.82 Signé 2018-07-10 2018-09-16 2018-10-16 fourniture de bureau au Management Envelope profit du SP-PST BF-PST2-92376-GO-RFB / Acquisition et installation de Component B: Urban signalisations routières pour Single Stage - One IDA / 58590 Infrastructure in Targeted A posteriori Appel d'offres Open - National 360,000.00 200,992.53 Signé 2019-01-09 2019-01-29 2019-03-12 2019-04-11 2019-06-05 2019-09-03 la mise en œuvre du plan Envelope Regional Capitals provisoire de circulation de la commune de Ouagadougou BF-PST2-125937-GO-RFQ / Acquisition de matériel Component C: Institutional Single Stage - One En attente informatique et de la IDA / 58590 Support and Sector A posteriori Demande de prix Limited 100,000.00 0.00 2019-10-10 2019-12-17 2020-02-15 Envelope d'exécution licence SIG, suivi de la Governance formation à son utilisation NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-126091-NC-RFQ / Recrutement d'une agence de communication pour la Component C: Institutional Single Stage - One En attente gestion événementielle de la IDA / 58590 Support and Sector A posteriori Demande de prix Limited 77,700.00 0.00 2019-09-17 2019-11-12 2019-12-12 Envelope d'exécution campagne de communication Governance poids lourds de la Mairie de Ouagadougou CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-12242-CS-QCBS / Component B: Urban Sélection fondée Etudes de faisabilité IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 82,000.00 0.00 Annulé 2017-05-18 2017-06-08 2017-07-02 2017-07-12 2017-07-22 2017-08-01 2017-09-14 2017-12-13 techniques, économiques pour Regional Capitals le coût le maraichage à Ouahigouya BF-PST2-12256-CS-QCBS / Component B: Urban Sélection fondée Etudes de faisabilité IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 82,000.00 0.00 Annulé 2017-06-22 2017-07-13 2017-08-06 2017-08-11 2017-08-21 2017-08-31 2017-10-14 2018-01-12 techniques, économiques pour Regional Capitals le coût le maraichage à Manga BF-PST2-12262-CS-CQS / Sélection fondée Contrôle et surveillance des Component B: Urban sur les En attente travaux pour l'aménagement IDA / 58590 Infrastructure in Targeted A posteriori Open - National 82,000.00 0.00 2018-02-05 2018-02-26 2018-03-22 2018-04-05 2018-05-19 2018-12-15 qualifications des d'exécution d'une zone de maraichage à Regional Capitals consultants Manga BF-PST2-12286-CS-QCBS / Etude de mise en place d'un Component C: Institutional Sélection fondée Open - plan de jalonnement IDA / 58590 Support and Sector A posteriori sur la qualité et 545,455.00 0.00 Annulé 2017-10-11 2017-11-01 2017-11-25 2017-11-30 2017-12-10 2017-12-29 2018-02-11 2018-11-08 International favorisant les itinéraires de Governance le coût contournement BF-PST2-12287-CS-QCBS / Component C: Institutional Sélection fondée Etude de restructuration et IDA / 58590 Support and Sector A posteriori sur la qualité et Open - National 91,000.00 0.00 Annulé 2017-11-27 2017-12-18 2018-01-11 2018-01-16 2018-01-26 2018-02-14 2018-03-30 2018-12-25 extension du réseau de la Governance le coût SOTRACO BF-PST2-12318-CS-QCBS / Contrôle et surveillance des Sélection fondée travaux de construction et Component A: Inter-urban Open - IDA / 58590 A priori sur la qualité et 2,300,000.00 1,887,262.87 Signé 2016-10-30 2016-11-20 2017-02-03 2017-03-03 2017-03-13 2017-04-17 2017-06-30 2019-08-19 de bitumage de 79 km Infrastructure International le coût Route Principale et 9km de bretelle et terre BF-PST2-12316-CS-QCBS / Sélection fondée Élaboration d’une stratégie Component D: Project IDA / 58590 A posteriori sur la qualité et Open - National 36,000.00 27,109.48 Signé 2016-03-09 2016-03-30 2016-05-13 2016-06-10 2016-07-10 2016-08-14 2016-09-18 2016-12-17 et d’un plan de Management le coût communication BF-PST2-16754-CS-CQS / Sélection fondée Recrutement d'un consultant Component C: Institutional sur les pour la réalisation de IDA / 58590 Support and Sector A posteriori Open - National 181,818.00 173,878.34 Signé 2017-06-22 2017-07-13 2017-08-26 2017-09-25 2017-10-30 2018-04-28 qualifications des l'Enquête origine-destination Governance consultants à Ouaga Page 3 BF-PST2-16752-CS-QCBS / Contrôle et surveillance des Sélection fondée travaux de construction et Component A: Inter-urban Open - IDA / 58590 A priori sur la qualité et 2,300,000.00 0.00 Annulé 2016-10-30 2016-11-29 2017-01-02 2017-02-16 2017-03-02 2017-04-11 2017-06-24 2019-08-13 de bitumage de 79 km Infrastructure International le coût Route Principale et 9km de bretelle et terre BF-PST2-16762-CS-CQS / Sélection fondée Component C: Institutional Recrutement d'un consultant sur les En cours IDA / 58590 Support and Sector A posteriori Open - National 136,363.00 0.00 2018-03-12 2018-04-02 2018-05-16 2018-06-15 2018-08-19 2019-02-15 pour la révision du code de qualifications des d'exécution Governance l'Urbanisme consultants BF-PST2-12273-CS-CQS / Sélection fondée Etudes environnementales et Component B: Urban sur les sociales de la gare routière, IDA / 58590 Infrastructure in