The World Bank Report No: ISR12432 Implementation Status & Results Nigeria Lagos Eko Secondary Education Project (P106280) Public Disclosure Copy Operation Name: Lagos Eko Secondary Education Project (P106280) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive Date: 27-Mar-2014 Country: Nigeria Approval FY: 2009 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 16-Jun-2009 Original Closing Date 31-Dec-2013 Planned Mid Term Review Date 14-Nov-2011 Last Archived ISR Date 15-Sep-2013 Effectiveness Date 09-Nov-2009 Revised Closing Date 30-Jun-2014 Actual Mid Term Review Date 06-Dec-2011 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the project is to improve the quality of public junior and senior secondary education in Lagos State. The project will support over half a million public school students in 637 secondary schools, over 7,000 teachers and school administrators and will strengthen the capacity of district, state and education institutions. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Secondary School Effect. through School Development Grants 62.60 Enhancing Quality Assurance for Junior and Senior Secondary Schools 13.70 Project Coordination/Management 4.60 Strengthening Federal Post-Basic Edu Strategy 5.00 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Highly Satisfactory Highly Satisfactory Overall Implementation Progress (IP) Highly Satisfactory Highly Satisfactory Overall Risk Rating Low Low Implementation Status Overview The Project has continued to excel, and has achieved or exceeded its end of project targets. The targeted improvements in schools (measured by project-administered standardized student tests) has been exceeded with 90% of the schools showing improvement comparedto the target of 40% by end of the project. In 2013 , the West Africa Senior Secondary Certificate Examination English pass grade was 85% improving from 71 % in 2009. The pass grade improved from 57% to 84% and 52% to 85% in Mathematics and Biology Page 1 of 7 The World Bank Report No: ISR12432 respectively. Some schools attained a 100% pass rate in the 2013 West Africa Senior Secondary Certificate Examinations (WASSCE) across different subjects. Additionally, the analysis of results from the 2013 West African Examinations Council (WAEC) external standardized exams and Junior Secondary School Exams showed substantial improvement in passing grade in all the three subject areas in 2013 compared to the 2009 baseline data. In particular, the percentage of students with five credit passes including English and Mathematics in WASSCE has increased from 18% in 2009 to 41% in 2013. Public Disclosure Copy The Project has also continued to make strong progress in the distribution of school grants, with 100% of all secondary schools receiving their grants within the stipulated period (including eleven schools with facilities to accommodate individual with disabilities). A total of 7,998 trainees participated in the leadership training for principals and school district administrators, exceeding the appraisal target of 1,706 by over 400%. The number of district level staff trained also exceeded appraisal targets (1,643 versus 693). Moreover, the Project exceeded target for teacher training in English, Mathematics and Science—training 16,832 teachers (versus a target of 5,385). An additional 25,455 teachers were trained under the school grants ( a significantly greater number than the original target of 1,615 teachers). All the five targeted national and international public-private partnerships (PPP) have been completed and put into use. Locations Country First Administrative Division Location Planned Actual Nigeria Not Entered Ikorodu Nigeria Not Entered Kosofe Nigeria Not Entered Shomolu Nigeria Not Entered Lagos Mainland Nigeria Not Entered Apapa Nigeria Not Entered Amuwo-Odofin Nigeria Not Entered Ojo Nigeria Not Entered Badagry Nigeria Not Entered Lagos Island Nigeria Not Entered Agege Public Disclosure Copy Nigeria Not Entered Alimosho Nigeria Not Entered Ifako-Ijaiye Nigeria Not Entered Epe Nigeria Not Entered Ibeju-Lekki Nigeria Not Entered Ikeja Nigeria Not Entered Mushin Page 2 of 7 The World Bank Report No: ISR12432 Country First Administrative Division Location Planned Actual Nigeria Not Entered Oshodi-Isolo Public Disclosure Copy Nigeria Not Entered Eti-Osa Nigeria Not Entered Surulere Nigeria Not Entered Ajeromi-Ifelodun Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Increase in percentage of public senior Percentage Value 41.00 84.00 45.00 secondary students with pass grade in Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 WASSCE in English, Math and Biology Comments Target exceeded English Percentage Value 41.00 85.00 50.00 Sub Type Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Breakdown Comments Target exceeded Math Percentage Value 41.00 84.00 49.00 Sub Type Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Breakdown Comments Target exceeded Biology Percentage Value 41.00 85.00 37.00 Sub Type Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Breakdown Comments Target exceeded Increase in percentage of public junior Percentage Value 41.00 60.00 45.00 secondary students at or above credit for JSCE Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 in English, Math, Integrated Science Comments Target exceeded Public Disclosure Copy English Percentage Value 32.00 70.00 45.00 Sub Type Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Breakdown Comments Target exceeded Math Percentage Value 31.00 45.00 45.00 Sub Type Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Breakdown Comments Target acheived Integrated Science Percentage Value 27.00 65.00 31.00 Page 3 of 7 The World Bank Report No: ISR12432 Sub Type Date 01-Sep-2008 03-Nov-2013 31-Dec-2013 Breakdown Comments Target