E2682 v7   MENDERES GEOTHERMAL ELEKTRİK ÜRETİM A.Ş.    DORA�3 GEOTHERMAL POWER PLANT    ENVIRONMENTAL MANAGEMENT PLAN      January, 2012  TABLE OF CONTENTS 1. INTRODUCTION OF THE PROJECT 1.1 The Objective of the Proposed Sub-loan 1.2 The Sub-Project 2. ENVIRONMENTAL MANAGEMENT PLAN FOR THE GPP PROJECT 2.1 Mitigation Plan 2.2 Monitoring Plan 2.3 Implementation Plan 3. PROJECT SCHEDULE 4. PROCESS FLOW 5. PUBLIC CONSULTATION 6. APPENDIX 1 I.INTRODUCTION OF THE PROJECT 1.1 Objective of the Proposed Sub-loan 1.1.1 Name of Beneficiary Enterprise: MENDERES GEOTHERMAL ELEKTRİK ÜRETİM A.S. 1.1.2 Sub-loan Amount : 68.300.000.-USD (front-end fee included) Construction of a geothermal power plant (GPP) with an installed 1.1.3 Purpose of the Project : capacity of 34 MWe (2 x 17 MWe) with an energy production of 220 GWh annually in AYDIN - TURKEY. 1.2.The Sub-Project 1.2.1 Summary Investment Description*: Menderes Geothermal Elektrik Uretim A.S. (MEGE) was established as a part of MB Holding A.S. in 1999 and obtained an Electricity Production License for DORA-3 GPP (EÜ/2709-12/1680) from the Energy Market Regulatory Authority (EMRA) on August 19th, 2010, which is valid until 02.08.2031. In recent years the usage of geothermal resources has increased rapidly in Turkey. Geothermal energy is one of the alternative renewable energy sources in the world. The geothermal energy does not lead to pollution; it is renewable, sustainable, local and environmentally friendly. The installed geothermal power has reached from 17 MWe in 2005 to 114.2 MWe at the end of 2011 in Turkey. An additional 279.77 MWe capacity has been licensed by the EMRA. MEGE is based on a 33 km2 reserve basin in Aydin - Salavatli geothermal field and is the holder of a geothermal license for producing of geothermal energy in this licensed field (named as J- 550 Salavatlı Geothermal Field). According to the reservoir modelling studies, Aydın Salavatli geothermal field has a potential installed capacity of approximately 100 MWe. MEGE’s first project DORA-1 GPP, with an installed capacity of 7.95 MWe has been operating since 2006 and the second GPP, DORA-2 GPP, with an installed capacity of 9.5 MWe has been operating since 2010. After the construction of DORA-1 GPP, the reservoir pressures and the reservoir capacity were monitored during the operation period especially in first two years. An assessment for the new well locations for DORA-2 and DORA-3 GPPs were conducted by the experts from Istanbul Technical University, Izmir Dokuz Eylül University and also Izmir Institute of Technology. The reservoir characteristics were monitored from the wells drilled for DORA-2 GPP during the operation of DORA-1 GPP and currently the existing reservoir characteristics are also being 2 monitored from the new drilled wells during the operation of DORA-1 and DORA-2 GPP. Currently, AS-5 and ASR-3 wells are used as monitoring wells. It was also noted that during the operation of DORA-1 and DORA-2 GPPs, no interference was observed between the existing production and reinjection wells. The construction activities of the proposed GPP, DORA-3, with a licensed capacity of 34 MWe (2 x 17 MWe) has been started in January 2011 with the drilling of the production and reinjection wells at the proposed well locations. The drilling of the production and the reinjection wells are planned to be completed in June 2012. In addition, the construction activities at the power house is planned to be started in February 2012. The investment area of the project site is about 137.395 m2. The following areas are reserved in the project; • 21,000 m2 for power plant building, • 400 m2 for stock and warehouse of replacement and administrative building, and • 750 m2 for installation of pits, pump stations, box, construction site, etc. All regulatory approvals and permits related to the project area were obtained and secured before the start of the construction works. DORA-3 has an installed capacity of 34 MWe (2 x 17 MWe) with an annual energy production of 220,000,000 kWh. There will be two units and each unit of the DORA-3 power plant is planned with two binary turbines and a single generator. Installed Power Generation Capacity : 34,000 kWe Inlet Consumption : 5,000 kWe Net Power Generation Capacity : 29,000 kWe Average Annual Power Generation Time : 8,700 hours Total Net Annual Power Generation for Sales :220,000,000 kWh The net electricity generation of the plant varies with the meteorological conditions and also with the performance of the designed air cooled condenser. Since the ambient temperature decreases during winter period, the efficiency of the air cooling unit increases and the generation performance of the plant reaches to its maximum efficiency. In the scope of DORA-3 GPP project, ten (10) geothermal wells, six (6) for production and four (4) for reinjection are planned to be installed. The drilling activities have been started in January, 2011. The drilling of six (6) production wells and two (2) reinjection wells have been completed as of January 2012. Approximately 10,000 meters for production wells and 6,500 meters for the re-injection 3 wells are planned to be drilled in total. DORA-3 GPP will be operated with the AS-5, AS-6, AS-7, AS-8, AS-9, AS-10 production wells, which are between 1,300 m and 1,600 m in depth and the ASR-6, ASR-7, ASR-8 and ASR-9 re-injection wells, which are between 1,800 m and 2,200 m in depth. The location of DORA-1 GPP, DORA- 2 GPP, proposed DORA-3 GPP and the production/reinjection wells are shown in Figure-1. During the operation period the temperature of the geothermal fluid that will be extracted from