PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive Bidding 1. 3M and above All contracts (ICB) (Goods) National Competitive Bidding (NCB) 2. less than 3M 2M and above (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated: May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 LN 8421 PH Procurement Plan Updated June 2018 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Ref. No. Description g ent Comments US$1= Source nce by Bank Opening Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review Threshold No. Selection Method Method Threshold US$ US$ 1. Competitive Methods 0.3M & above (may be used for also less 1m and above (QCBS, QBS, FBS) (Firms) than 0.3M) 2. Competitive Method CQS less than 0.3M None (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to justification Firms: 1M and above; Individuals) in accordance with paras. 3.9 and 5.4 Individuals 0.3M and respectively of Consultant Guidelines at above. the Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref. Description of Estimated Cost (USD Funding Procuring Expected Bid Comme Selection Method No. Contract Package million) Source Agency Opening Date nts Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 million) LP/GoP Selection US$1,042,75 Single Source Luzon A ( Php59.152 million) LP/GoP Selection US$1,042,75 Single Source Luzon B ( Php48.614 million) LP/GoP Selection US$1,042,75 Single Source Visaya ( Php29.612 million) LP/GoP Selection US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: LN 8421 PH Procurement Plan Updated June 2018 ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 2019-09-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 88160, IBRD / 84210 Executing Agency(ies): PRDP PSO Luzon B, Dept of Agriculture WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IB-R005-CAT-009-000- Pending 000-2017-AF / Concreting of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 2,490,137.00 0.00 Implementati 2018-08-24 2018-08-30 2018-10-02 2018-11-01 2018-12-06 2019-10-25 Junction Sabangan-Datag Development Envelope on East FMR, Caramoran PRDP-IB-R04A-BTG-003-000- Pending 000-2018-AF / Concreting of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 2,109,275.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Sapangan-Libato, San Juan Development Envelope on FMR PRDP-IB-R04A-BTG-007-SAL- 006-2018-AF / Rehabilitation Pending Component 2: Infrastructure Single Stage - One of Farm-to-Market Road of IBRD / 88160 Post Request for Bids Open - National 866,882.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope Calumpang East and on Calumpang West PRDP-IB-R04A-LAG-004- Pending PAN-004-2017-AF / Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,078,431.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Construction of Pangil Development Envelope on Potable Water System PRDP-IB-R04A-LAG-003- SAA-003-2018-AF / Pending Concreting of Kayhakat- Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 2,048,686.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Bubucal-Inayapan-Calangay- Development Envelope on Coralan-Bagumbayan-Farm-to- Market Road PRDP-IB-R04A-QUE-041- CAT-001-2017-AF / Concreting of San Isidro Pending Component 2: Infrastructure Single Stage - One Bolo San Vicente Kanluran- IBRD / 88160 Post Request for Bids Open - National 3,090,333.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope San Vicente Silangan- on Sta.Maria Dao Farm-To- Market Road Sub-Project PRDP-IB-R04A-QUE-042-SAI- 001-2017-AF / Rehabilitation Pending and Concreting of Concepcion Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 3,817,275.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Palasan to Manggalang Development Envelope on Kiling Farm-To-Market-Road with Line Canal PRDP-IB-R04B-MAR-002-000- Pending 000-2016-AF / Improvement / Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,339,235.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Upgrading of Pantayin-Jolo- Development Envelope on Napo Farm-to-Market Road PRDP-IB-R04B-ORM-006-000- Pending 000-2015-AF / Concreting of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,224,471.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Tigkan-General Esco- Development Envelope on Mahabang Parang FMR Page 1 PRDP-IB-R04B-PAL-005-000- 000-2014-AF / Construction Pending Component 2: Infrastructure Single Stage - One and Upgrading of Junction IBRD / 88160 Post Request for Bids Open - National 3,817,725.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope Salban-Culasian-Magsaysay on FMR PRDP-IB-R04B-PAL-014- ROX-003-2016-AF / Pending Component 2: Infrastructure Single Stage - One Construction and Upgrading IBRD / 88160 Post Request for Bids Open - National 2,835,373.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope of Antonio-Taradungan FMR on with 30 L.M. RCDG Bridge PRDP-IB-R04B-PAL-009- PUE-003-2015-AF / Pending Component 2: Infrastructure Single Stage - One Construction and Concreting IBRD / 88160 Post Request for Bids Open - National 4,760,000.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope of Maruyugon to Macarascas on FMR PRDP-IB-R005-ALB-006-TAB- 001-2017-AF / Rehabilitation Pending Component 2: Infrastructure Single Stage - One / Improvement of Hacienda IBRD / 88160 Post Request for Bids Open - National 3,896,059.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope to Rawis Farm to Market on Road PRDP-IB-R005-ALB-004- Pending MAN-001-2018-AF / Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 698,039.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Construction of Level II Development Envelope on Potable Water System PRDP-IB-R005-CAN-010-JOS- 010-2017-AF / Upgrading of Pending Component 2: Infrastructure Single Stage - One Nakalaya-Sta.Elena-San IBRD / 88160 Post Request for Bids Open - National 4,078,431.