The World Bank Report No: ISR11523 Implementation Status & Results China China: Nanchang Urban Rail Project (P132154) Public Disclosure Copy Operation Name: China: Nanchang Urban Rail Project (P132154) Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Archive Date: 15-Sep-2013 Country: China Approval FY: 2013 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Nanchang Urban Rail Group Co. Key Dates Board Approval Date 20-Jun-2013 Original Closing Date 31-Oct-2018 Planned Mid Term Review Date 03-Aug-2015 Last Archived ISR Date Effectiveness Date Revised Closing Date 31-Oct-2018 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project development objective (PDO) is to provide an effective urban mass rapid transit system of appropriate quality along the Line 2 corridor from ZhanQianNanDaDao Station to XinJiaAn Station. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Component 1: Construction of Line 2 1139.04 Component 2: Equipment for Line 2 624.99 Component 3: Design, Construction Management and Technical Assistance 185.48 Component 4: Safeguards and Other Construction Costs 370.65 Physical and Price Contingencies 100.87 Interest During Construction and Initial Working Capital 147.44 Public Disclosure Copy Front-end Fee 0.63 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Overall Implementation Progress (IP) Satisfactory Overall Risk Rating Substantial Implementation Status Overview Page 1 of 4 The World Bank Report No: ISR11523 The project was approved by the board on June 20, 2013. Implementation just started with the launch of civil works procurement. Locations Public Disclosure Copy Country First Administrative Division Location Planned Actual China Jiangxi Sheng Jiangxi Sheng ✔ Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Indicator Two - Quality: Percentage of users Text Value 0 >70 percent that rate the service “satisfactory� on average Date 31-Dec-2017 (also recorded for each gender for reference) Comments Effective urban mass rapid transit system Text Value 0 100% Date 31-Dec-2017 Comments Sub-indicator 1, 2 and 3 meet (33% weighing for each). Improvement above or under target value will be counted as percentage of target value. Sub-Indicator Two: Reduced travel time on Text Value 0 >25 minutes public transport modes along Line 2 corridor Sub Type Date 31-Jan-2013 31-Dec-2017 Breakdown Comments Sub-Indicator Three: Percentage of urban rail Text Value 0 >15% commuters along Line 2 with access to a car Sub Type Date 31-Jan-2013 31-Dec-2017 Breakdown Comments Sub-Indicator One: Line 2 ridership Text Value 0 200,000 Public Disclosure Copy Sub Type Date 31-Jan-2013 31-Dec-2017 Breakdown Comments Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Intermediate Result Indicator One: Percentage Percentage Value 100.00 of construction of stations (in value) Date 31-Dec-2017 Comments Page 2 of 4 The World Bank Report No: ISR11523 Intermediate Result Indicator Two: Percentage Percentage Value 100.00 of completion of tunnels (in value) Date 31-Dec-2017 Comments Public Disclosure Copy Intermediate Result Indicator Three: Level of Percentage Value 90.00 integration in terms of facilities for bus/rail/bike Date 31-Dec-2017 transfer designed and constructed in line with Comments integration plan Intermediate Result Indicator Four: Level of Text Value Routes Reorganized integration in terms of bus routes reorganized Date 31-Dec-2017 to reflect Line 2 opening Comments Intermediate Result Indicator Five: Level of Text Value Yes integration in terms of availability of a single Date 31-Dec-2017 payment card for rail and bus Comments Intermediate Result Indicator Six: Accessibility Percentage Value 100.00 – percentage of stations with barrier-free Date 31-Dec-2017 accessibility to the wheel-chair boundand sight Comments impaired Intermediate Result Indicator Seven: Number Text Value 0 3 of TAs completed (cumulative) Date 31-Dec-2017 Comments Data on Financial Performance (as of 01-Aug-2013) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P132154 IBRD-82620 Not Effective 20-Jun-2013 26-Jul-2013 31-Oct-2018 31-Oct-2018 Disbursements (in Millions) Public Disclosure Copy Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P132154 IBRD-82620 Not Effective USD 250.00 250.00 0.00 0.00 250.00 0.00 Disbursement Graph Page 3 of 4 The World Bank Report No: ISR11523 Public Disclosure Copy Key Decisions Regarding Implementation N/A Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 4 of 4