Gansu Revitalization and Innovation Project: Procurement Plan Annex: Procurement Plan Procurement Plan of Gansu Revitalization and Innovation Project April 24, 2019 Project information: Country: The People’s Republic of China Borrower: The People’s Republic of China Project Name: Gansu Revitalization and Innovation Project Loan/Credit No: Project ID: P158215 Project Implementation Agency (PIA): Gansu Financial Holding Group Co. Ltd (line of credit PPMO) will be responsible for microcredit management under Component 1. Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) will be responsible for Component 2 and 3. The culture and tourism PPMO will be centrally responsible for overseeing, coordinating, and training its cascaded PIUs at lower levels for subproject management. Both PPMOs will be responsible for liaison with the provincial PLG, municipal PLGs, and the World Bank on all aspects of project management, fiduciary, safeguards, and all other areas. The project will be implemented by eight project implementation units (PIUs) in the respective cities/districts/counties under the four prefecture municipalities. They are: Qin’an County Culture and Tourism Bureau, Maiji District Culture and Tourism Bureau, Wushan County Culture and Tourism Bureau, Lintao County Culture and Tourism Bureau, Tongwei County Culture and Tourism Bureau, Ganzhou District Culture and Tourism Bureau, Jiuquan City Culture and Tourism Bureau and Dunhuang City Culture and Tourism Bureau. Name of Components PIUs Gansu Financial Holding Group Co. Ltd (line of credit PPMO). GFHG is designated as the wholesaler FI to handle Component 1. Under the direct oversight and Component 1: Increased Access to Financial management of the line of credit PPMO (GFHG), Bank Services for MSEs of Gansu is designated as the 1st participating financial institution (PFI) to handle micro- and small credit transactions. 1. The Gansu Provincial Culture and Tourism Department (culture and tourism PPMO). The culture and tourism PPMO will be centrally responsible for Component 2: Urban-Rural Regeneration (investments by county): overseeing, coordinating, and training its cascaded PIUs at lower levels for subproject management. 2. Qin’an County PMO (Dadiwan-Longcheng Ancient Town-Shangguan Ming and Qing Dynasty Historic Street Scenic Area Construction Sub-project) 1 Gansu Revitalization and Innovation Project: Procurement Plan 3. Lintao County PMO (Majiayao Cultural Exhibition Center Construction Sub-project) 4. Ganzhou District PMO (Ganzhou District Cultural Heritage Protection and Downtown Tourism Development Subproject) 5. Dunhuang City PMO (Dunhuang City Xuanquanzhi Cultural Relic Protection Development Sub-project) 6. Jiuquan City PMO (Suzhou District Silk Road Cultural Research Center and Library Construction Sub- project) 7. Tongwei County PMO (Tongwei County Moxiang Painting and Calligraphy Town Hanmo Cultural Center Construction Sub-project) 8. Maiji District PMO (Maiji District Yellow River Carved Wooden Lacquerwares Intangible Cultural Heritage Center Construction Sub-project) 9. Wushan County PMO (Wushan County Yuanyang Jade Featured Cultural Town Construction Sub-project) Gansu Financial Holding Group Co. Ltd (line of credit PPMO) (capacity building to GFHG and selected PFIs, Component 3: Institutional Strengthening and as well as business start-up advisory services for MSEs) Global Knowledge Transfer Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) and 8 county/district/city PMOs Date of the Procurement Plan: April 24, 2019 Period covered by this Procurement Plan: 2019-2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 2 Gansu Revitalization and Innovation Project: Procurement Plan A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of thirty (30) days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. Winning Bidders shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. 3 Gansu Revitalization and Innovation Project: Procurement Plan k. The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. A. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. B. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: C. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable. G. Other Relevant Procurement Information: Goods, Works and Non-Consulting Services: Prior Review Threshold: Procurement Decisions are subject to Prior Review by the Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018). Procurement Contract Procurement Method Bank Prior Review Category Value (US$) Goods & Non- ≥ 10 million International Open Competitive All contracts Consulting Procurement (International + Services Open) ≥ 0.5 million National Open Competitive All contracts ≥ USD 2 million. to < 10 million Procurement (RFB) (National + Open) < 0.5 million Shopping (RFQ) None Others DS (Direct Selection) All contracts ≥ USD 2 million. Works, Supply ≥ 40 million International Open Competitive All contracts & Installation Procurement (International + Open) ≥0.5 million to National Open Competitive All contracts ≥ USD 10 million. Procurement (RFB) < 40 million 4 Gansu Revitalization and Innovation Project: Procurement Plan (National + Open) < 0.5 million Shopping (RFQ) None N/A DS (Direct Selection) All contracts ≥ USD 10million. Notes: DS: Direct Selection NA: Not Applicable 5 Gansu Revitalization and Innovation Project Procurement Plan Procurement Packages with Methods and Time Schedule: Gansu Revitalization and Innovation Project Procurement Plan (Civil works and Goods) WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s)                         PPMO RFB/Op Post  October SXMB- Supporting vehicles Supporting vehicles in scenic area Good  August 1 12.90 1.88 en/Natio Revie 12, 3 PPMO HW-01 in scenic area (Wuying, Longcheng) s 12, 2022 nal/ w 2022   Qin’an                     County Urban Qin’an Regeneration of Tianshui Dadiwan construction and  April County TSTJ- Civil RFB/Op Post   Wuying Town of renovation works; Shaodian Village Culture 2 DDW- 6.50 0.95 Work en/Natio Revie February 12, 10 Dadiwan Area: traditional houses protection and repair and 01 s nal w 12, 2020 2020 Residential Houses works Tourism Renovation Works Bureau Qin’an Urban  March  May County TSTJ- Regeneration of Tianshui Dadiwan infrastructure Civil RFB/Op Post Culture 3 DDW- Wuying Town of construction, renovation and upgrading 51.73 7.53 Work en/Natio Revie 12, 12, 15 and 02 Dadiwan Area: works ( Shaodian Village) s nal w 2021 2021 Tourism Municipal works Bureau Qin’an Urban County Regeneration of   TSTJ- Tianshui Dadiwan environment Civil RFB/Op Post Culture Wuying Town of April 10, 4 DDW- enhancement works; Yanjiagou River 3.00 0.44 Work en/Natio Revie February 5 and Dadiwan Area: 2020  03 course treatment works s nal w 8, 2020 Tourism Water conservancy BureauB works ureau 6 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Dadiwan Cultural Tianshui Dadiwan sub-project: Digital Qin’an Experience Zone, Exhibition Hall, Academic Research County TSTJ- Civil RFB/ Post  Feb Incubators Space Exchange Training Center, Interactive April 7, Culture 5 DDW- 31.27 4.55 Work Open/ Revie 12 and Tourist Service Display Experience Hall, Intangible 5, 2020 2020 and 04 s National w Center Housing Cultural Heritage Folk Customs Tourism construction works Exhibition Hall, Tourist Service Center Bureau Urban Dadiwan housing renovation works: Qin’an Regeneration of Protection and renovation of buildings County TSTJ- Longcheng Historic Civil RFB/ Post on both sides of the historic street of July 10, Aug12, Culture 6 DDW- Town of Dadiwan 19.21 2.80 Work Open/ Revie 15 Longcheng; protection and renovation 2020 2020 and 05 Area Housing s National w of historical courtyard and Nuwa Tourism conservation and Cultural Exhibition Hall Bureau renovation works Urban Qin’an Regeneration of August County TSTJ- Tianshui Dadiwan infrastructure Civil RFB/ Post Longcheng Historic July 6, Culture 7 DDW- construction, renovation and upgrading 53.40 7.77 Work Open/ Revie 10, 16 Town of Dadiwan 2020 and 06 works (Longcheng) s National w 2020  Area Municipal