Targeted A posteriori Open - National 82,000.00 0.00 Annulé 2017-08-21 2017-09-11 2017-10-05 2017-10-15 2017-11-28 2018-01-27 qualifications des du marché à bétail, mise à Regional Capitals consultants niveau de l'abattoir a Manga BF-PST2-12272-CS-QCBS / Etudes de faisabilité Component B: Urban Sélection fondée techniques, économiques de IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 272,000.00 0.00 Annulé 2017-07-18 2017-08-08 2017-09-21 2017-09-26 2017-10-06 2017-10-25 2017-12-08 2018-03-08 la gare routière, du marché Regional Capitals le coût à bétail, mise à niveau de l'abattoir a Manga BF-PST2-12275-CS-QCBS / Contrôle et surveillance des Component B: Urban Sélection fondée travaux de construction de IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 272,000.00 0.00 Annulé 2018-03-13 2018-04-03 2018-04-27 2018-05-02 2018-05-12 2018-05-22 2018-07-05 2019-01-31 la gare routière, du marché Regional Capitals le coût à bétail, mise à niveau de l'abattoir a Manga BF-PST2-10058-CS-QCBS / Etudes de faisabilité techniques et économiques Component B: Urban Sélection fondée de la voirie (Koudougou, IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 357,000.00 0.00 Annulé 2017-06-12 2017-07-03 2017-07-31 2017-08-14 2017-08-24 2017-09-28 2017-11-16 2018-05-15 Ouahigouya, Tenkodogo) y Regional Capitals le coût compris l'assainissement de Koudougou BF-PST2-10033-CS-QCBS / Sélection fondée Etudes techniques et Component A: Inter-urban Open - IDA / 58590 A posteriori sur la qualité et 327,000.00 0.00 Annulé 2017-04-17 2017-05-08 2017-06-21 2017-07-19 2017-08-18 2017-09-22 2017-12-05 2018-06-03 économiques construction de Infrastructure International le coût 40 ouvrages BF-PST2-41738-CS-CQS / Etudes techniques et Sélection fondée economiques et DAO pour la Component A: Inter-urban sur les IDA / 58590 A posteriori Open - National 3,237,000.00 0.00 Annulé 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-13 2018-11-10 construction de 40 ouvrages Infrastructure qualifications des de franchissement et des consultants remblais de raccordement  BF-PST2-10039-CS-QCBS / Sélection fondée Etudes techniques et Component A: Inter-urban IDA / 58590 A posteriori sur la qualité et Open - National 364,000.00 0.00 Annulé 2017-03-30 2017-04-20 2017-06-03 2017-07-01 2017-07-31 2017-09-04 2017-11-17 2018-09-13 économiques de 200km de Infrastructure le coût pistes BF-PST2-10086-CS-QCBS / Etudes environnementales et sociales de la voirie Component B: Urban Sélection fondée (Koudougou, Ouahigouya, IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 357,000.00 0.00 Annulé 2017-11-07 2017-11-28 2017-12-26 2018-01-30 2018-02-09 2018-03-16 2018-04-29 2018-12-25 Tenkodogo) y compris Regional Capitals le coût l'assainissement de Koudougou Page 4 BF-PST2-10138-CS-QCBS / Contrôle et surveillance des travaux de la voirie Component B: Urban Sélection fondée En attente (Koudougou, Ouahigouya, IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 357,000.00 0.00 2018-10-24 2018-11-14 2018-12-13 2019-01-12 2019-02-01 2019-03-08 2019-04-21 2019-10-18 d'exécution Tenkodogo) y compris Regional Capitals le coût l'assainissement de Koudougou BF-PST2-12238-CS-CQS / Sélection fondée Etudes environnementales et Component B: Urban sur les sociales pour l'aménagement IDA / 58590 Infrastructure in Targeted A posteriori Open - National 90,909.00 0.00 Annulé 2017-08-10 2017-08-31 2017-09-24 2017-10-24 2017-11-28 2018-01-27 qualifications des d'une zone de maraichage à Regional Capitals consultants Manga BF-PST2-12265-CS-QCBS / Etudes de faisabilité Component B: Urban Sélection fondée techniques, économiques pour IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 127,000.00 0.00 Annulé 2017-05-30 2017-06-20 2017-07-14 2017-07-24 2017-08-03 2017-09-07 2017-10-21 2018-01-19 gare routière, et marche Regional Capitals le coût secteur 6 de Dedougou BF-PST2-42112-CS-CQS / Sélection fondée Component B: Urban Etude de restructuration et sur les En attente IDA / 58590 Infrastructure in Targeted A posteriori Open - National 136,000.00 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-18 2018-10-01 2019-02-28 extension du réseau de la qualifications des d'exécution Regional Capitals SOTRACO consultants BF-PST2-12284-CS-QCBS / Politique de stationnement des véhicules particulier, des 2 roues et des véhicules et Component B: Urban Sélection fondée Open - des véhicules de liaisons IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 272,727.00 253,061.53 Signé 2017-06-06 2017-07-06 2017-09-14 2017-10-04 2017-10-24 2017-11-17 2017-12-23 2018-07-21 International dans le centre Ouaga (plan Regional Capitals le coût de circulation et de stationnement dans le centre- ville de Ouagadougou) BF-PST2-42109-CS-CQS / Sélection fondée Component B: Urban Plan de jalonnement sur les En attente IDA / 58590 Infrastructure in Targeted A posteriori Open - National 200,000.00 0.00 2018-04-24 2018-05-15 2018-06-28 2018-07-28 2018-09-10 2019-03-09 favorisant les itineraires