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope Isidro-Sta.Cruz-Dayhagan on FMR in Jose Panganiban PRDP-IB-R005-MAS-003- ARO-001-2017-AF / Pending Component 2: Infrastructure Single Stage - One Concreting of San Agustin to IBRD / 88160 Post Request for Bids Open - National 4,829,588.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Development Envelope Tibgao Farm to Market on Road PRDP-IB-R005-SOR-004-000- Pending 000-2017-AF / Rehabilitation Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,443,627.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 of Cumadcad-Canjela Farm-to- Development Envelope on Market Road in Castilla PRDP-IB-R04A-BTG-005-000- 000-2018-AF / Concreting Pending and Improvement of Brgy. Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 3,755,294.00 0.00 Implementati 2018-10-22 2018-10-27 2018-12-08 2019-01-07 2019-02-11 2019-08-10 Leviste Calantas, Matamis Development Envelope on and Nasi, Rosario, Batangas FMR GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IB-LUB-001-R000-000- Component 4: Project 2018-AF / IBUILD IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Component Head PRDP-IB-LUB-002-R000-000- Component 4: Project 2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Bridges Specialist PRDP-IB-LUB-003-R000-000- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 14,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Infrastructure Engineer (RIE) PRDP-IS-LUB-001-R000-000- Component 2: Infrastructure 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Assistant (EA) PRDP-IS-LUB-002-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Driver Implementation Support PRDP-IS-LUB-003-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,824.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Legal Officer Implementation Support PRDP-IS-LUB-004-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 1,906.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Messenger Implementation Support PRDP-IS-LUB-005-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Economist Implementation Support PRDP-IS-LUB-006-R000-000- Component 4: Project 2018-AF / Assistant IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Economist PRDP-IS-LUB-007-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Training Specialist Implementation Support PRDP-IS-LUB-008-R000-000- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate (Office Implementation Support of the Project Director) PRDP-IS-LUB-009-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / M&E Officer Implementation Support PRDP-IS-LUB-010-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / MIS Officer Implementation Support PRDP-IS-LUB-011-R000-000- Component 4: Project 2018-AF / GIS Data IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Specialist PRDP-IS-LUB-012-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / GIS Data Officer Implementation Support Page 3 PRDP-IS-LUB-013-R000-000- 2018-AF / SES Specialist / Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Environment Safeguards Implementation Support Specialist PRDP-IS-LUB-014-R000-000- 2018-AF / SES Officer / Component 4: Project Environment Safeguards IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer/Social Safeguards Officer PRDP-IS-LUB-015-R000-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Development Associate (SES) PRDP-IS-LUB-016-R000-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Head PRDP-IS-LUB-017-R000-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer III PRDP-IS-LUB-018-R000-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer PRDP-IS-LUB-019-R000-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 12,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Assistant PRDP-IS-LUB-020-R000-000- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate Implementation Support (Admin Unit) PRDP-IS-LUB-021-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Utility Implementation Support PRDP-IS-LUB-022-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Procurement Head Implementation Support PRDP-IS-LUB-023-R000-000- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Specialist PRDP-IS-LUB-026-R000-000- Component 4: Project 2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 8,471.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Procurement Officer PRDP-IS-LUB-027-R000-000- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate Implementation Support (Procurement Unit) PRDP-IS-LUB-028-R000-000- Component 4: Project 2018-AF / Finance Unit IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Head PRDP-IS-LUB-029-R000-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support III / Finance Specialist PRDP-IS-LUB-030-R000-000- Individual Component 4: Project Pending 2018-AF / Financial Analyst IBRD / 84210 Post Consultant Open 4,235.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Implementation Support Implementation I Selection Page 4 PRDP-IS-LUB-031-R000-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 8,471.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support I PRDP-IS-LUB-032-R000-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support II PRDP-IS-LUB-033-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Budget Specialist Implementation Support PRDP-IS-LUB-034-R000-000- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate Implementation Support (Finance Unit) PRDP-IS-LUB-035-R000-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,235.