Tourism works Bureau Urban Regeneration of Shangguan Ming- Qin’an Tianshui Qin'an Shangguan Ming and and Qing- Dynasty County Qing Dynasties Ancient Street Building Civil RFB/ Post August TSTJ- Historic Street of Oct 6, Culture 8 Renovation and Improvement; 13.97 2.03 Work Open/ Revie 16 GJ-01 Dadiwan Area 3, 2020 2020  and Infrastructure Renovation and s National w Housing and Tourism Improvement. supporting Bureau infrastructure construction works 7 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Qin’an Dadiwan Cultural Tianshui Dadiwan: Scenic area County Experience Zone, exhibition equipment, lighting and RFB/ Post  March QA- Good April 6, Culture 9 Incubators Space sound equipment, intelligent systems, 5.77 0.84 Opn/ Revie 3 HW-01 s 6, 2021 2021  and and Tourist Service garbage compression and National w Tourism Center: Equipment transportation equipment Bureau                         Maiji District Tianshui Carved Wooden Lacquerwares Inheritance and Development Building Maiji Yellow River Renovation and Improvement: Carved District Lacquerware Civil RFB/ Post  Feb TSTJ- Wooden Lacquerware Intangible April 10, Culture 10 Creative Industry 50.43 7.34 Work Open/ Revie 12 QD-01 Cultural Heritage Inheritance Training 8, 2020 2020  and and Incubator s National w Center; Tourism Center Bureau Infrastructure upgrading and improvement: roads and ancillary facilities. Yellow River Maiji Lacquerware Tianshui Carved Wood Lacquerware    January District Creative Industry Inheritance and Development Sub- RFB/Op Post TS- Good Novembe Culture 11 and Incubator project: Multimedia Equipment, Audio 3.72 0.54 en/Natio Revie 10, 3 HW-01 s r 10, and Center: Equipment, LED Screen, Showcase, nal w 2021 2020 Tourism Multi-media Exhibition Board Bureau equipment   Wushan                     County 8 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Wushan Jade Art Tianshui Wushan Yuanyang Jade Creative Industry Featured Cultural Town Construction Wushan Exhibition and   sub-project: County Incubator Center; Civil RFB/ Post TSTJ- Yuanyang jade culture complex, road February April 11, Culture 12 and Urban 58.81 8.56 Work Open/ Revie 16 WS-01 reconstruction along the river, municipal 11, 2020  and Regeneration of s National w works etc. 2020 Tourism Shandan Town of Landscape improvement along Wushan Bureau Wushan Jade County to Shandan Town Industry Urban Wushan Tianshui Wushan Yuanyang Jade Regeneration of County Featured Cultural Town Construction Civil RFB/ Post TSTJ- Shandan Town of February April 9, Culture 13 sub-project: River course treatment: 1.54 0.22 Work Open/ Revie 5 WS-02 Wushan Jade 9. 2020 2020  and landscape improvement works on both s National w Industry Water: Tourism sides of the river conseration works Bureau Wushan Wushan Jade Art Tianshui Wushan Yuanyang Jade County Creative Industry RFB/ Post March WS- Featured Cultural Town Construction Good May 6, Culture 14 Exhibition and 1.00 0.15 Open/ Revie 3 HW-01 sub-project: Office equipment, audio s 6, 2021 2021  and Incubator Center National w equipment, LED screens, showcases. Tourism Equipment Bureau                       Lintao County Dingxi Majiaoyao Cultural Exhibition Rural regeneration Architectural renovation and Lintao of 8 villages of improvement County Civil RFB/ Prior December DXTJ- Majiayao Area: 1: Renovation of exterior walls of Oct 12, Culture 15 76.22 11.09 Work Open/ Revie 16 MJY-01 Housing renovation residential houses on both sides of the 2020 6, 2020  and s National w and infrastructure main road; repair of roadway in the Tourism construction works village, beautification of roadway Bureau landscape etc. 9 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Dingxi Majiaoyao Cultural Exhibition Architectural renovation and Lintao Majiayao Cultural   improvement County Exhibition, Civil RFB/Op Post DXTJ- 2. Majiayao Cultural Exhibition Center, February April 20, Culture 16 Research, and 36.91 5.37 Work en/Natio Revie 15 MJY-02 Majiayao Cultural Experience Center, 20, 2020  and Incubator Center: s nal