exceeded Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of State secondary education plans Number Value 0.00 5.00 5.00 supported under the project Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments Target met. This has been measured throughout the project life but now included as part of the indicators required and as stated inthe PAD Detailed Program and annual plans developed, Percentage Value 0.00 100.00 100.00 discussed, and agreed with the Bank by Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 December 31 of preceeding year Comments Target met. This has been measured throughout the project life but now included as part of the indicators required and as stated inthe PAD Result Based Monitoring and Evaluation Percentage Value 0.00 100.00 95.00 System established and implimented Date 01-Sep-2009 04-Nov-2013 31-Dec-2013 continously Comments Target exceeded. This has been measured throughout the project life but now included as part of the indicators required and as stated in the PAD Annual program outputs and reports Percentage Value 0.00 100.00 100.00 Public Disclosure Copy disseminated in first quarter of succeeding year Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 Comments Target met. This has been measured throughout the project life but now included as part of the indicators required and as stated inthe PAD Page 4 of 7 The World Bank Report No: ISR12432 Required procurement technical and financial Percentage Value 0.00 100.00 95.00 monitoring reports are provided in a Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 satisfcatory and timely manner Comments Target exceeded. This has Public Disclosure Copy been measured throughout the project life but now included as part of the indicators required and as stated in the PAD Testing agencies release exam results within 2 Yes/No Value No Yes Yes months of adminsitration Date 10-Dec-2013 31-Dec-2013 Comments Target met. This has been measured throughout the project life but now included as part of the indicators required and as stated inthe PAD Technical College grant activities completed on Percentage Value 0.00 80.00 60.00 time Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 Comments Target exceeded. This has been measured throughout the project life but now included as part of the indicators required and as stated in the PAD Targetted # schools reporting above 80% Percentage Value 0.00 97.00 50.00 teachers attendnace during school year Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 Comments Target exceeded. This has been measured throughout the project life but now included as part of the indicators required and as Public Disclosure Copy stated in the PAD. Secondary schools receiving grants within 60 Percentage Value 0.00 100.00 80.00 days of school Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 Comments Target exceeded. This has been measured throughout the project life but now included as part of the indicators required and as stated in the PAD Page 5 of 7 The World Bank Report No: ISR12432 District staff trained in project monitoring , Number Value 0.00 1643.00 693.00 admin & financial management ( cummulative) Date 01-Sep-2008 10-Dec-2013 31-Dec-2013 Comments Target exceeded. Public Disclosure Copy School principals and vice trained on Number Value 0.00 7998.00 1706.00 performance improvement and grant Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 operations Comments No school principals ( and Target exceeded vice) training based on performance and grant operations Percentage targeted schools demonstrating Percentage Value 0.00 98.00 40.00 improvement in learning outcomes Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments No standardize test linking Target exceeded result to resources for improved performance Partnerships between technical colleges and Number Value 0.00 5.00 5.00 private sector Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments No partnership between Target Acheieved technical colleges and private sector New standardized tests developed and Number Value 0.00 66.00 18.00 administered Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments No uniform and standardized Target exceeded tests Number teachers trained on leadership and/or Number Value 0.00 16832.00 5385.00 core subject areas (cumulative) Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments No training on core subject Target exceeded areas based on need assessment Number of teachers trained under school Number Value 0.00 28125.00 1615.00 Public Disclosure Copy grants (cumulative) Date 01-Sep-2008 04-Nov-2013 31-Dec-2013 Comments No training under school Target exceeded. grants Data on Financial Performance (as of 23-Jan-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P106280 IDA-45910 Effective 16-Jun-2009 20-Jul-2009 09-Nov-2009 31-Dec-2013 30-Jun-2014 Page 6 of 7 The World Bank Report No: ISR12432 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P106280 IDA-45910 Effective XDR 63.60 63.60 0.00 63.25 0.35 99.00 Public Disclosure Copy Disbursement Graph Key Decisions Regarding Implementation The rating of the project's Implementation Progress (IP) remains Highly Satisfactory on the basis of the high level of improvement in the execution of program activities, legal covenants, project management and safeguard issues and especially in terms of project disbursements. The towards achievement of the Project Development Objective (PDO) is Highly Satisfactory, with significant improvements in the senior and Junior secondary examinations in English and Science, and Mathematics in the project-administered standardized student tests. Restructuring History Public Disclosure Copy There has been no restructuring to date. Related Projects P148593-Lagos Eko Secondary Education Project Additional Financing Page 7 of 7