The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Enhanced Road Access Project (P145545) EAST ASIA AND PACIFIC | Samoa | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 12 | ARCHIVED on 22-Mar-2019 | ISR36155 | Implementing Agencies: Samoa, Land Transport Authority Key Dates Key Project Dates Bank Approval Date: 17-Oct-2013 Effectiveness Date: 20-Feb-2014 Planned Mid Term Review Date: 08-Aug-2017 Actual Mid-Term Review Date: 08-Aug-2017 Original Closing Date: 30-Apr-2019 Revised Closing Date: 31-Oct-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To restore key road sector assets damaged by extreme weather events and enhance the climate resilience of critical roads and bridges in Samoa. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road and Bridge Reconstruction:(Cost $26.30 M) Technical Assistance:(Cost $2.00 M) Project Management:(Cost $1.40 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Project has completed the reconstruction of the Leone Bridge in 2017 and the Vaitele Street extension works in 2016. The Project has made good progress on key activities, especially on the civil works for Mali’oli’o Bridge that started on October 2018, the equipment and training assessment of the Land Transport Authority laboratory staff, and the detailed designs and drawings for upgrading Moamoa crossing. Over the next six months, the selection and design of works for selected crossings in Upolu will be a priority, function of the available project budget, as will completion of technical assistance on axle-load limit, for which axle load surveys are in progress with portable weigh pads purchased with project funds. 3/22/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Improved connectivity through rehabilitation or construction of roads to improved standards IN00679276 ►Improved connectivity through rehabilitation or construction of roads to improved standards (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2.30 -- 2.30 3.90 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 Vaitele Street completed. Comments: Improved connectivity through rehabilitation or replacement of water crossings to improved standards IN00679281 ►Improved connectivity through rehabilitation or replacement of water crossings to improved standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 -- 1.00 3.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 3/22/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Overall Comments PDO The baselines were recalculated based on the Project restructuring date, which was 31-May-2018. The baselines for the start date of the project (17-Oct-2013) are 0.00 for all indicators. Intermediate Results Indicators by Components Technical Assistance IN00679275 ►Instances when project designs are informed by access audits (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4.00 -- 4.00 5.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 IN00679291 ►Grievances registered related to delivery of project benefits that are addressed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 -- 100.00 100.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 IN00679292 ►Number of gender responsive design features (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 -- 5.00 5.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 Road and Bridge Reconstruction IN00679277 ►Roads constructed (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.60 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 IN00679259 ►Roads rehablitated (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 2.30 -- 2.30 2.30 3/22/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 IN00679287 ►Water crossings replaced or rehabilitated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 -- 1.00 3.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 IN00679288 ►Targeted locations where traffic flows will have reduced disruptions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 -- 3.00 4.00 Date 31-May-2018 -- 08-Feb-2019 31-Oct-2020 Overall Comments IR The baselines were recalculated based on the Project restructuring date, which was 31-May-2018. The baselines for the start date of the project (17-Oct-2013) are 0.00 for all indicators. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P145545 IDA-H8840 Effective USD 20.00 20.00 0.00 15.75 2.87 85% P145545 TF-17563 Effective USD 6.35 3.83 2.52 3.22 0.60 84% P145545 TF-A6371 Effective USD 5.88 5.88 0.00 0.00 5.88 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P145545 IDA-H8840 Effective 17-Oct-2013 01-Nov-2013 20-Feb-2014 30-Apr-2019 31-Oct-2020 P145545 TF-17563 Effective 08-Oct-2014 08-Oct-2014 08-Oct-2014 30-Apr-2019 30-Apr-2019 P145545 TF-A6371 Effective 31-May-2018 12-Jun-2018 31-Aug-2018 30-Apr-2019 31-Oct-2020 Cumulative Disbursements 3/22/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Enhanced Road Access Project (P145545) Restructuring History Level 2 Approved on 29-Feb-2016 ,Level 2 Approved on 25-Oct-2018 Related Project(s) P165943-Enhanced Road Access Project Additional Financing 3/22/2019 Page 5 of 5