The World Bank Report No: ISR15764 Implementation Status & Results Yemen, Republic of Corridor Highway Project (P145361) Public Disclosure Copy Operation Name: Corridor Highway Project (P145361) Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Archive Date: 03-Sep-2014 Country: Yemen, Republic of Approval FY: 2014 Product Line: IBRD/IDA Region: MIDDLE EAST AND NORTH AFRICA Lending Instrument: Investment Project Financing Implementing Agency(ies): Ministry of Public Works and Highways Key Dates Board Approval Date 02-Jun-2014 Original Closing Date 30-Jun-2019 Planned Mid Term Review Date 30-Sep-2015 Last Archived ISR Date Effectiveness Date Revised Closing Date 30-Jun-2019 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is "improved transport connectivity and safety on the targeted section of the transport corridor between Aden and Taiz". Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Highway Construction 150.00 Institutional Support and Strengthening 22.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Public Disclosure Copy Overall Implementation Progress (IP) Overall Risk Rating Substantial Implementation Status Overview Despite the difficult operating environment in Yemen, the project is progressing well. Pre-qualification of contractors for highway construction is complete. The procurement processes for most other contracts under the project's components (civil works and institutional strengthening activities) are underway. The Grant agreement is to be signed on August 24, 2014 and the grant should become effective in September 2014. Locations No Location data has been entered Page 1 of 5 The World Bank Report No: ISR15764 Results Project Development Objective Indicators Public Disclosure Copy Indicator Name Core Unit of Measure Baseline Current End Target Decrease in Vehicle Operating Costs for traffic Percentage Value 100.00 100.00 93.00 between Aden and Noubat Dokaim. Date 26-Dec-2013 14-Jul-2014 30-Jun-2019 Comments Baseline is the VOC on The target for this indicator Target figure is based on existing road between Aden can only be achieved once estimated average VOC and Noubat Dokaim the highway is complete and reduction of at least 7 percent calculated with HDM4 during open to traffic. calculated using HDM4, for project preparation. traffic between Aden andNoubat Dokaim. Traffic fatalities on road corridor between Aden Number Value 74.00 50.00 and Noubat Dokaim. Date 26-Dec-2013 14-Jul-2014 30-Jun-2019 Comments Baseline data as obtained This indicator will be Target number is for both the from Yemen traffic police in measured once the highway existing road and the new 2013 (2012 data) for existing is open to traffic. highway between Aden and road between Aden and Noubat Dokaim. Noubat Dokaim. Decrease in travel time between Aden and Minutes Value 60.00 60.00 40.00 Noubat Dokaim. Date 26-Dec-2013 14-Jul-2014 30-Jun-2019 Comments Baseline is typical travel time The target for this indicator Target is to be measured after observed in 2013. can only be achieved once completion of the new the highway is complete and highway between Aden and open to traffic. Noubat Dokaim. Direct project beneficiaries Number Value 0.00 0.00 4000000.00 Date 26-Dec-2013 14-Jul-2014 30-Jun-2019 Comments The highway must be Number of people in the area completed and open to traffic of influence of the new Aden - for this indicator to be fulfilled. Taiz Corridor Highway. Public Disclosure Copy Female beneficiaries Percentage Value 0.00 0.00 50.00 Sub Type Supplemental Intermediate Results Indicators Page 2 of 5 The World Bank Report No: ISR15764 Indicator Name Core Unit of Measure Baseline Current End Target Roads constructed, Rural Kilometers Value 0.00 0.00 55.00 Date 26-Dec-2013 14-Jul-2014 30-Jun-2019 Public Disclosure Copy Comments The selection of contractors The target figure is the length and supervision consultant for of the highway section to be highway construction is built through the project. ongoing. Number of MPWH staff trained. Number Value 0.00 0.00 30.00 Date 12-Feb-2014 14-Jul-2014 30-Jun-2019 Comments Earthworks completion rate. Percentage Value 0.00 0.00 100.00 Date 12-Feb-2014 14-Jul-2014 30-Jun-2019 Comments The selection of contractors and supervision consultant for highway construction is ongoing. Definition and establishment of an institutional Yes/No Value No No Yes structure for the management, operation and Date 12-Feb-2014 14-Jul-2014 30-Jun-2019 maintenance of the new Corridor Highway. Comments The selection of the This indicator is considered consultant to undertake the fulfilled if the MPWH has study that will inform the formally adopted an institutional structure is appropriate structure. ongoing. No. of person-days of work created. Number Value 0.00 0.00 1280000.00 Date 12-Feb-2014 14-Jul-2014 30-Jun-2019 Comments Construction activity has not Number (in person-days) of yet commenced. overall employment related to the construction of the Corridor Highway during the project period. Public Disclosure Copy Fiber Optic Duct installed. Yes/No Value No No Yes Date 12-Feb-2014 14-Jul-2014 30-Jun-2019 Comments Fiber Optic ducts not installed. The fiber optic duct will be Fulfilled if the fiber optic ducts installed as part of highway has been installed as part of construction. the civil works under the project. Pavement completion rate Percentage Value 0.00 0.00 100.00 Date 25-Feb-2014 14-Jul-2014 30-Jun-2019 Page 3 of 5 The World Bank Report No: ISR15764 Comments Construction activity has not yet commenced. Public Disclosure Copy Data on Financial Performance (as of 06-Jun-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P145361 IDA-H9430 Not Effective 02-Jun-2014 30-Jun-2019 30-Jun-2019 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P145361 IDA-H9430 Not Effective XDR 86.30 86.30 0.00 0.00 86.30 0.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation No key decisions taken at this point in time. Restructuring History There has been no restructuring to date. Related Projects Page 4 of 5 The World Bank Report No: ISR15764 There are no related projects. Public Disclosure Copy Public Disclosure Copy Page 5 of 5