w Majiayao Cultural Research and 2020 Tourism construction works Exchange Center, Majiayao Cultural Bureau Industry Incubation Center Lintao Rural regeneration Dingxi Majiaoyao Cultural Exhibition   County Civil RFB/Op Post DXTJ- of 8 villages of Architectural renovation and February April 22, Culture 17 12.07 1.76 Work en/Natio Revie 10 MJY-03 Majiayao Area: improvement 2: Outdoor engineering, 22, 2020  and s nal w Municipal works cultural square paving, etc. 2020 Tourism Bureau Lintao Majiayao Cultural Dingxi Majiaoyao Cultural Exhibition   County Exhibition, Architectural renovation and RFB/Op Post LT-HW- Good April 1, Culture 18 Research, and improvement: Cultural Exhibition 2.25 0.33 en/Natio Revie February 3 01 s 2021  and Incubator Center: equipment, office equipment, security nal w 1, 2021 Tourism Equipment equipment, information equipment etc. Bureau   Tongwei                     County Tongwei Tongwei Calligraphy and Ink Dingxi Moxiang Hot Springs Town  July County Painting Creative Construction works: Civil RFB/ Post Augest DXTJ- Culture 19 Industry Exhibition 1. Gallery / Cultural Products Store / 37.91 5.52 Work Open/ Revie 11, 12 WQ-01 1, 2020  and and Incubator Maker Center, calligraphy materials s National w 2020 Tourism Center: store Bureau construction 10 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) works(1) Tongwei Calligraphy and Ink Tongei Painting Creative Dingxi Moxiang Hot Springs Town County Civil RFB/ Post DXTJ- Industry Exhibition Construction works: Feb 15, April 15, Culture 20 32.27 4.70 Work Open/ Revie 8 WQ-02 and Incubator 2020 2020  and 2:Hanmo Cultural Art Center s National w Center: Tourism construction works Bureau (2) Tongwei Tongwei Calligraphy and Ink Dingxi Moxiang Hot Springs Town County Painting Creative Infrastructure Construction and Civil RFB/ Post DXTJ- Feb 13, April 13, Culture 21 Industry Exhibition Improvement: 15.77 2.29 Work Open/ Revie 8 WQ-03 2020 2020 and and Incubator Square pavement, calligraphy and s National w Tourism Center: Municipal painting street, landscape pool Bureau works Tongwei Tongwei Calligraphy and Ink County Cultural relics security monitoring RFB/ Post TW- Painting Creative Good Feb 11, April 11, Culture 22 system, intelligent scenic spot system, 1.35 0.20 Open/ Revie 3 HW-01 Industry Exhibition s 2020 2020  and display equipment etc. National w and Incubator Tourism Center: Equipment Bureau                       Zhangye City 11 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Zhangye Ming Dynasty Granary Zhangye Discovery Cultural Heritage Inheritance and Ganzho and Tourist Service Development Sub-project housing u District ZYTJ- Center; and Rural upgrading and improvement: Civil RFB/ Post March 1, May 10, Culture 23 MLC- regeneration of 1. repair of the north and west buildings 12.09 1.76 Work Open/ Revie 13 2020 2020  and 01 Folk Village in of the Ming Dynasty Granary; Tourist s National w Tourism Wulan Ancient Service Center (New); Square paving Bureau Town of Zhangye and essays, square lighting installation, roads and ancillary facilities. Zhangye General Military Cultural Ganzho Rural regeneration Heritage Protection Inheritance and u District of Folk Village in Development Project Building Civil RFB/ Post ZYTJ- March 9, May 11, Culture 24 Wulan Ancient Renovation and Improvement 4.41 0.64 Work Open/ Revie 13 ZBF-01 2020 2020  and Town of Zhangye: 2: Renovation of the old library, s National w Tourism Municipal works installation of lighting facilities; Bureau Municipal works. Rural regeneration Ganzho of Folk Village in Zhangjia Wulan Ancient Town Folk u District ZYTJ- Wulan Ancient Village Renovation and Upgrading: Civil RFB/ Post March May 13, Culture 25 WLGZ- Town of Zhangye: protection and repair of ancient houses, 40.53 5.90 Work Open/ Revie 16 12, 2020 2020  and 01 Housing repair and traditional dwellings and ancient s National w Tourism infrastructure buildings; Roads and ancillary facilities. Bureau construction Zhangye Ming Dynasty granary cultural heritage protection