de qualifications des d'exécution Regional Capitals contournement consultants BF-PST2-12281-CS-QCBS / Component B: Urban Sélection fondée Open - En attente faisabilité pour mise en IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 454,545.00 0.00 2018-05-17 2018-06-07 2018-07-05 2018-08-19 2018-08-29 2018-09-22 2018-11-05 2019-03-05 International d'exécution place TCSP à Ouagadougou Regional Capitals le coût BF-PST2-12253-CS-CQS / Sélection fondée Component B: Urban Contrôle pour sur les En attente IDA / 58590 Infrastructure in Targeted A posteriori Open - National 80,000.00 0.00 2018-10-24 2018-11-14 2018-12-08 2018-12-22 2019-02-04 2019-08-03 l'aménagement à Ouahigouya qualifications des d'exécution Regional Capitals zone maraichage consultants BF-PST2-45003-CS-CQS / Sélection fondée Études techniques et Component A: Inter-urban sur les IDA / 58590 A posteriori Open - National 327,000.00 308,658.65 Signé 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 économiques de 40 ouvrages Infrastructure qualifications des de franchissement consultants BF-PST2-52652-CS-CQS / Sélection fondée Component B: Urban Etude faisabilité sur les En cours IDA / 58590 Infrastructure in Targeted A posteriori Open - National 120,455.00 0.00 2018-03-07 2018-04-06 2018-07-05 2018-08-14 2018-10-28 2019-02-25 construction canal qualifications des d'exécution Regional Capitals drainage Koudougou consultants BF-PST2-41697-CS-CQS / Etudes de faisabilité Sélection fondée Component B: Urban technique, économique de la sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 272,727.00 0.00 Annulé 2018-02-14 2018-03-07 2018-04-20 2018-05-20 2018-06-24 2018-06-25 gare routière, du marché à qualifications des Regional Capitals bétail, mise à niveau de consultants l'abattoir a Manga Page 5 BF-PST2-41745-CS-CQS / Sélection fondée Component B: Urban Etudes de faisabilite sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 127,000.00 0.00 Annulé 2018-02-12 2018-03-05 2018-04-18 2018-05-18 2018-07-01 2018-10-29 techniques, économiques gare qualifications des Regional Capitals routiere et marche secteur 6 consultants BF-PST2-66968-CS-CQS / Etudes pour Sélection fondée Component B: Urban l'aménagementzone de sur les En cours IDA / 58590 Infrastructure in Targeted A posteriori Open - National 163,636.00 0.00 2018-07-05 2018-07-26 2018-09-24 2018-10-24 2018-12-28 2019-04-27 maraichage à Manga sur 20 qualifications des d'exécution Regional Capitals hectares et à Ouahigouya consultants sur 50 hectares BF-PST2-12278-CS-QCBS / Etude de faisabilité pour l'aménagement de zones Component B: Urban Sélection fondée d'activités économiques dans Open - IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 801,818.00 0.00 Annulé 2018-05-09 2018-05-30 2018-06-23 2018-06-27 2018-07-07 2018-07-31 2018-09-28 2019-03-27 12 villes (aménagement International Regional Capitals le coût initialement prévu) et Evaluation environnementale et sociale BF-PST2-12267-CS-CQS / Sélection fondée Component B: Urban Etudes environnementales sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 64,000.00 0.00 Annulé 2018-08-12 2018-09-16 2018-11-20 2018-12-30 2019-03-30 2019-05-29 gare routière et marché qualifications des Regional Capitals de Dedougou consultants BF-PST2-12260-CS-CQS / Sélection fondée Component B: Urban Etudes environnementales sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 90,909.00 0.00 Annulé 2018-05-23 2018-06-13 2018-08-02 2018-09-01 2018-11-15 2019-01-14 aménagement maraichage à qualifications des Regional Capitals Manga consultants BF-PST2-41741-CS-CQS / Sélection fondée Etudes environnementales et Component B: Urban sur les sociales de la voirie IDA / 58590 Infrastructure in Targeted A posteriori Open - National 357,000.00 0.00 Annulé 2018-02-15 2018-03-08 2018-04-21 2018-05-21 2018-07-04 2018-10-02 qualifications des (Koudougou, Ouahigouya, Regional Capitals consultants Tenkodogo) BF-PST2-92298-CS-QCBS / Elaboration d'un schéma de Component B: Urban Sélection fondée drainage des eaux pluviales Open - En cours IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-20 2019-01-19 2019-03-10 2019-04-24 2019-05-14 2019-07-03 2019-08-31 2020-02-27 à Bobo-Dioulasso, Banfora et International d'exécution Regional Capitals le coût Gaoua et Evaluation environnementale et sociale BF-PST2-92300-CS-QCBS / Elaboration d'un schéma de Component B: Urban Sélection fondée drainage des eaux pluviales Open - En cours IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-20 2019-01-19 2019-03-10 2019-04-24 2019-05-14 2019-07-03 2019-08-31 2020-02-27 à Kaya, Ziniaré et Dori et International d'exécution Regional Capitals le coût Evaluation environnementale et sociale BF-PST2-92301-CS-QCBS / Elaboration d'un schéma de Component B: Urban Sélection fondée drainage des eaux pluviales Open - En attente IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-20 2019-01-19 2019-03-10 2019-04-24 2019-05-14 2019-07-03 2019-08-31 2020-02-27 à Manga, Tenkodogo, Fada International