The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Land Administration System Modernization (P159692) MIDDLE EAST AND NORTH AFRICA | Lebanon | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 2 | ARCHIVED on 25-Jun-2019 | ISR37752 | Implementing Agencies: Ministry of Finance, General Directorate of Land Registration and Cadastre Key Dates Key Project Dates Bank Approval Date: 08-Jun-2018 Effectiveness Date: -- Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve access to land use and value data, property rights data, and geospatial information through the Land Registry and Cadastre system modernization. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Modernization of the Digital Land Registry and Cadastre System:(Cost $19.00 M) National Spatial Data Infrastructure:(Cost $2.50 M) Property Valuation and Taxation:(Cost $11.00 M) State Land Inventory and Management:(Cost $3.00 M) Institutional Development, Capacity Building and Project Management:(Cost $7.40 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating High High Implementation Status and Key Decisions Project's effectiveness has been delayed for a year. While the Loan Agreement was signed on May 31, 2019 the ratification by the Parliament is still pending. Full implementation is not expected to start by the fall. 6/25/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High Substantial Macroeconomic Moderate Moderate Substantial Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other -- -- -- Overall High High High Results PDO Indicators by Objectives / Outcomes Improve access to land use and value data, and geospatial information IN00719953 ►Number of Land Registry and Cadastre eService transactions completed annually (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10,000.00 10,000.00 10,000.00 500,000.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00719954 ►State Land Registration Datasheets quality improved in the digital Land Registry (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 30.00 30.00 70.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00719955 ►Number of Districts/Municipalities covered by the mass valuation system (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 6/25/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Intermediate Results Indicators by Components Modernization of the Digital Land Registry and Cadastre System IN00720011 ►Avg no. of days to complete recordn of purchase/sale of property in land adm systm (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 34.00 34.00 34.00 25.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720019 Avg no. of days to complete recordn of purchase/sale of property–Urban (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 34.00 34.00 34.00 25.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720022 Avg no. of days to complete recordn of purchase/sale of property–Rural (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 34.00 34.00 34.00 25.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720024 ►Number of external databases linked to the Land Registry and Cadastre system (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720026 ►Number of Districts where the Land Registry and Cadastre Archives have been converted to the Digital Archives (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720028 Land Registry and Cadastre Digital Archives established (Yes/No, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes IN00720029 ►Percentage of the Cadastral and Land Registry Maps digitized (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/25/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Value 50.00 50.00 50.00 70.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720030 ►Number of online requests processed annually by the Land Registry and Cadastre System (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 50,000.00 50,000.00 50,000.00 10,000,000.00 Date 30-Jun-2017 04-Dec-2018 17-Jun-2019 30-Jun-2022 IN00720031 ►Land Registry and Cadastre System provides gender disaggregated data (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-Dec-2018 04-Dec-2018 17-Jun-2019 31-Oct-2022 National Spatial Data Infrastructure IN00720012 ►Number of institutions providing data to NSDI (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720016 ►NSDI accessible online and through the Lebanese e-Government portal (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720020 ►Number of requests processed annually by the NSDI (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7,000,000.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 Property Valuation and Taxation IN00720013 ►Sales Price and Rental Price Registers created (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/25/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Value No No No Yes Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720017 ►Generic mass valuation models developed for five key property types (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720021 ►Property valuation results published and made accessible to the public (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 State Land Inventory and Management IN00720014 ►New Automated State Land Management System implemented (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 Institutional Development, Capacity Building and Project Management IN00720015 ►Institutional development and business plan developed for the General Directorate of Land Registration and Cadastre (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720018 ►User perception of quality of Land Registry and Cadastre services (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 66.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720023 User perception of quality of Land Registry and Cadastre services (female) (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 6/25/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720025 ►Number of people trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 IN00720027 Number of people trained (female) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600.00 Date 02-Oct-2017 04-Dec-2018 17-Jun-2019 03-Oct-2022 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P159692 IBRD-88800 USD 43.00 43.00 0.00 0.00 43.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P159692 IBRD-88800 08-Jun-2018 -- -- 31-Dec-2023 31-Dec-2023 Effective Cumulative Disbursements 6/25/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Land Administration System Modernization (P159692) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/25/2019 Page 7 of 7