inheritance Ganzho development project intelligence and u District ZY- Zhangye Discovery RFB/ Prior office equipment Good Feb 20, April 15, Culture 26 HW— and Tourist Service 18.74 2.73 Open/ Revie 3 1&2. s 2021 2021  and 01 Center Equipment National w Wulan Ancient Town Project: Wireless Tourism Network, Portal, Online Booking Bureau System, Payment System Jiuqua                         n City 12 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Jiuquan Jiuquan Silk Road Cultural Heritage City JQTJ- Jiuquan Silk Road Civil RFB/Op Post March Research Center Construction: New May 14, Culture 27 SWYZ- Culture Research 66.02 9.61 Work en/Natio Revie 15 Research Center; Roads and ancillary 5, 2020 2020  and 01 Center and Library s nal w facilities. Tourism Bureau Jiuquan Jiuquan Silk Road City Jiuquan Silk Road Cultural Heritage RFB/ Post JQ- Culture Research Good Feb 21, April 20, Culture 28 Research Center intelligent system and 9.07 1.32 Open/ Revie 3 HW-01 Center and Library: s 2021 2021  and office equipment National w Equipment Tourism Bureau   Dunhuang                       City Dunhuang City Xuanquanzhi Cultural Site architectural renovation and upgrading: Exhibition Center and Visitor Center; Dunhua Dunhuang Tianshuijing Display Area, Yizhan Site March ng City Posthouse Display Area, Gobi Landform Display Civil RFB/ Prior DHTJ- May 20, Culture 29 Discovery and Area, Xuanquanzhi and Surrounding 78.65 11.45 Work Open/ Revie 14, 16 XQZ-01 2020  and Tourist Service Environment Display Area, viewing s National w 2020  Tourism Center platform, internal display road, self- Bureau driving camp and hiking campsite, sewage treatment facilities (sewage pipelines and septic tanks), garbage disposal facilities, electricity. Dunhua Dunhuang ng City DH- Posthouse RFB/ Prior Dunhuang City Xuanquanzhi Cultural Good Feb 13, April 11, Culture 30 HW— Discovery and 25.47 3.71 Open/ Revie 3 Site Intelligent facilities and basic s 2021 2021  and 01 Tourist Service National w equipment. Tourism Center Equipment Bureau 13 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate No. Contract No. Contract Description Method Estimate Duratio PIU gory Contract RMB USD Prior/ d Bid n Signing million million Post Opening (month Date Date s) Dunhua Dunhuang ng City DH- Posthouse Post Ox cart and horse cart exhibits in Good July 13, June 13, Culture 31 HW— Discovery and 0.40 0.06 DS Revie 1 Xuanquanzhi Relics Site in Dunhuang s 2021 2021 and 02 Tourist Service w City Tourism Center Exhibits Bureau Total (BF): 783.38 114.00               Legend:   First 18 months Packages Note: US$1 = CNY6.8718 6.8718 USD/RMB Exchange Rate 14 Gansu Revitalization and Innovation Project Procurement Plan Selection of Consultants: Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018): Prior Review Procurement Contract Bank Prior Review Threshold for Selection Method Category Value (US$) Threshold Contracts under Retroactive Financing ≥ 300,000 QCBS, QBS, Firms: All contracts Firms: All contracts >=USD 1 million; >=USD 500,000; QCBS, QBS, FBS, < 300,000 LCS, CQS Firms: All DS contracts Firms: All DS contracts >= USD 1 million; >= USD 500,000; Others DS Individual Consultant: Individual Consultant: All Consultants All contracts >=0.3 contracts >= USD million; 200,000; Others IC DS for individual DS for individual consultant: All consultant: All contracts>=USD 0.3 contracts>=USD million 200,000 Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection procedure FBS: Fixed Budget Selection NA: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Consultancy Assignments with Selection Methods and Time Schedule: 15 Gansu Revitalization and Innovation Project Procurement Plan Consultancy Assignments with Selection Methods and Time Schedule: Gansu Revitalization and Innovation Project Procurement Plan (Consulting Services) WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review QCBS/Open SXMB- Credit Risk Management and Post May 31, Oct 31, 1 3.09 0.45 /Internationa   60   PPMO C01 Corporate Governance Review 2019 