Large Scale Irrigation Modernization Project Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: 5 may 2015]: Revision 2 of Updated Procurement Plan, March 28, 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Works Above US$ 15 million All 2. Goods Above US$ 4 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 2 million 2. Single Source All 3. Individual Above US$ 400,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule July 9, 2010 PROCUREMENT Morocco : MA-Large Scale Irrigation Modernization Project PLAN General Information Country: Morocco Bank’s Approval Date of the Original Procurement Plan: 2017-03-31 2019-02-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150930 GPN Date: Project Name: MA-Large Scale Irrigation Modernization Project Loan / Credit No: IBRD / 85140 Executing Agency(ies): Office Regionale de Mise en Valeur Agricole de TADLA (ORMVA TADLA WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-14/2016/TA-DA / Travaux du laboratoire pour Single Stage - One le contrôle de qualité pour IBRD / 85140 A posteriori Appel d'offres Open - National 215,224.65 Signé 2016-03-16 2016-03-28 2016-04-21 2016-04-21 2016-04-21 2016-04-21 Envelope secteur M et G et travaux bassin REF-28/2016/TA-DA / Travaux d'exécution des conduites du réseau de Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 10,333,713.35 Signé 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-06 2016-09-06 distribution y compris Envelope ouvrage annexes des secteurs M10-M18 ( L1 ) REF-29/2016/TA-DA / Travaux d'exécution de la Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 7,025,507.78 Signé 2016-06-28 2016-07-12 2016-09-06 2016-09-06 2016-09-06 2016-09-06 conduite d'adducteur A5 des Envelope secteurs M10-M18 ( L2 ) REF-10/2017/TA-DA / Travaux de réalisation des prises bornes,prises Single Stage - One propriétés et les conduite de IBRD / 85140 A posteriori Appel d'offres Open - National 4,909,254.84 Signé 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-02-28 2017-02-28 Envelope raccordement y compris la télégestion des secteurs M10- M13 (Lot 1) REF-15/2017/TA-DA / Travaux d'exécution des Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 7,211,688.62 Signé 2017-02-07 2017-02-17 2017-03-14 2017-03-14 2017-03-14 2017-03-14 conduites d'adducteur A6 des Envelope secteurs G13-G18 REF-11/2017/TA-DA / Travaux de réalisation des prises bornes,prises Single Stage - One propriétés et les conduite de IBRD / 85140 A posteriori Appel d'offres Open - National 4,047,710.58 Signé 2017-01-03 2017-01-17 2017-02-28 2017-02-28 2017-02-28 2017-02-28 Envelope raccordement y compris la télégestion des secteurs M14-M18 (Lot 2) REF-40/2015/TA-DA / Travaux d'exécution des conduites des adducteurs A5, Single Stage - One A6-1 et A6-2 de la partie IBRD / 85140 A posteriori Appel d'offres Open - National 8,345,909.83 Signé 2015-11-10 2015-11-23 2015-12-17 2015-12-17 2015-12-17 2015-12-17 Envelope amont sur 5.3 km y compris les ouvrages de prises principaux REF-30/2017/TA-DA / Fourniture et installation du matériel d'équipement de la Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 946,912.70 Signé 2017-03-24 2017-03-29 2017-05-10 2017-06-09 2017-07-14 2018-01-10 station de filtration du Envelope secteur M10/M18 y compris génie civil. Page 1 REF-32/2017/TA-DA / Travaux de construction d'un Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 5,894,336.29 Signé 2017-05-25 2017-05-30 2017-07-11 2017-08-10 2017-09-14 2018-03-13 bassin de régulation Envelope hydraulique ( 1ère Tranche ) REF-40/2017/TA-DA / Travaux de génie civil, de fourniture,transport et pose de conduites et Single Stage - One équipements nécessaires, IBRD / 85140 A posteriori Appel d'offres Open - National 5,121,569.31 Signé 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2018-11-10 Envelope pour la réalisation des réseaux de distribution d'eau d'irrigation des secteurs G15 Bis- G18 REF-41/2017/TA-DA / Travaux de génie civil, de fourniture,transport et pose de conduites et Single Stage - One équipements nécessaires, IBRD / 85140 A posteriori Appel d'offres Open - National 6,584,511.57 Signé 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2018-11-10 Envelope pour la réalisation des réseaux de distribution d'eau d'irrigation des secteurs G13- G15 