d'exécution Regional Capitals le coût N'Gourma et Evaluation environnementale et sociale BF-PST2-92302-CS-QCBS / Elaboration d'un schéma de Component B: Urban Sélection fondée drainage des eaux pluviales Open - En attente IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-20 2019-01-10 2019-02-23 2019-03-23 2019-04-22 2019-05-27 2019-07-01 2019-12-28 à Ouahigouya, Koudougou, et International d'exécution Regional Capitals le coût Dédougou et Evaluation environnementale et sociale Page 6 BF-PST2-92311-CS-CQS / Etudes de faisabilité technico- Sélection fondée économique des travaux Component B: Urban sur les d'aménagement de voies IDA / 58590 Infrastructure in Targeted A posteriori Open - National 164,941.00 143,553.25 Signé 2018-12-20 2019-01-10 2019-03-11 2019-04-10 2019-06-14 2019-11-11 qualifications des urbaines à Koudougou sur Regional Capitals consultants 7,00 km + deux (2) ouvrages de franchissements BF-PST2-92312-CS-CQS / Etudes de faisabilité technico- Sélection fondée Component B: Urban économique des travaux sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 132,650.00 115,496.37 Signé 2018-12-20 2019-01-10 2019-03-11 2019-04-10 2019-06-14 2019-11-11 d'aménagement de voies qualifications des Regional Capitals urbaines à Ouahigouya sur consultants 7,00 Km BF-PST2-92313-CS-CQS / Etudes de faisabilité technico- Sélection fondée Component B: Urban économique des travaux sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 99,360.00 85,665.80 Signé 2018-12-26 2019-01-16 2019-03-17 2019-04-16 2019-06-20 2019-11-17 d'aménagement de voies qualifications des Regional Capitals urbaines à Tenkodogo (5,00 consultants km) BF-PST2-92314-CS-CQS / Etudes techniques détaillées et élaboration des dossiers Sélection fondée d'appel d'offres pour les Component B: Urban sur les travaux de construction de IDA / 58590 Infrastructure in Targeted A posteriori Open - National 145,000.00 0.00 Annulé 2018-12-21 2019-01-11 2019-02-24 2019-03-26 2019-04-30 2019-09-27 qualifications des quarante (40) ouvrages de Regional Capitals consultants franchissement dans la Boucle du Mouhoun et le Nord BF-PST2-92315-CS-CQS / Etude de faisabilité technico- économique pour la Sélection fondée Component B: Urban réalisation de 200 km de sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 169,885.00 145,790.72 Signé 2018-12-20 2019-01-10 2019-03-11 2019-04-10 2019-06-14 2019-12-11 pistes rurales par la qualifications des Regional Capitals méthode mécanisée dans les consultants régions du Centre-Sud et Centre-Est BF-PST2-92316-CS-CQS / Etudes techniques détaillées et élaboration des dossiers Sélection fondée d'appel d'offres pour les Component B: Urban sur les travaux de construction de IDA / 58590 Infrastructure in Targeted A posteriori Open - National 200,000.00 0.00 Annulé 2018-12-20 2019-01-10 2019-03-11 2019-04-10 2019-06-14 2019-11-11 qualifications des quarante (40) ouvrages de Regional Capitals consultants franchissement dans la Boucle du Mouhoun et le Nord BF-PST2-92317-CS-CQS / Etude de faisabilité technico- économique pour la Sélection fondée Component B: Urban réalisation de 200 km de sur les IDA / 58590 Infrastructure in Targeted A posteriori Open - National 181,700.00 69,626.27 Signé 2018-12-20 2019-01-10 2019-03-11 2019-04-10 2019-06-14 2019-11-11 pistes rurales par la qualifications des Regional Capitals méthode mécanisée dans les consultants régions de la Boucle du Mouhoun et Centre -Ouest BF-PST2-92356-CS-CQS / Etude de faisabilité technico- Sélection fondée économique pour la Component B: Urban sur les réalisation de 200 km de IDA / 58590 Infrastructure in Targeted A posteriori Open - National 80,000.00 68,653.87 Signé 2018-12-21 2019-01-11 2019-03-12 2019-04-11 2019-06-15 2019-12-12 qualifications des pistes rurales par la Regional Capitals consultants méthode mécanisée dans la région du Nord BF-PST2-92372-CS-QCBS / Etude de faisabilité pour Component B: Urban Sélection fondée l'aménagement de zones Open - En attente IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-11 2020-01-07 d'activités économiques à International d'exécution Regional Capitals le coût Bobo-Dioulasso, Banfora et Gaoua Page 7 BF-PST2-92373-CS-QCBS / Etude de faisabilité pour Component B: Urban Sélection fondée Open - En attente l'aménagement de zones IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-11 2020-01-07 International d'exécution d'activités économiques à Regional Capitals le coût Kaya, Ziniaré et Dori BF-PST2-92374-CS-QCBS / Etude de faisabilité pour Component B: Urban Sélection fondée l'aménagement de zones Open - En attente IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 209,090.