2019 l Financial Technology in support of QCBS/Open SXMB- Post May 31, Oct 31, 2 MSEs Application and Credit 2.41 0.35 /Internationa   60   PPMO C02 Review 2019 2019 Assessment l TA to the GFGC on global good SXMB- CQS/Open/ Post Oct. 31, Dec. 15, 3 practice in executing and 1.37 0.20   24   PPMO C03 National Review 2019  2019  managing guarantees Improve Strategic Planning and  Oct. SXMB- CQS/Open/ Post Dec. 15, 4 Regulations of Culture and 1.51 0.22 31,   24   PPMO C04 National Review 2019  Tourism Sector 2019 SXMB- Direct Post Oct. 31, Sep 30, 5 Branding, Marketing & Promotion 1.99 0.29 84 PPMO C05 Selection Review 2019 2019 16 Gansu Revitalization and Innovation Project Procurement Plan WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review SXMB- Training of Cultural Tourism Direct Post Oct. 31, Sep 30, PPMO 6 1.99 0.29 84 C06 Practitioners. Selection Review 2019 2019 Community Outreach and Training SXMB- on Creative Industries and Direct Post Oct. 31, Sep 30, 7 1.99 0.29 84 PPMO C07 Safeguarding Intangible Cultural Selection Review 2019 2019 Heritage Business Start-up advisory SXMB- Services for Prospective Small Direct Post Oct. 31, Sep 30, 8 1.99 0.29 84 PPMO C08 and Micro Enterprise Operators, Selection Review 2019 2019 especially women. SXMB- Skills Training of Tianshui Lacquer Direct Post Oct. 31, Sep 30, 9 1.03 0.15 84 PPMO C09 Carving. Selection Review 2019 2019 Community Outreach and SXMB- Capacity Building Services for Direct Post Oct. 31, Sep 30, 10 1.03 0.15 84 PPMO C10 Low-Income Group on Business Selection Review 2019 2019 Start-up 17 Gansu Revitalization and Innovation Project Procurement Plan WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review Project Management Consulting QCBS/Open SXMB- Services, including socio- Prior May 15, Oct 1, 11 17.87 2.60 /Internationa   84   PPMO C11 economic impact evaluation and Review 2019 2019 l beneficiary satisfaction surveys. Establishment of Project QCBS/Open Post SXMB- Management Information System May 15, Oct 15, 12 2.82 0.41 /Internationa Review   24   PPMO C12 (Procurement of Standard 2019 2019 l Software). Post SXMB- Environmental Impact CQS/Open/ May 31, Oct 31, 13 1.99 0.29 Review   84   PPMO C13 Assessment & Monitoring. National 2019 2019 Post SXMB- Social Development Assessment CQS/Open/ May 31, Oct 31, 14 1.99 0.29 Review   84   PPMO C14 & Monitoring. National 2019 2019 Qin’an County Consulting Services for Design, QCBS/Open Prior SXMB- May 15, Oct 15, Culture 15 Construction Drawings, BQs of 7.42 1.08 /Internationa Review   12   C15 2019 2019 and Qin'an County, Tianshui. l Tourism Bureau 18 Gansu Revitalization and Innovation Project Procurement Plan WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review Maiji Cultural and Tourism Consulting Services for Design, QCBS/Open Bureau SXMB- Construction Drawings, BQs of Prior May 15, Oct 15, 16 4.26 0.62 /Internationa   12   Wushan C16 Maiji District and Wushan County, Review 2019 2019 l County Tianshui. Culture and Tourism Bureau Lintoa County Culture and Consulting Services for Design, QCBS/Open Tourism SXMB- Construction Drawings, BQs of Prior May 15, Oct 15, 17 8.45 1.23 /Internationa   12   Bureau C17 Lintao County and Tongwei Review 2019 2019 l County County, Dingxi City. Culture and Tourism Bureau Ganzhou District Consulting Services for Design, QCBS/Open SXMB- Post May 15, Oct 15, Culture 18 Construction Drawings, BQs of 3.30 0.48 /Internationa   12   C18 Review 2019 2019 and Zhangye. l Tourism Bureau Jiuquan City Culture and Consulting Services for Design, QCBS/Open SXMB- Prior May 15, Oct 15, Tourism 19 Construction Drawings, BQs of 7.28 1.06 /Internationa   12   C19 Review 2019 2019 Bureau Jiuquan and Dunhuang. l Dunhuan g City Culture and 19 Gansu Revitalization and Innovation Project Procurement Plan WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review Tourism Bureau Construction Supervision of QCBS/Open SXMB- Prior Jul 31, Nov 30, 20 Qin'an, Tianshui, Tongwei and 14.29 2.08 /Internationa   84   PPMO C20 Review 2019 