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Writer Implementation Support PRDP-IS-LUB-036-R000-000- Component 4: Project 2018-AF / Graphic Layout IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Artist PRDP-IB-LUB-000-R04A-001- Component 4: Project 2018-AF / Alternate IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Component Head PRDP-IB-LUB-000-R04A-002- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 9,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Infrastructure Engineer PRDP-IB-LUB-000-R04A-003- Individual Component 4: Project Pending 2018-AF / Rural IBRD / 84210 Post Consultant Open 5,647.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A-004- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 2,941.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate for Implementation Support I-BUILD PRDP-IS-LUB-000-R04A-001- Component 4: Project 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Assistant for RED PRDP-IS-LUB-000-R04A-002- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 2,914.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate for Implementation Support DRPD PRDP-IS-LUB-000-R04A-003- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 1,764.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Assistant PRDP-IS-LUB-000-R04A-004- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 4,118.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support I PRDP-IS-LUB-000-R04A-005- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support II PRDP-IS-LUB-000-R04A-006- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer PRDP-IS-LUB-000-R04A-007- Individual 2018-AF / Project Component 4: Project Pending IBRD / 84210 Post Consultant Open 2,941.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Development Associate for Implementation Support Implementation Selection Procurement Page 5 PRDP-IS-LUB-000-R04A-008- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,118.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Writer Implementation Support PRDP-IS-LUB-000-R04A-009- Component 4: Project IBRD / 84210 Post Direct Selection Direct 2,353.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Driver Implementation Support Individual PRDP-IS-LUB-000-R04A-010- Component 4: Project Pending IBRD / 84210 Post Consultant Open 5,294.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 2018-AF / Economist Implementation Support Implementation Selection Individual PRDP-IS-LUB-000-R04A-011- Component 4: Project Pending IBRD / 84210 Post Consultant Open 4,235.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 2018-AF / Compliance Officer Implementation Support Implementation Selection PRDP-IS-LUB-000-R04A-012- Component 4: Project 2018-AF / Monitoring and IBRD / 84210 Post Direct Selection Direct 9,412.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Evaluation Officer PRDP-IS-LUB-000-R04A-013- Individual Component 4: Project Pending 2018-AF / Monitoring and IBRD / 84210 Post Consultant Open 5,294.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Implementation Support Implementation Evaluation Specialist Selection PRDP-IS-LUB-000-R04A-014- 2018-AF / SES Component 4: Project Specialist/Social Safeguards IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Specialist/ Environmental Safeguards Specialist PRDP-IS-LUB-000-R04A-015- 2018-AF / SES Officer/Social Component 4: Project Safeguards Officer/ IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Environmental Safeguards Officer PRDP-IS-LUB-000-R04A-016- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / GIS Data Officer Implementation Support PRDP-IB-LUB-000-R04B-001- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 22,588.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Infrastructure Engineer (RIE) PRDP-IB-LUB-000-R04B-002- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Development Associate for Implementation Support I-BUILD PRDP-IS-LUB-000-R04B-001- Component 4: Project 2018-AF / Monitoring & IBRD / 84210 Post Direct Selection Direct 11,294.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Evaluation (M&E) Officer PRDP-IS-LUB-000-R04B-002- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 9,882.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support I PRDP-IS-LUB-000-R04B-003- Individual Component 4: Project Pending 2018-AF / Financial Analyst IBRD / 84210 Post Consultant Open 4,941.00 0.00 2017-11-27 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Implementation Support Implementation I Selection PRDP-IS-LUB-000-R04B-004- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer PRDP-IS-LUB-000-R04B-005- Component 4: Project 2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 9,882.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Procurement Officer Page 6 PRDP-IS-LUB-000-R04B-006- Component 4: Project 2018-AF / Natural Resource IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Management Specialist PRDP-IS-LUB-000-R04B-007- 2018-AF / Social Component 4: Project IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Environment Safeguards Implementation Support Specialist PRDP-IS-LUB-000-R04B-008- Individual 2018-AF / Social Component 4: Project Pending IBRD / 84210 Post Consultant Open 3,765.00 0.00 2017-11-27 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Environment Safeguards Implementation Support Implementation Selection Officer PRDP-IS-LUB-000-R04B-009- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / GIS Data Officer Implementation Support PRDP-IS-LUB-000-R04B-010- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,941.