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-11 2020-01-07 d'activités économiques à International d'exécution Regional Capitals le coût Manga, Tenkodogo, Fada N'Gourma BF-PST2-67549-CS-QCBS / Etude de faisabilité pour Component B: Urban Sélection fondée l'aménagement de zones Open - IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 801,818.00 0.00 Annulé 2018-06-28 2018-07-28 2018-09-16 2018-10-31 2018-11-20 2018-12-20 2019-02-17 2019-08-16 d'activités économiques dans International Regional Capitals le coût 12 villes capitales régionales du Burkina Faso BF-PST2-66971-CS-QCBS / Etudes de faisabilité pour les travaux de construction Component B: Urban Sélection fondée d'équipements structurants : IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et Open - National 549,000.00 0.00 Annulé 2018-07-16 2018-08-06 2018-10-20 2018-11-19 2018-12-19 2019-02-08 2019-04-14 2019-08-12 gare routière à Manga et Regional Capitals le coût Dédougou, marché à bétail à Manga, la réhabilitation de l'abattoir BF-PST2-92380-CS-QCBS / Etudes techniques et économiques et DAO pour Sélection fondée Component A: Inter-urban Open - les travaux d'aménagement IDA / 58590 A posteriori sur la qualité et 106,000.00 100,438.78 Signé 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2019-11-29 Infrastructure International de 100 km de pistes en le coût HIMO dans la Boucle du Mouhoun et le Nord BF-PST2-92381-CS-QCBS / Etudes techniques et économiques et DAO pour Sélection fondée Component A: Inter-urban Open - les travaux d'aménagement IDA / 58590 A posteriori sur la qualité et 127,000.00 118,907.74 Signé 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-02 2019-11-29 Infrastructure International de 100 km de pistes en le coût HIMO dans le Centre Sud, Centre Est, et Centre Ouest BF-PST2-10036-CS-QCBS / Sélection fondée Etudes techniques et Component A: Inter-urban Open - IDA / 58590 A posteriori sur la qualité et 236,000.00 0.00 Annulé 2017-03-13 2017-04-03 2017-05-17 2017-06-14 2017-07-14 2017-08-18 2017-09-22 2018-04-20 économiques de 100km de Infrastructure International le coût pistes en HIMO BF-PST2-41739-CS-CQS / Sélection fondée Etudes techniques et Component A: Inter-urban sur les economiques et DAO pour IDA / 58590 A posteriori Open - National 364,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-24 2018-12-21 Infrastructure qualifications des les travaux d' amenagements consultants de 200km de pistes BF-PST2-41731-CS-CQS / Sélection fondée Etudes de faisabilite Component B: Urban sur les techniques et économiques IDA / 58590 Infrastructure in Targeted A posteriori Open - National 357,000.00 0.00 Annulé 2018-01-30 2018-02-20 2018-04-05 2018-05-05 2018-06-18 2018-11-15 qualifications des de la voirie (Koudougou, Regional Capitals consultants Ouahigouya, Tenkodogo) BF-PST2-12276-CS-QCBS / Elaboration d'un schéma de Component C: Institutional Sélection fondée Open - drainage des eaux pluviales IDA / 58590 Support and Sector A posteriori sur la qualité et 801,818.00 0.00 Annulé 2018-05-09 2018-05-30 2018-06-23 2018-06-26 2018-07-06 2018-07-25 2018-09-22 2019-03-21 International dans 12 villes et Evaluation Governance le coût environnementale et sociale Page 8 BF-PST2-104701-CS-QCBS / Sélection fondée Audits annuels 2019, 2020 Component D: Project En cours IDA / 58590 A posteriori sur la qualité et Open - National 127,272.00 0.00 2019-03-29 2019-04-19 2019-06-18 2019-07-16 2019-08-15 2019-09-25 2019-11-18 2022-11-17 et 2021 des comptes des Management d'exécution le coût projets du SP-PST BF-PST2-124599-CS-CQS / Sélection fondée Component B: Urban suivi-contrôle de la sur les En attente IDA / 58590 Infrastructure in Targeted A posteriori Open - National 57,000.00 0.00 2019-10-21 2019-11-05 2019-12-04 2019-12-05 2019-12-29 2020-06-26 construction du village qualifications des d'exécution Regional Capitals artisanal de Ouahigouya consultants BF-PST2-12270-CS-CQS / Sélection fondée Contrôle et surveillance des Component B: Urban sur les En attente travaux de la gare routière IDA / 58590 Infrastructure in Targeted A posteriori Open - National 145,000.00 0.00 2019-10-14 2019-10-28 2019-11-15 2019-11-22 2019-12-29 2020-06-26 qualifications des d'exécution et du marché du secteur 6 Regional Capitals consultants de Dédougou BF-PST2-125767-CS-CQS / Sélection fondée Suivi-contrôle des travaux Component B: Urban sur les En cours d’aménagement de voiries IDA / 58590 Infrastructure in Targeted A posteriori Open - National 118,888.00 0.00 2019-08-14 2019-09-13 2019-09-27 2019-09-30 2019-10-10 2020-03-06 qualifications des d'exécution urbaines dans la commune Regional Capitals consultants de Tenkodogo BF-PST2-125923-CS-QCBS / Etudes de faisabilité, études techniques détaillées et Component B: Urban Sélection fondée Open - En cours élaboration du Dossier IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 472,727.00 0.00 2019-08-01 2019-08-02 2019-08-04 2019-08-07 2019-08-12 2019-08-18 2019-08-30 2019-11-15 International d'exécution d’Appel d’Offres pour les Regional Capitals le coût travaux de construction d’équipements structurants BF-PST2-92379-CS-QCBS / Etudes de faisabilité, études techniques détaillées et Component B: Urban Sélection fondée Open - élaboration du Dossier IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 549,000.00 0.00 Annulé 2019-01-09 