REF-16/2018/TA-DA / Single Stage - One Fourniture et installation IBRD / 85140 A posteriori Appel d'offres Open - National 1,326,558.27 Signé 2018-11-06 2018-11-11 2018-12-23 2019-01-22 2019-02-26 2019-08-25 Envelope des stations de filtration REF-02/2019/TA-SMG / Equipement des locaux Single Stage - One En attente IBRD / 85140 A posteriori Demande de prix Limited 0.00 2019-03-20 2019-05-15 2019-11-11 administratifs dans la zone Envelope d'exécution de reconversion REF-03/2019/TA-DA / Travaux d'execution des Single Stage - One En attente prises bornes et prises IBRD / 85140 A posteriori Appel d'offres Open - National 0.00 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-18 Envelope d'exécution propriétés secteur G en 3 lots GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-37/2016/TA-DGRID / Fournitures de materiel pour le suivi des paramètres de Single Stage - One IBRD / 85140 A posteriori Appel d'offres Open - National 76,569.48 Signé 2017-01-22 2017-01-27 2017-03-10 2017-04-09 2017-05-14 2017-11-10 la nappe au niveau des Envelope secteurs M10/M18 et G13/G18 REF-58/2017/TA-SMG / Single Stage - One Aménagement et équipement IBRD / 85140 A posteriori Demande de prix Limited 69,778.78 Signé 2017-12-20 2018-02-14 2018-08-13 Envelope des locaux administratifs REF-59/2017/TA-SMG / Single Stage - One IBRD / 85140 A posteriori Demande de prix Limited 28,983.93 Signé 2017-12-11 2018-02-05 2018-08-04 Mobilier de bureau Envelope REF-08/2016/TA-SMG / Single Stage - One IBRD / 85140 A posteriori Demande de prix Limited 36,961.73 Signé 2016-04-11 2016-06-06 2016-12-03 Acquisition micro ordinateurs Envelope REF-17/2016/TA-SMG / Single Stage - One IBRD / 85140 A posteriori Demande de prix Limited 1,758.89 Signé 2016-05-21 2016-07-16 2017-01-12 Acquisition tablette tactile Envelope Page 2 REF-66/2017/TA-SMG / Aménagement et équipement Single Stage - One IBRD / 85140 A posteriori Demande de prix Limited 18,593.94 Signé 2018-01-12 2018-03-09 2018-09-05 des locaux administratifs Envelope dans la zone de reconversion REF-12/2017/TA-SMG / Single Stage - One Achat de matériel IBRD / 85140 A posteriori Demande de prix Limited 26,148.71 Signé 2017-05-15 2017-07-10 2018-01-06 Envelope informatique REF-01/2019/TA-SMG / Aménagement des locaux Single Stage - One En attente IBRD / 85140 A posteriori Demande de prix Limited 0.00 2019-04-06 2019-06-01 2019-11-28 administratifs dans la zone Envelope d'exécution de reconversion NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual REF-29/2017/TA-DGRID / Mise à niveau de la station Single Stage - One des éxpérimentations hydro IBRD / 85140 A posteriori Demande de prix Limited 0.00 Annulé 2017-02-19 2017-04-16 2017-10-13 Envelope agricoles de Oulad Gnaou ( Expertise + Etude) REF-21/2017/DGRID / Réalisation de la situation Single Stage - One de référence des paramètres IBRD / 85140 A posteriori Appel d'offres Open - National 35,966.57 Signé 2017-05-08 2017-05-11 2017-06-20 2017-06-30 2017-08-09 2018-02-05 Envelope environnenomentaux et mise en place d'un PGES REF-04/2019/TA-DGRID / Assistance technique et accompagnement pour Single Stage - One En attente IBRD / 85140 A posteriori Appel d'offres Open - National 0.00 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 2020-07-19 l'exploitation et la Envelope d'exécution maintenance des équipements hydro-agricoles CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-23 / Assistance Sélection fondée technique pour le suivi et Open - IBRD / 85140 A priori sur la qualité et 1,407,946.04 Signé 2015-04-23 2015-05-24 2015-07-07 2016-03-10 2016-04-07 2016-05-04 2016-08-08 2020-08-21 contrôle des travaux des International le coût secteurs M10-M18 MOF-REF-24 / Assistance Sélection fondée technique pour le suivi et Open - IBRD / 85140 A priori sur la qualité et 1,095,553.21 Signé 2016-07-26 2016-08-16 2016-09-29 2016-10-27 2016-11-26 2016-12-31 2017-02-04 2018-02-04 contrôle des travaux des International le coût secteurs G13-G18 REF-01/2017/DDA / Appuis Sélection fondée aux agriculteurs pour la Open - En cours IBRD / 85140 A priori sur la qualité et 0.00 2016-08-27 2016-09-17 2016-10-31 2016-11-28 2016-12-28 2017-02-01 2017-03-08 2018-03-08 valorisation de l'eau International d'examen le coût d'irrigation INDIVIDUAL CONSULTANTS Page 3