the production wells will reach to about 160 0C with a flow rate of 2,800 tons per hour. Due to the temperature of the geothermal fluid, Binary System Technology (O.R.C. Organic Rankine Cycle) will be applied. Geothermal fluid contains a brine, steam and NCG (non- condensable gases) mixture. DORA-3 GPP will save about 150,000 tons of CO2 emission annually. The geothermal fluid, which reaches to the surface at 10 bars from the production wells, passes through a separator and is divided into hot water (brine) and steam. Geothermal fluid is then transferred to DORA-3 GPP. All pipelines are insulated to prevent the heat loss. Geothermal brine is accumulated into the accumulator tank and pumped into the system. Separated steam flows with its own pressure into the power station. The brine and steam are directed to the different heat-exchangers. Geothermal fluid transfers its heat to a secondary fluid, Pentane, in the heat-exchanger. The heated Pentane enables the turbines to turn at high speeds. Then, the generator, which is connected to the turbine with a shaft, generates the electrical energy. The geothermal and pentane systems run continuously as a closed circuit. Pentane, which turns into pressurized gas as it is heated, reaches to the air cooling system and returns into the liquid form and then is pumped back to the system. In this system, the geothermal fluid heats pentane in the evaporator and is released after completing its task. An air cooing system will be used in the scope of DORA-3 GPP. However, a limited amount of water for each production well (1-2 tons/day) will be used as cooling water at the production wells area. This amount will be supplied from the water network of Köşk, Salavatlı and Yavuzköy Districts. No water from Büyük Menderes River or groundwater will be used as cooling water in the scope of the project. The geothermal liquid, which transfers its heat to Pentane, drops to 75 0C and is sent to the re-injection wells by underground pipe lines and re-injected into the reservoir. The synchronization process produces electricity that is sent to the High Voltage interconnection network. 4 The electrical power that is produced by the generator will be transformed from 11 kilovolts to high voltage (i.e. 154 kV) with a step-up transformer and will be connected to the national network by a 154 kV high voltage overhead energy transmission lines. The switchyard and the support units will be controlled with a SCADA system. Since the existing facilities were connected to the 31.5 kV national networks with an underground system, there is no switchyard (substation) at the project site. In the scope of DORA-3 GPP, a switchyard will be constructed at the project site. This switchyard will be connected to the 154 kV Aydın – Nazilli energy transmission line (ETL) from the Yavuzköy Some pylon that is located at the 18th km of the Aydın-Nazilli ETL. The location of the switchyard will be determined according to the location of DORA-3 GPP and the location of the ETL route, including the number and the location of the pylons, will be decided by TEIAS (Turkish Electricity Transmission Company) accordingly. Furthermore, a possible location of the switchyard and the 2.2 km long transmission route is given in Figure-2. The transmission route is located on the agricultural lands and these lands are planned to be acquired from the owners by mutual agreement. DORA-3 GPP will be an Integrated Two Level Units (ITLU) modular power plant comprised of all the equipment and controls required to convert the hot geothermal brine into electric power. The major components of the ITLU consist of pre-heaters, vaporizers, turbines, generator, lubrication and sealing systems, air- cooled condenser, and motive fluid cycle pumps. The module also includes automatic and manual control valves, instrumentation (gauges, switches and transmitters), internal piping, and power and control boards. Operation process of the ITLU is based on the Rankine cycle, in which an organic fluid absorbs heat from a heat source. This makes the motive fluid (Pentane) to vaporize; then expands in the turbine, producing rotational shaft power by transforming kinetic energy gained by the vapor’s expansion process. In other words; the geothermal brine from the separators flows through the level 1 vaporizer tubes and then the brine plus steam from the separator enter the tube section of the level 1-2 pre-heater. The steam condensate is returned for reinjection while the brine flows to the level 2 vaporizer tubes. After the exit from the vaporizers the brine flows in parallel to the level 1 and level 2 tube sides of the pre-heaters and is then returned for reinjection, while organic fluid flows through the shell side. The organic motive fluid thermal cycle is a closed loop cycle. 