2019-01-30 2019-03-15 2019-04-12 2019-05-12 2019-06-16 2019-08-04 2019-12-02 International d'Appel d'Offres pour les Regional Capitals le coût travaux de construction d'équipements structurants BF-PST2-125929-CS-CQS / Etude sur la situation de Sélection fondée Component C: Institutional référence des indicateurs de sur les En attente IDA / 58590 Support and Sector A posteriori Open - National 181,818.00 0.00 2019-08-20 2019-09-10 2019-10-24 2019-11-23 2020-01-21 2020-07-19 l’observatoire urbain national qualifications des d'exécution Governance dans les trente-six (36) villes consultants du BURKINA FASO BF-PST2-126443-CS-CQS / Suivi-contrôle des Travaux Sélection fondée Component B: Urban d’aménagement d'un canal sur les En cours IDA / 58590 Infrastructure in Targeted A posteriori Open - National 60,227.00 0.00 2019-08-14 2019-09-13 2019-09-25 2019-09-30 2019-10-10 2020-03-06 de drainage des eaux qualifications des d'exécution Regional Capitals pluviales à Koudougou d’un consultants linéaire de 2,5 km BF-PST2-126448-CS-CQS / Sélection fondée Suivi-contrôle des Travaux Component B: Urban sur les En cours d’aménagement de voiries IDA / 58590 Infrastructure in Targeted A posteriori Open - National 118,182.00 0.00 2019-08-14 2019-09-13 2019-09-30 2019-10-10 2019-12-09 2020-07-01 qualifications des d'exécution urbaines dans les communes Regional Capitals consultants de Koudougou BF-PST2-126450-CS-CQS / Sélection fondée Suivi-contrôle des Travaux Component B: Urban sur les En cours d’aménagement de voiries IDA / 58590 Infrastructure in Targeted A posteriori Open - National 119,588.00 0.00 2019-08-14 2019-09-13 2019-10-03 2019-10-13 2019-12-09 2020-07-01 qualifications des d'exécution urbaines dans les communes Regional Capitals consultants de Ouahigouya BF-PST2-115701-CS-CQS / Mise en place et Sélection fondée Component C: Institutional opérationnalisation d'un sur les IDA / 58590 Support and Sector A posteriori Open - National 136,363.00 0.00 Annulé 2019-06-30 2019-07-21 2019-09-03 2019-10-03 2019-12-01 2020-04-29 dispositif national de suivi qualifications des Governance des prix de transports des consultants marchandises Page 9 BF-PST2-92378-CS-CQS / Sélection fondée Recrutement d'une maîtrise Component B: Urban sur les Open - d'ouvrage déléguée pour IDA / 58590 Infrastructure in Targeted A posteriori 300,000.00 0.00 Annulé 2019-04-23 2019-05-14 2019-06-27 2019-07-27 2019-08-31 2020-02-27 qualifications des International appuyer les communes du Regional Capitals consultants projet dans le volet urbain BF-PST2-144583-CS-CQS / Sélection fondée Recrutement d'un cabinet Component D: Project sur les En attente d'assistance au recrutement IDA / 58590 A posteriori Open - National 5,000.00 0.00 2019-11-20 2019-12-11 2020-01-24 2020-02-23 2020-03-29 2020-05-28 Management qualifications des d'exécution du personnel complémentaire consultants du SP-PST BF-PST2-147506-CS-CQS / Sélection fondée Etude de Faisabilité des Component C: Institutional sur les En cours Contrats Pluriannuels avec IDA / 58590 Support and Sector A posteriori Open - National 100,000.00 0.00 2019-12-20 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 qualifications des d'exécution obligation de résultat Governance consultants (GENIS) au Burkina Faso BF-PST2-148600-CS-CQS / Sélection fondée Réalisation d’une Etude Component C: Institutional sur les En attente d’Impact Environnemental IDA / 58590 Support and Sector A posteriori Open - National 150,000.00 0.00 2019-12-20 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-06-27 qualifications des d'exécution et social du corridor de Governance consultants Transport Public de Ouaga BF-PST2-148645-CS-CQS / Sélection fondée Réalisation d’un Plan Component C: Institutional sur les En attente d’Actions de Réinstallation IDA / 58590 Support and Sector A posteriori Open - National 150,000.00 0.00 2019-12-23 2020-01-13 2020-02-26 2020-03-27 2020-05-01 2020-06-30 qualifications des d'exécution du corridor de Transport Governance consultants Public de Ouagadougou BF-PST2-12276-CS-QCBS-2 / Elaboration d'un schéma de drainage des eaux pluviales Component C: Institutional Sélection fondée Open - En attente dans 12 villes capitales IDA / 58590 Support and Sector A posteriori sur la qualité et 802,000.00 0.00 2020-01-15 2020-02-05 2020-03-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-07-26 International d'exécution régionales du Burkina Faso Governance le coût et Evaluation environnementale et sociale BF-PST2-92375-CS-QCBS / Études de faisabilité pour l’aménagement de zones d’activités économiques dans douze (12) villes capitales Component B: Urban Sélection fondée Open - En attente régionales du Burkina Faso IDA / 58590 Infrastructure in Targeted A posteriori sur la qualité et 802,000.00 0.00 2018-12-21 2019-01-11 2019-02-24 2019-03-24 2019-04-23 2019-05-28 2019-07-11 2020-01-07 International d'exécution (Bobo-Dioulasso, Banfora, Regional Capitals le coût Koudougou, Ouahigouya, Kaya, Gaoua, Tenkodogo, Manga, Fada