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Writer Implementation Support PRDP-IS-LUB-000-R04B-011- Individual Component 4: Project Pending 2018-AF / Administrative IBRD / 84210 Post Consultant Open 2,941.00 0.00 2017-11-27 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Implementation Support Implementation Officer Selection PRDP-IS-LUB-000-R04B-012- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Development Associate PRDP-IS-LUB-000-R04B-013- Individual Component 4: Project Pending 2018-AF / Administrative IBRD / 84210 Post Consultant Open 706.00 0.00 2018-01-24 2018-03-14 2018-04-04 2018-05-09 2018-11-05 Implementation Support Implementation Assistant Selection PRDP-IS-LUB-000-R04B-014- Individual Component 4: Project Pending 2018-AF / Executive IBRD / 84210 Post Consultant Open 3,529.00 0.00 2018-02-24 2018-04-14 2018-05-05 2018-06-09 2018-12-06 Implementation Support Implementation Assisstant (EA) Selection PRDP-IS-LUB-000-R04B-015- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 2018-AF / Driver Implementation Support PRDP-IB-LUB-000-R005-001- Component 4: Project 2018-AF / RIE (Roads and IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Implementation Support Bridges) Specialist PRDP-IB-LUB-000-R005-002- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 28,235.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Implementation Support Infrastructure Engineer (RIE) PRDP-IS-LUB-000-R005-001- Component 4: Project 2018-AF / Training IBRD / 84210 Post Direct Selection Direct 4,941.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Implementation Support Coordinator/Project Assistant PRDP-IS-LUB-000-R005-002- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for I- Implementation Support PLAN PRDP-IS-LUB-000-R005-003- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for Implementation Support Econ PRDP-IS-LUB-000-R005-004- Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 2018-AF / PDA for Finance Implementation Support Individual PRDP-IS-LUB-000-R005-005- Component 4: Project Pending IBRD / 84210 Post Consultant Open 3,529.00 0.00 2018-09-08 2018-10-27 2018-11-17 2018-12-22 2019-06-20 2018-AF / PDA for Finance Implementation Support Implementation Selection Page 7 PRDP-IS-LUB-000-R005-006- Component 4: Project IBRD / 84210 Post Direct Selection Direct 2,824.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 2018-AF / Driver Implementation Support Individual PRDP-IS-LUB-000-R005-007- Component 4: Project Pending IBRD / 84210 Post Consultant Open 2,824.00 0.00 2018-09-08 2018-10-27 2018-11-17 2018-12-22 2019-06-20 2018-AF / Driver Implementation Support Implementation Selection PRDP-IS-LUB-000-R005-008- Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2018-03-09 2018-03-19 2018-05-23 2018-11-19 2018-AF / Admin Officer I Implementation Support PRDP-IS-LUB-000-R005-009- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,235.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 2018-AF / Admin Assistant Implementation Support PRDP-IS-LUB-000-R005-010- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2018-03-09 2018-03-19 2018-05-23 2018-11-19 Implementation Support Officer PRDP-IS-LUB-000-R005-011- 2018-AF / Project Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for Implementation Support Procurement PRDP-IS-LUB-000-R005-012- 2018-AF / Program Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for Implementation Support Writer PRDP-IS-LUB-000-R005-013- 2018-AF / Program Component 4: Project IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for Implementation Support SES PRDP-IS-LUB-000-R005-014- Component 4: Project 2018-AF / Monitoring & IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Implementation Support Evaluation (M&E) Officer PRDP-IS-LUB-000-R005-015- 2018-AF / Program Component 4: Project IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 Development Associate for Implementation Support M&E PRDP-IS-LUB-000-R005-016- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-28 2017-12-08 2018-02-11 2018-08-10 2018-AF / GIS Data Officer Implementation Support PRDP-IS-LUB-000-R005-017- Individual 2018-AF / Program Component 4: Project Pending IBRD / 84210 Post Consultant Open 3,529.00 0.00 2017-11-28 2018-01-16 2018-02-06 2018-03-13 2018-09-09 Development Associate for Implementation Support Implementation Selection GGU PRDP-IS-LUB-024-R000-000- Individual Component 4: Project Pending 2018-AF / Procurement IBRD / 84210 Post Consultant Open 9,529.00 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Implementation Support Implementation Officer Selection PRDP-IS-LUB-025-R000-000- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 2017-12-07 2018-02-10 2018-08-09 Implementation Support Officer PRDP-IB-LUB-001-R000-000- Individual Component 4: Project Pending 2019-AF / I-BUILD IBRD / 88160 Post Consultant Direct 19,765.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Component Head Selection PRDP-IB-LUB-002-R000-000- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 14,118.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Specialist Selection PRDP-IB-LUB-003-R000-000- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 25,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer (RIE) Selection Page 8 PRDP-IB-LUB-003-R000-001- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 25,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer (RIE) Selection PRDP-IB-LUB-004-R000-000- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IB-LUB-005-R000-000- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-LUB-001-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,765.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Compliance Officer Implementation Support Implementation Selection PRDP-IS-LUB-002-R000-000- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 18,353.