2019 Shandan Works. l QCBS/Open Prior SXMB- Construction Supervision of Jul 31, Nov 30, 21 7.63 1.11 /Internationa Review   84   PPMO C21 Zhangye, Jiuquan and Dunhuang 2019 2019 l Prior Advisory Service with UNESCO to Strengthen Gansu Creative Industry; Intangible Heritage Direct SXMB- Prior May 31, Jun 30, 22 Support; Dunhuang Site 3.50 0.51 Selection of   60   PPMO C22 Review 2019 2019 Management Plan; and Support UNESCO Global Knowledge Sharing (on- the-job capacity strengthening) 20 Gansu Revitalization and Innovation Project Procurement Plan WB Cost Estimation Review Estimat Duratio Contract Contrac Selection Prior ed Bid Contract n Progre No. Contract Description Signing Owner t No. RMB USD method Review/ Openin Amount (month ss Date (million) (million) Post g Date s) Review Advisory Service with UNWTO to Review and Enhance Gansu Tourism Strategy; Enhance Direct SXMB- Marketing, Promotion and Post May 31, Jun 30, 23 2.75 0.40 Selection of   60   PPMO C23 Branding Strategy Efforts; and Review 2019 2019 UNWTO Support Global Knowledge Sharing (on-the-job capacity strengthening) SXMB- CQS/Open/ Post Oct. 31, Sep 30, 24 Learning Exchanges 5.22 0.76 42 PPMO C24 National Review 2019 2019 Establishment of Gansu Global Culture and Tourism Knowledge SXMB- CQS/Open/ Post Oct. 31, Sep 30, 25 Hub (curating knowledge content 2.75 0.40 84 PPMO C25 National Review 2019 2019 and development of communication strategies) Total (BF): 109.95 16.00                     Legend:   Retroactive Financed Packages   New added packages Note : US$1 = CNY6.8718 6.8718 USD/RMB Exchange Rate 21 PROCUREMENT China : Gansu Revitalization and Innovation Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2019-05-15 2019-10-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158215 GPN Date: 2019-05-06 Project Name: Gansu Revitalization and Innovation Project Loan / Credit No: / , IBRD / 89700 Executing Agency(ies): Gansu Silk PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SXMB-C11 / Project Management Consulting Component 1: Increased Services, including socio- Quality And Cost- Open - Under / Access to Financial Services Prior 2,600,000.00 0.00 2019-05-15 2019-06-20 2019-08-03 2019-08-31 2019-09-30 2019-11-04 2019-12-09 2020-12-08 economic impact evaluation Based Selection International Implementation for MSEs and beneficiary satisfaction surveys. SXMB-C02 / Financial Component 1: Increased Technology in support of Quality And Cost- Open - Pending / Access to Financial Services Post 350,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-01 2019-10-01 2019-11-05 2019-12-10 2020-12-09 MSEs Application and Credit Based Selection International Implementation for MSEs Assessment SXMB-C16 / Consulting Services for Design, Component 1: Increased Quality And Cost- Open - Pending Construction Drawings, BQs IBRD / 89700 Access to Financial Services Post 620,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Based Selection International Implementation of Maiji District and for MSEs Wushan County, Tianshui. SXMB-C17 / Consulting Services for Design, Component 1: Increased Construction Drawings, BQs Quality And Cost- Open - Pending IBRD / 89700 Access to Financial Services Prior 1,230,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 of Lintao County and Based Selection International Implementation for MSEs Tongwei County, Dingxi City. Page 1 SXMB-C18 / Consulting Component 1: Increased Services for Design, Quality And Cost- Open - Pending IBRD / 89700 Access to Financial Services Post 480,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Construction Drawings, BQs Based Selection International Implementation for MSEs of Zhangye SXMB-C19 / Consulting Component 1: Increased Services for Design, Quality And Cost- Open - Pending IBRD / 89700 Access to Financial Services Post 530,000.00 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Construction Drawings, BQs Based Selection International Implementation for MSEs of Jiuquan and Dunhuang. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2