The World Bank Report No: ISR4868 Implementation Status & Results Albania SECONDARY AND LOCAL ROADS (P107833) Public Disclosure Copy Operation Name: SECONDARY AND LOCAL ROADS (P107833) Project Stage: Implementation Seq.No: 8 Status: ARCHIVED Archive Date: 07-May-2011 Country: Albania Approval FY: 2008 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Albanian Development Fund (ADF) Key Dates Board Approval Date 03-Jun-2008 Original Closing Date 31-Dec-2012 Planned Mid Term Review Date 30-Nov-2010 Last Archived ISR Date 07-May-2011 Effectiveness Date 29-Sep-2008 Revised Closing Date 31-Dec-2012 Actual Mid Term Review Date 17-Nov-2010 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to improve access to essential services and economic markets, via the provision of all weather roads, for the resident population in the hinterland of the project roads. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost COMPONENT 1 - THE IMPROVEMENT OF PRIORITY SECTIONS OF THE SECONDARY 7.50 (REGIONAL) ROAD NETWORK COMPONENT 2 - THE IMPROVEMENT OF PRIORITY SECTIONS OF THE LOCAL (COMMUNE) 1.60 ROAD NETWORK COMPONENT 3 - IMPLEMENTATION AND INSTITUTIONAL SUPPORT 10.90 Overall Ratings Public Disclosure Copy Previous Rating Current Rating Progress towards achievement of PDO Highly Satisfactory Satisfactory Overall Implementation Progress (IP) Highly Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview The implementation of the Secondary and Local Roads Project is continuing to progress very well. The works are either complete, or substantially complete, on all eleven road sections within the project. In addition, all year 5 project monitoring indicators have been met. Page 1 of 6 The World Bank Report No: ISR4868 The project also prepared a program for other donors to contribute, and at present some USD 500 million have been committed or are under discussion, in parallel to the Bank/OPEC Fund for International Development (OFID) contribution. Public Disclosure Copy Locations Country First Administrative Division Location Planned Actual Albania Not Entered Xarre Albania Not Entered Pllake Albania Not Entered Ciuci Albania Not Entered Podgorie Albania Not Entered Malqene Albania Not Entered Lunxheri Albania Not Entered Kuben Albania Not Entered Korite Albania Not Entered Erind Albania Not Entered Elbasan District Albania Not Entered Domaj Albania Not Entered Diber District Albania Not Entered Renz Albania Not Entered Valare Albania Not Entered Berat County Albania Not Entered Velabisht Public Disclosure Copy Albania Not Entered Tirana District Albania Not Entered Strum Albania Not Entered Shkoder District Albania Not Entered Nenshat Albania Not Entered Mbreshtan Albania Not Entered Marinez Page 2 of 6 The World Bank Report No: ISR4868 Country First Administrative Division Location Planned Actual Albania Not Entered Lezhe Public Disclosure Copy Albania Not Entered Kallmeti i Madh Albania Not Entered Ura e Gorices Albania Not Entered Fier District Albania Not Entered Vau i Dejes Albania Not Entered Belsh Albania Not Entered Fierze Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Change in road user perception of road quality Percentage Value 0.00 97.00 20.00 Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Results far exceeded as reported in previous ISR. Proportional reduction in travel time on project Percentage Value 0.00 60.00 40.00 roads in free flowing conditions Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Targets met and exceeded as stated in the previous ISR. Updates will be sought during the next mission in May. Share of rural population with access to an all- Percentage Value 0.00 0.00 season road Date 22-Sep-2011 31-Dec-2012 Public Disclosure Copy Comments No robust data available for this indicator. Team is investigating data options and will update this information during the next supervision mission in May. Number of rural people with access to an all- Number Value 0.00 0.00 season road Sub Type Supplemental Page 3 of 6 The World Bank Report No: ISR4868 Roads in good and fair condition as a share of Percentage Value 32.00 33.00 34.00 total classified roads Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments suppl. value is for rural roads Actual 33% Public Disclosure Copy in Albania, of which project roads are a part. Size of the total classified network Kilometers Value 4979.00 4979.00 4979.00 Sub Type Supplemental Proportional increase in traffic volumes on Text Value 0 21 10 percentage points project roads - one year after scheme Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 complettion Comments Target was met and exceeded as reported in previous ISR. Updates to be sought during next mission in May. Number of communities that have improved Text Value 0 81 50 access to markets, social services and Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 administrative centers by project end Comments This reflects that all 106.2 km of road has been substantially completed. Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Increase in annual recurrent maintenance Percentage Value 0.00 0.00 budget for Local roads Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Team is investigating data options for the baseline and current values during next mission in May Public Disclosure Copy Increase in annual recurrent maintenance Percentage Value 0.00 0.00 budget for National roads Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Team is investigating the possibility of securing this information and will update this information during the next mission in May Number of people in the communities trained to Number Value 0.00 0.00 procure contractors to undertake maintenance Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Page 4 of 6 The World Bank Report No: ISR4868 Comments Team is investigating the possibility of securing this information and will update this information during the Public Disclosure Copy next mission in May Number of people trained to undertake Number Value 0.00 maintenance Date 30-Jun-2008 31-Dec-2012 Comments Team will include this information during next mission in May Management Information System in place and Text Value Not established not yet establisehed Established functioning Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Roads rehabilitated, Non-rural Kilometers Value 0.00 106.20 109.00 Date 30-Jun-2008 22-Sep-2011 31-Dec-2012 Comments Data on Financial Performance (as of 16-Mar-2012) Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P107833 IDA-44590 Effective 03-Jun-2008 02-Jul-2008 29-Sep-2008 31-Dec-2012 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P107833 IDA-44590 Effective XDR 12.20 12.20 0.00 9.67 2.53 79.00 Disbursement Graph Public Disclosure Copy Page 5 of 6 The World Bank Report No: ISR4868 Public Disclosure Copy Key Decisions Regarding Implementation There are no key decisions requiring disclosure at this time Restructuring History Level two Approved on 23-May-2011 Related Projects There are no related projects. Public Disclosure Copy Page 6 of 6