Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) WAEMU Affordable Housing Finance (P161658) AFRICA | Western Africa | Finance, Competitiveness and Innovation Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 2 | ARCHIVED on 11-Jun-2018 | ISR32159 | Implementing Agencies: CRRH, BOAD, WAEMU, WAEMU Commission Key Dates Key Project Dates Bank Approval Date:28-Sep-2017 Effectiveness Date:21-Dec-2017 Planned Mid Term Review Date:10-Jul-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2022 Revised Closing Date:31-Dec-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective is to expand access to long-term housing finance in WAEMU, including for underserved households. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Participating Banks Mortgage Refinancing:(Cost $80.00 M) Non-Bank Financial Institutions Mortgage Refinancing:(Cost $50.00 M) Affordable Housing Policies Technical Assistance:(Cost $15.00 M) Technical Assistance for Non-Bank Financial Institutions and CRRH:(Cost $5.00 M) Design of Regional Guarantee Product for Housing Loans:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Satisfactory Overall Risk Rating  Substantial  Substantial 6/11/2018 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) Implementation Status and Key Decisions Implementation is moving ahead and a lot of progress has been made in the past 6 months. First disbursement under the DLI (tier 2) was done in February 2018. First disbursements under the technical assistance have just been completed at the end of May for CRRH and WAEMU Commission. Procurement activities for CRRH have been slow due to the lack of familiarity with Bank's procedures, and the recruitment of a specialist in Bank procedures will help. The WAEMU commission has assigned a well-trained staff to the project and procurement activities are moving well. The speed of implementation of the technical assistance could be an issue considering the strong expectations of the WAEMU countries to obtain support. It will be important that focal points of each country support the WAEMU Commission. An official launch of the project is planned in the margin of the WAEMU Council of Ministers meeting in September. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Substantial  Substantial  Substantial Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  Moderate  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  Substantial  Substantial  Substantial Fiduciary  Substantial  Substantial  Substantial Environment and Social  Moderate  Moderate  Moderate Stakeholders  Substantial  Substantial  Substantial Other  Moderate  Moderate  Moderate Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Number of new mortgage loans issued by banks in WAEMU (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 12,000.00 -- -- 32,000.00 Date 28-Dec-2017 -- -- 29-Dec-2022 6/11/2018 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) PHINDPDOTBL  Number of housing loans issued by banks and non bank financial institutions below FCFA 15 Million refinanced by CRRH (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,440.00 -- 4,718.00 13,000.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 Overall Comments Intermediate Results Indicators PHINDIRITBL  Outstanding bonds issued by CRRH (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 180,000,000.00 -- 242,000,000.00 740,000,000.00 Date 28-Dec-2017 -- 28-Feb-2018 29-Dec-2022 PHINDIRITBL  Number of non-bank financial institutions making use of CRRH refinancing window (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 6/11/2018 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) PHINDIRITBL  A land and housing price index is established in a research centre, harmonized across all 8 countries and with effective data in at least 2 countries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 PHINDIRITBL  Number of countries which implement recommendations from the advisory services on affordable housing programs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 PHINDIRITBL  A regional guarantee product for housing loans is available (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 PHINDIRITBL  Number of housing loans issued by non-bank financial institutions below 10 M FCFA and refinanced by CRRH (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3,000.00 Date 28-Dec-2017 -- 30-Apr-2018 29-Dec-2022 6/11/2018 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) PHINDIRITBL  Survey of a sample of beneficiaries by mid-term review to provide feedback on terms and conditions of housing loans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 28-Dec-2017 -- -- 29-May-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P161658 IDA-61410 Effective USD 130.00 130.00 0.00 22.02 110.00 17% P161658 IDA-D2360 Effective USD 25.00 25.00 0.00 0.00 25.82 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P161658 IDA-61410 Effective 28-Sep-2017 13-Oct-2017 21-Dec-2017 31-Dec-2022 31-Dec-2022 P161658 IDA-D2360 Effective 28-Sep-2017 13-Oct-2017 21-Dec-2017 31-Dec-2022 31-Dec-2022 Cumulative Disbursements 6/11/2018 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report WAEMU Affordable Housing Finance (P161658) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/11/2018 Page 6 of 6 Public Disclosure Copy