The World Bank Report No: ISR5219 Implementation Status & Results Tonga Tonga Post Tsunami Reconstruction (P120595) Public Disclosure Copy Operation Name: Tonga Post Tsunami Reconstruction (P120595) Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 12-Oct-2012 Country: Tonga Approval FY: 2011 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Project Management Unit Key Dates Board Approval Date 19-Oct-2010 Original Closing Date 31-Mar-2013 Planned Mid Term Review Date 15-Mar-2012 Last Archived ISR Date 21-Sep-2011 Effectiveness Date 09-Nov-2010 Revised Closing Date 31-Mar-2013 Actual Mid Term Review Date 10-Sep-2012 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project objective is to assist the Government of Tonga to implement its Niuatoputapu Priority Tsunami Recovery Program aimed atrecovering the living standard of the population living in the island affected by the Tsunami of September 30, 2009, through the reconstruction of residential houses with auxiliary water facilities in Niuatoputapu, and strengthening Tonga's capacity to address future natural disasters. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Component 1 - Cyclone-Resistant Housing Construction 3.35 Component 2 - Retrofitting of partially damaged housing and buildings 0.35 Component 3 - Strengthening of Disaster Risk Management 0.50 Component 4 - Project Management 0.40 Public Disclosure Copy Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview Housing reconstruction, including water and sanitation facilities, is still behind schedule but has been making much better progress. The Ministry of Lands has received equipment needed to help strengthen its disaster risk management capacity,and training of the Ministry's staff is progressing well, though some capacity building activities are still delayed. Page 1 of 5 The World Bank Report No: ISR5219 Locations Country First Administrative Division Location Planned Actual Tonga Niuas Niuatoputapu Public Disclosure Copy Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Restored Housing for Affected Families Number Value 0.00 39.00 73.00 Date 05-Oct-2010 06-Sep-2012 31-Mar-2013 Comments 0 houses restored at Physical progress has This component includes beginning of project focused on construction by construction and supervision activity rather than of 85 units of low cost cyclone construction by home. While category 4 resistant housing only 39 homes have been in NTT to replacecompletely completedand handed over to damaged houses. However, their new owners, 80% of the some houses were already overall construction is restored by an NGO, so the complete. current target is 73 units. In addition, the project will retrofit 40 partially damaged structures. Provision of auxiliary water and sanitation Yes/No Value No No Yes facilities Date 05-Oct-2010 06-Sep-2012 31-Mar-2013 Comments No auxiliary water and At time of mission, auxiliary Monitoring indicator is yes/no sanitation facilities provided water and sanitation facilities whether or not auxiliary water have been constructed for 39 and sanitation facilities are houses, but these facilities provided. could not be used as not connected to the reticulated Public Disclosure Copy water supply and due to drought conditions no collected rainwater was available. The connection of the new houses to the reticulated water system has been proposed as additional activity . Establishment of Community Risk Yes/No Value No No Yes Management Plans Date 05-Oct-2010 10-Sep-2012 31-Mar-2013 Page 2 of 5 The World Bank Report No: ISR5219 Comments No risk management plans At end of most recent Have community risk supervision mission, no risk management plans management plans yet established no later than established. project closing date. Public Disclosure Copy Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Supply of materials to NTT Percentage Value 0.00 80.00 100.00 Date 05-Oct-2010 06-Sep-2012 31-Dec-2011 Comments 0% at project start-up Approximately 80% of the 100% at end of year 1 materials have been supplied to NTT. Enhance mapping capacity Percentage Value 0.00 100.00 100.00 Date 05-Oct-2010 10-Sep-2012 31-Mar-2013 Comments 0% at project start-up Essential mapping equipment, GIS computer hard- and software, including training have been provided to enhance the mapping capacityof the GIS unit of the Ministry of Lands, Environment, Climate Change and Natural Resources. Improved Risk Information Percentage Value 0.00 10.00 100.00 Date 05-Oct-2010 10-Sep-2012 31-Mar-2013 Comments 0% at project start-up A needs and capacity assessment of the responsible line ministry to produce and serve risk information has been carried out, and the selection of a Public Disclosure Copy consulting firm to strengthen the capacity of the ministry in incorporating risk information into land-use planningis underway. Community Awareness and Preparedness Percentage Value 30.00 100.00 Date 05-Oct-2010 10-Sep-2012 31-Dec-2012 Comments NA A series of community 100% by end of year 2 disaster awareness Page 3 of 5 The World Bank Report No: ISR5219 workshops (2 per village) have been held to inform community preparedness planning. An operational Public Disclosure Copy exercise to test the disaster response arrangements is planned for October. Community consultation on risk awareness Percentage Value 30.00 100.00 Date 05-Oct-2010 10-Sep-2012 31-Dec-2011 Comments NA A series of community 100% by end of year 1 consultations on disaster risks (2 per village) have been undertaken. Data on Financial Performance (as of 24-Sep-2012) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P120595 IDA-H6280 Effective 19-Oct-2010 19-Oct-2010 09-Nov-2010 31-Mar-2013 31-Mar-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P120595 IDA-H6280 Effective XDR 3.32 3.32 0.00 2.42 0.90 73.00 Disbursement Graph Public Disclosure Copy Page 4 of 5 The World Bank Report No: ISR5219 Public Disclosure Copy Key Decisions Regarding Implementation The Bank and the government of Tonga are discussing the possibility of restructuring the project to implement additional activities in restoring and/or improving essential infrastructure facilities on Niuatoputapu with the project funds that have not yet been committed. Restructuring History Level two Approved on 17-Jan-2012 Related Projects There are no related projects. Public Disclosure Copy Page 5 of 5