N’Gourma, Ziniaré, Dori et Dédougou) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-12293-CS-INDV / Recrutement d'un consultant Component D: Project IDA / 58590 A posteriori Individuel Limited 54,545.00 0.00 Annulé 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2017-09-06 pour l'élaboration d'un plan Management d'action de lutte VIH/SIDA BF-PST2-12317-CS-INDV / Etudes de définition des besoins de connectivité Component A: Inter-urban IDA / 58590 A posteriori Individuel Limited 45,000.00 45,223.91 Signé 2016-10-30 2016-11-29 2016-12-20 2017-02-02 2017-04-03 virtuelle ainsi que impact Infrastructure environnemental et social dans les agglomérations Page 10 BF-PST2-39408-CS-INDV / Component D: Project Recrutement d'un Spécialiste IDA / 58590 A posteriori Individuel Open 76,364.00 0.00 Annulé 2017-12-28 2018-02-15 2018-03-08 2018-04-12 2018-04-30 Management en développement social BF-PST2-9861-CS-INDV / Component A: Inter-urban Contrôle et surveillance des IDA / 58590 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-03-21 2018-03-26 2018-04-16 2018-05-21 2018-11-17 Infrastructure travaux de connectivité BF-PST2-42117-CS-INDV / Etude diagnostic du système Component D: Project IDA / 58590 A posteriori Individuel Limited 25,000.00 27,552.46 Signé 2018-01-30 2018-02-04 2018-02-25 2018-04-10 2018-05-25 de passation des marchés Management des activités du PTDIU BF-PST2-43470-CS-INDV / Etude de préfaisabilité des Component B: Urban investissements du volet IDA / 58590 Infrastructure in Targeted A posteriori Individuel Limited 45,000.00 53,888.66 Signé 2016-11-20 2016-12-20 2017-01-24 2017-04-18 2017-07-17 urbain à Dédougou, Regional Capitals Koudougou, Ouahigouya lot 1 BF-PST2-43469-CS-INDV / Etude de préfaisabilité des Component B: Urban investissements du volet IDA / 58590 Infrastructure in Targeted A posteriori Individuel Limited 45,000.00 30,839.78 Signé 2016-11-20 2016-12-04 2017-01-18 2017-04-07 2017-07-06 urbain à Manga et Regional Capitals Tenkodogo ( lot 2) BF-PST2-59641-CS-INDV / Component B: Urban Impact social pour la IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 98,181.00 86,774.00 Signé 2018-04-17 2018-07-11 2018-08-10 2018-10-04 2019-01-02 délimitation du zonage des Regional Capitals SDAU BF-PST2-41682-CS-INDV / Etudes environnementales et Component B: Urban sociales de la gare routière, IDA / 58590 Infrastructure in Targeted A posteriori Individuel Limited 82,000.00 0.00 Annulé 2018-02-13 2018-02-14 2018-03-07 2018-04-11 2018-04-20 du marché à bétail, mise à Regional Capitals niveau de l'abattoir a Manga BF-PST2-92383-CS-INDV / réalisation des notices d'impact environnemental et social (NIES) pour Component B: Urban construction de la gare En cours IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 68,564.90 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 routière et du marché de d'exécution Regional Capitals bétail de Manga et la construction du marché du secteur 6 et de la gare routière de Dédougou BF-PST2-92384-CS-INDV / réalisation des notices d'impact environnemental et Component B: Urban social (NIES) pour les IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 684,474.24 Signé 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 constructions de voiries et Regional Capitals de caniveaux à Tenkodogo, Koudougou et Ouahigouya BF-PST2-92385-CS-INDV / réalisation des notices d'impact environnemental et social (NIES) pour le Component B: Urban maraichage et la En cours IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 0.00 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 construction du village d'exécution Regional Capitals artisanal de Ouahigouya et le maraichage ainsi que la mise à niveau de l'abattoir de Manga Page 11 BF-PST2-92386-CS-INDV / Plans d'Action de Réinstallation des personnes Component B: Urban En cours affectées par les IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 0.00 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 d'exécution constructions de voiries et Regional Capitals de caniveaux à Tenkodogo, Koudougou et Ouahigouya BF-PST2-92387-CS-INDV / Plans d'Action de Réinstallation des personnes affectées par la construction Component B: Urban de la gare routière et du IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 68,580.80 Signé 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 marché de bétail de Manga Regional Capitals et la construction du marché du secteur 6 et de la gare routière de Dédougu BF-PST2-92388-CS-INDV / Plans d'Action de Réinstallation des personnes affectées par le maraichage Component B: Urban En cours et la construction du village IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 50,000.00 0.00 2018-12-21 2019-02-19 2019-03-21 2019-05-04 2019-07-03 d'exécution artisanal de Ouahigouya et Regional Capitals le maraichage ainsi que la mise à niveau de l'abattoir de Manga BF-PST2-66980-CS-INDV / PAR des personnes affectées Component B: Urban par les activités du volet IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 150,000.00 0.00 Annulé 2018-07-02 2018-09-20 2018-10-25 2018-12-23 2019-03-23 urbain du PTDIU à Manga, Regional Capitals Tenkodogo, Koudougou, Dédougou et à Ouahigouya BF-PST2-66969-CS-INDV / Notices d'impact environnemental et social Component B: Urban (NIES) pour les activités du IDA / 58590 Infrastructure in Targeted A posteriori Individuel Open 150,000.00 0.00 Annulé 2018-07-10 2018-09-08 2018-10-08 2018-11-21 2019-02-19 volet urbain du PTDIU à Regional Capitals Manga, Tenkodogo, Koudougou, Dédougou et à Ouahigouya BF-PST2-104703-CS-INDV / Component D: Project En cours recrutement du IDA / 58590 A priori Individuel Limited 164,000.00 0.00 2019-03-06 2019-03-11 2019-04-01 2019-05-06 2022-05-05 Management d'exécution Coordonnateur du SP-PST BF-PST2-104761-CS-INDV / formation du personnel et Component D: Project En cours l'élaboration d'une IDA / 58590 A posteriori Individuel Limited 27,272.00 0.00 2019-04-16 2019-04-21 2019-05-12 2019-07-05 2019-09-03 Management d'examen cartographie des risques au SP-PST BF-PST2-115699-CS-INDV / Component C: Institutional Etude d'impact social pour En cours IDA / 58590 Support and Sector A posteriori Individuel Open 272,727.00 0.00 2019-05-31 2019-07-30 2019-08-29 2019-10-27 2019-12-26 la délimitation du zonage d'exécution Governance des SDAU BF-PST2-115703-CS-INDV / Component C: Institutional En cours Assistance technique au IDA / 58590 Support and Sector A posteriori Individuel Limited 54,545.00 0.00 2019-05-20 2019-05-25 2019-06-15 2019-07-20 2021-07-19 d'exécution MUH Governance BF-PST2-125932-CS-INDV / Component D: Project En cours Revue à mi-parcours du IDA / 58590 A posteriori Individuel Limited 50,000.00 0.00 2019-08-02 2019-08-07 2019-08-17 2019-08-29 2019-10-03 Management d'examen PTDIU Page 12 BF-PST2-125935-CS-INDV / Recrutement d’un Consultant chargé de la formation des acteurs du PTDIU à la Component D: Project En attente IDA / 58590 A posteriori Individuel Limited 27,272.00 0.00 2019-08-13 2019-08-18 2019-09-02 2019-09-24 2019-10-04 maitrise des procédures Management d'exécution environnementales et sociales nationales et de la Banque mondiale BF-PST2-125936-CS-INDV / Recrutement d’un Consultant chargé de la formation en Component B: Urban En cours passation des marchés des IDA / 58590 Infrastructure in Targeted A posteriori Individuel Limited 27,272.00 0.00 2019-08-26 2019-08-31 2019-09-15 2019-10-07 2019-10-17 d'exécution agents des marchés publics Regional Capitals de Agetib, ACOMOD et DMP/MUH BF-PST2-126473-CS-INDV / Component D: Project En cours recrutement d'un spécialiste IDA / 58590 A posteriori Individuel Open 24,000.00 0.00 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-12-08 Management d'exécution en sauvegarde sociale BF-PST2-143199-CS-INDV / Mise en place et Component C: Institutional opérationnalisation d'un En attente IDA / 58590 Support and Sector A posteriori Individuel Limited 136,363.00 0.00 2019-10-29 2019-11-03 2019-11-24 2019-12-29 2020-06-26 dispositif national de suivi d'exécution Governance des prix de transports des marchandises BF-PST2-144594-CS-INDV / Recrutement d'un consultant individuel pour l'élaboration Component C: Institutional En attente de la stratégie, la conception IDA / 58590 Support and Sector A posteriori Individuel Limited 5,000.00 0.00 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2020-02-14 d'exécution de la campagne de Governance communication de la Mairie de Ouagadougou BF-PST2-144389-CS-INDV / Component D: Project En attente Recrutement d'un spécialiste IDA / 58590 A posteriori Individuel Open 22,000.00 0.00 2019-12-30 2020-02-17 2020-03-09 2020-04-13 2020-05-19 Management d'exécution en suivi-évaluation BF-PST2-147504-CS-INDV / Réalisation d’un Cadre de Component C: Institutional Gestion Environnementale et En attente IDA / 58590 Support and Sector A posteriori Individuel Limited 55,000.00 0.00 2020-01-06 2020-01-11 2020-02-01 2020-03-07 2020-05-06 sociale du Projet de d'exécution Governance Transport Public de Ouaga (optis) BF-PST2-147505-CS-INDV / Réalisation d’un Cadre de Component C: Institutional Politique de Réinstallation En attente IDA / 58590 Support and Sector A posteriori Individuel Limited 55,000.00 0.00 2020-01-07 2020-01-12 2020-02-02 2020-03-08 2020-05-07 du Projet de Transport d'exécution Governance Public de Ouagadougou (optis) BF-PST2-147508-CS-INDV / Cadre de Politique de Component C: Institutional En attente Réinstallation (CPR) du IDA / 58590 Support and Sector A posteriori Individuel Limited 55,000.00 0.00 2019-12-27 2020-01-01 2020-01-22 2020-02-26 2020-03-27 d'exécution Projet Intégré de Governance Connectivité et de Mobilité BF-PST2-147509-CS-INDV / Cadre de Gestion Component C: Institutional En attente Environnementale et sociale IDA / 58590 Support and Sector A posteriori Individuel Limited 55,000.00 0.00 2020-01-07 2020-01-12 2020-02-02 2020-03-08 2020-04-07 d'exécution du Projet Intégré de Governance Connectivité et de Mobilité Page 13