The World Bank Report No: ISR16216 Implementation Status & Results Guyana GY Flood Risk Management (P147250) Public Disclosure Copy Operation Name: GY Flood Risk Management (P147250) Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Archive Date: 27-Sep-2014 Country: Guyana Approval FY: 2014 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Investment Project Financing Implementing Agency(ies): Agriculture Sector Development Unit (ASDU), Ministry of Agriculture Key Dates Board Approval Date 04-Jun-2014 Original Closing Date 31-Jan-2019 Planned Mid Term Review Date 06-Feb-2017 Last Archived ISR Date Effectiveness Date Revised Closing Date 31-Jan-2019 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the project is to reduce the risk of flooding in the low-lying areas of the East Demerara. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Priority Works for Flood Risk Reduction 10.30 Institutional Strengthening for Flood Risk Reduction 0.40 Project Management and Implementation Support 1.20 Overall Ratings Previous Rating Current Rating Satisfactory Public Disclosure Copy Progress towards achievement of PDO Overall Implementation Progress (IP) Satisfactory Overall Risk Rating Moderate Implementation Status Overview The project was approved by the Board on June 4, 2014. The signing and effectiveness of the Financing Agreement will take place in the upcoming months. Locations Page 1 of 4 The World Bank Report No: ISR16216 Country First Administrative Division Location Planned Actual Guyana Demerara-Mahaica Demerara-Mahaica Region ✔ Public Disclosure Copy Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Area with improved protection against breach Hectare(Ha) Value 0.00 0.00 15700.00 of EDWC dams Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Area provided with irrigation and drainage Hectare(Ha) Value 0.00 0.00 7864.00 services (ha) Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Area provided with irrigation and drainage Hectare(Ha) Value 0.00 0.00 0.00 services - New (ha) Sub Type Date 11-Sep-2014 31-Jan-2019 Breakdown Comments Area provided with irrigation and drainage Hectare(Ha) Value 0.00 0.00 7864.00 services - Improved (ha) Sub Type Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Breakdown Comments Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Direct project beneficiaries Number Value 0.00 0.00 113066.00 Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Female beneficiaries Percentage Value 0.00 0.00 51.00 Public Disclosure Copy Sub Type Supplemental Water users provided with new/improved Number Value 0.00 0.00 47638.00 irrigation and drainage services (number) Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Water users provided with irrigation and Number Value 0.00 0.00 24010.00 drainage services - female (number) Sub Type Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Breakdown Comments Page 2 of 4 The World Bank Report No: ISR16216 Adoption of operational procedures and Yes/No Value No No Yes surveillance systems for the EDWC dams Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Public Disclosure Copy Length of dam upgraded Kilometers Value 0.00 0.00 4.00 Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Increased drainage capacity (capacity of Cubic Meter(m3) Value 0.00 0.00 5.00 drainage pumps or canals) Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Expanded meteorological, hydrological Yes/No Value No No Yes monitoring network installed and active Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 Comments Adoption of dam safety measures including Yes/No Value No No Yes procedures for emergency preparedness in Date 31-Aug-2014 11-Sep-2014 31-Jan-2019 case of dam breach Comments Data on Financial Performance (as of 09-Jun-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P147250 IDA-54740 Not Effective 04-Jun-2014 31-Jan-2019 31-Jan-2019 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P147250 IDA-54740 Not Effective XDR 7.70 7.70 0.00 0.00 7.70 0.00 Disbursement Graph Public Disclosure Copy Page 3 of 4 The World Bank Report No: ISR16216 Public Disclosure Copy Key Decisions Regarding Implementation Signing and effectiveness of the Financing Agreement is pending and will take place in the upcoming months. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 4 of 4