65741 v2 Restructuring Status: Draft Restructuring Type: Level two Last modified on date : 11/22/2011 1. Basic Information Project ID & Name P082373: GH-Urban Env Sanitation 2 ( FY04) Country Ghana Task Team Leader Ventura Bengoechea Sector Manager/Director Junaid Kamal Ahmad Country Director Sergiy V. Kulyk Original Board Approval Date 04/29/2004 Original Closing Date: 06/30/2010 Current Closing Date 12/31/2011 Proposed Closing Date [if applicable] 05/31/2012 EA Category A-Full Assessment Revised EA Category A-Full Assessment-Full Assessment EA Completion Date 11/11/2003 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 2.37 2.37 COMM 2.96 2.96 IDA 62.00 62.00 MUNI 3.25 3.25 NDF 10.35 10.35 Total 80.93 80.93 3. Borrower Organization Department Location Republic of Ghana Ghana 4. Implementing Agency Organization Department Location ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 11/22/2011 42.84 Fiscal Year Annual Cumulative 2011 0.00 42.84 Total 42.84 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The project development objective is to improve urban living conditions in regard to environmental health, sanitation, drainage, vehicular access, and solid waste management in a sustainable fashion, with special emphasis on the poor. 7b. Revised Project Development Objectives/Outcomes [if applicable] iii