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Unit Head Selection PRDP-IS-LUB-003-R000-000- Individual Component 4: Project Pending 2019-AF / Executive IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Assistant (EA) Selection PRDP-IS-LUB-004-R000-000- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer III Selection PRDP-IS-LUB-005-R000-000- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 7,765.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer II Selection PRDP-IS-LUB-007-R000-001- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-LUB-007-R000-002- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-LUB-007-R000-003- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-LUB-015-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / MIS Officer Implementation Support Implementation Selection PRDP-IS-LUB-017-R000-000- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer PRDP-IS-LUB-018-R000-000- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,765.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Specialist PRDP-IS-LUB-019-R000-000- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 12,706.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer PRDP-IS-LUB-020-R000-000- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Page 9 PRDP-IS-LUB-021-R000-000- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer PRDP-IS-LUB-022-R000-000- Individual Component 4: Project Pending 2019-AF / Procurement Unit IBRD / 88160 Post Consultant Direct 18,353.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Head Selection PRDP-IS-LUB-023-R000-000- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 12,706.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-LUB-024-R000-000- Individual Component 4: Project Pending 2019-AF / Associate IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Procurement Officer Selection PRDP-IS-LUB-025-R000-000- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-LUB-027-R000-000- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Officer Selection PRDP-IS-LUB-030-R000-000- Individual Component 4: Project Pending 2019-AF / Finance Unit IBRD / 88160 Post Consultant Direct 18,353.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Head Selection Individual PRDP-IS-LUB-031-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,353.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Budget Specialist Implementation Support Implementation Selection PRDP-IS-LUB-032-R000-000- Individual Component 4: Project Pending 2019-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 2,353.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation III Selection PRDP-IS-LUB-033-R000-000- Individual Component 4: Project Pending 2019-AF / Finance Analyst IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation II Selection Individual PRDP-IS-LUB-034-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Finance Analyst I Implementation Support Implementation Selection Individual PRDP-IS-LUB-036-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Finace Analyst I Implementation Support Implementation Selection Individual PRDP-IS-LUB-037-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Budget Analyst Implementation Support Implementation Selection PRDP-IS-LUB-038-R000-000- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-LUB-040-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 12,706.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Economist Implementation Support Implementation Selection Individual PRDP-IS-LUB-041-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Writer Implementation Support Implementation Selection Individual PRDP-IS-LUB-042-R000-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Writer Implementation Support Implementation Selection Page 10 PRDP-IS-LUB-043-R000-000- Individual Component 4: Project Pending 2019-AF / Media Production IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IB-LUB-000-R04A-001- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Infrastructure Specialist Selection PRDP-IB-LUB-000-R04A-002- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A-003- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A-004- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A-005- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-LUB-000-R04A-001- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate for Implementation Support Implementation Selection RDPD PRDP-IS-LUB-000-R04A-002- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection Individual PRDP-IS-LUB-000-R04A-003- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Budget Analsyt Implementation Support Implementation Selection Individual PRDP-IS-LUB-000-R04A-005- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Economist Implementation Support Implementation Selection Individual PRDP-IS-LUB-000-R04A-006- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / GIS Officer Implementation Support Implementation Selection Individual PRDP-IS-LUB-000-R04A-007- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Infoace Writer Implementation Support Implementation Selection PRDP-IS-LUB-000-R04A-008- Individual Component 4: Project Pending 2019-AF / Monitoring and IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Evaluation Officer Selection PRDP-IS-LUB-000-R04A-009- Individual Component 4: Project Pending 2019-AF / Monitoring and IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Evaluation Officer Selection PRDP-IS-LUB-000-R04A-010- Individual Component 4: Project Pending 2019-AF / Associate M&E IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-LUB-000-R04A-011- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-LUB-000-R04A-012- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer Page 11 PRDP-IB-LUB-000-R04B-013- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer PRDP-IB-LUB-000-R04B-014- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate Implementation Support Implementation Selection (IPLAN) PRDP-IS-LUB-000-R04B-015- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate Implementation Support Implementation Selection (IBUILD) PRDP-IS-LUB-000-R04B-016- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate Implementation Support Implementation Selection (ISUPPORT) PRDP-IS-LUB-000-R04B-019- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 5,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate Implementation Support Implementation Selection (INFO) PRDP-IB-LUB-000-R04B-003- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Infrastructure Engineer (RIE) Selection PRDP-IB-LUB-000-R04B-004- Individual 2019-AF / Project Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Development Associate for Implementation Support Implementation Selection IBUILD PRDP-IS-LUB-000-R04B-001- Individual Component 4: Project Pending 2019-AF / Monitoring & IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04B-002- Individual 2019-AF / Associate Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Monitoring & Evaluation Implementation Support Implementation Selection (M&E) Officer PRDP-IS-LUB-000-R04B-003- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection PRDP-IS-LUB-000-R04B-004- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation I Selection PRDP-IS-LUB-000-R04B-005- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection PRDP-IS-LUB-000-R04B-006- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection Individual PRDP-IS-LUB-000-R04B-007- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Budget Analyst Implementation Support Implementation Selection PRDP-IS-LUB-000-R04B-008- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection Page 12 PRDP-IS-LUB-000-R04B-009- Individual Component 4: Project Pending 2019-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Procurement Officer Selection PRDP-IS-LUB-000-R04B-010- Individual 2019-AF / Social & Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer PRDP-IS-LUB-000-R04B-011- Individual 2019-AF / Associate Social & Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Environmental Safeguards Implementation Support Implementation Selection Officer Individual PRDP-IS-LUB-000-R04B-012- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / GIS Officer Implementation Support Implementation Selection Individual PRDP-IS-LUB-000-R04B-013- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-LUB-000-R04B-014- Individual Component 4: Project Pending 2019-AF / Executive IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Assistant (EA) Selection PRDP-IS-LUB-000-R04B-018- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-LUB-000-R04B-020- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Economist Implementation Support Implementation Selection PRDP-IB-LUB-000-R005-002- Individual Component 4: Project Pending 2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer (RIE) Selection PRDP-IS-LUB-000-R005-001- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 5,882.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Officer II Selection PRDP-IS-LUB-000-R005-002- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer I Selection PRDP-IS-LUB-000-R005-003- Individual Component 4: Project Pending 2019-AF / Training IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Coordinator Selection Individual PRDP-IS-LUB-000-R005-006- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Economist Implementation Support Implementation Selection PRDP-IS-LUB-000-R005-007- Individual Component 4: Project Pending 2019-AF / Program IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate-Econ Selection PRDP-IS-LUB-000-R005-008- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Development Associate- Implementation Support Implementation Selection IBUILD PRDP-IS-LUB-000-R005-013- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection Page 13 PRDP-IS-LUB-000-R005-014- Individual Component 4: Project Pending 2019-AF / Associate IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Procurement Officer Selection PRDP-IS-LUB-000-R005-015- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate- Implementation Support Implementation Selection Procurement Individual PRDP-IS-LUB-000-R005-016- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-LUB-000-R005-017- Individual 2019-AF / Program Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate- Implementation Support Implementation Selection InfoAce Individual PRDP-IS-LUB-000-R005-018- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 2019-AF / SES Officer Implementation Support Implementation Selection PRDP-IS-LUB-000-R005-019- Individual Component 4: Project Pending 2019-AF / Associate SES IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Officer Selection PRDP-IS-LUB-000-R005-020- Individual Component 4: Project Pending 2019-AF / Program IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate-SES Selection PRDP-IS-LUB-000-R005-021- Individual Component 4: Project Pending 2019-AF / Monitoring & IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R005-022- Individual Component 4: Project Pending 2019-AF / Associate M&E IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 2019-04-12 2019-05-03 2019-06-07 2019-12-04 Implementation Support Implementation Officer Selection Individual PRDP-IS-LUB-000-R005-023- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / GIS Officer Implementation Support Implementation Selection Page 14