5 The motive fluid cycle of the two levels is totally independent. The ITLU enables the extraction of heat from the geothermal fluid in a simple and high efficient way without the complication of using mixtures of working fluids or operating in super critical cycles. The feed pumps pump the organic fluid from the condensers into the pre-heater(s) shell section. The fluid is heated in the pre-heater(s) to a temperature close to the boiling temperature and in the vaporizer the organic fluid reaches the boiling point and vaporizes. The organic vapor pentane passes through the demister, then enters the organic turbine and expands, thus dropping in pressure and temperature and producing rotational shaft power. From the exhaust of the turbine, the low-pressure vapor flows to air-cooled condensers, condenses and is then pumped back into the pre-heater(s). The organic motive fluid used in the thermal cycle is Pentane, selected for optimal utilization of available heat source. The most important issue after the test results is the calcium (Ca) concentration of the geothermal source. From well up to the end of valve bottom (spool), Ca concentration of the well fluids is 3 mg/lt however only 1.5 mg/lt of Ca come to the floodgates. The reason for this decrease in concentration is because a large proportion of Ca precipitates as they combine with CO32- ions that are formed according to the following reaction 2HCO3----H2O + CO32- + CO2 that the fluid becomes more and more basic after the flashing (2 phases) in the wells. Scaling can be prevented with the help of an appropriate inhibitor a type of anti-scalant. The starting point of scaling in the wells can be determined during inhibitor tests as well as with Kaliper or Go-devil tests. Scale inhibitor will be supplied from General Electrics Company as SCALETROL PDC9332. This additive is a deposit control agent used in process water systems. It contains highly stable organic phosphate and phosphonate that control fouling caused by suspended solids and precipitation of scaling ions. This chemical product is not classified as dangerous to the environment or health. The Material Safety Data Sheet is presented in the Appendix. During the operation period, an organic dye will also be used as a tracer to analyze and track the impact of the reinjection water to the production well. It is added to the reinjection wells during the reinjection process and it is monitored by the sampling from the production wells in every 6 hours during the operation period. The dye is used in very limited amount and the total amount of dye used during the operation is about 100 kg/year. The production and the reinjection wells are at least 1,200 meters depth in the project area. At these depths no impact is expected on surface ground waters. To prevention of leakage and contamination of the surface water and the groundwater, the wells are sealed by 6 cement and cased by steel pipe named casing from the natural ground to the level of different depth for each well between 650 m and 1200 m below ground level. In case of a technical malfunction water that will be reinjected will be collected in a discharge pool and the accumulated water will be injected back into the reservoir after the plan operation is operational. The leakage is not discharged into the receiving environment on the surface. Detailed information about production and re-injection wells are given below; The Coordinates of the Production Wells in UTM coordinate system AS-5; Y=594599.36 - X=4191596.47 AS-6; Y=594624.84 - X=4191543.99 AS-7; Y=594618.10 - X=4191466.77 AS-8; Y=594643.59 - X=4191348.32 AS-9; Y=594685.57 - X=4191176.65 AS-10; Y=594262.74 - X=4191135.41 The Coordinates of the Reinjection Wells in UTM coordinate system ASR-6; Y=594324.96 - X=4190675.85 ASR-7; Y=594737.30 - X=4190727.58 ASR-8; Y=595002.69 - X=4190609.88 ASR-9; Y=594750.79 - X=4190565.64 A map, showing the location of the production wells, reinjection wells, the location of the existing DORA-1 and DORA-2 GPPs and the proposed DORA-3 GPP including the assumed Energy Transmission Line route, is given in Figure-2, attached to the end of this section of the report. 7 The project site is located at the J-550 coded Salavatlı Geothermal Area. The license field is located at the 26 km to Aydın Province, in Sultanhisar and Köşk Districts. The location of the existing DORA-1 1.2.2 Location: GPP, DORA-2 GPP and existing production and reinjection wells including the proposed DORA-3 GPP, production and reinjection wells are shown in Figure-1. The construction period of the plant was initiated with the start of the drilling activities in January 2011 and is planned to be completed in June 2012. The start of the DORA-3 GPP will be started in March 1.2.3 Timetable: 2012 and the commercial production of the first and the second units are planned to be started in May 2013 and November 2013, respectively. 1.2.4. Project (Location) Salavatlı Geothermal Field is located about 26 km from Aydin Province. The activity area is located within the administrative borders of Kosk District. The facility area is located at 300 meters to the Aydin-Denizli highway. Geothermal Power Plant site is located at about 1,500 meters and 600 meters away from the southeast of Yavuzköy Village and northeast of Köşk District, respectively. Drinking water is supplied from a natural spring located about 10 km distance from Yavuzköy village. Water table is detected at 80-100 meters depth in the project area. Due to the chemical characteristics of the existing groundwater, it cannot be used for drinking purposes but used only for irrigation purposes. Groundwater temperature is about 30 - 35 0C and has a flowrate of about 5-6 lt/s. There is no groundwater well that is used for drinking or irrigation purposes in the project area. The irrigation water is brought from Büyük Menderes River by two irrigation channels, which are constructed on the surface and made of concrete. In the scope of the project, there is no intersection or intervention of the project locations or piping with these channels. The operation area consists of agricultural fields and fruit orchards. The geothermal power plant will work with a closed-circuit system. Therefore, the proposed geothermal power plant will not have any adverse environmental impact on the existing agricultural lands and orchards during its operation. The Project location is not in or adjacent to areas with important archaeological, historical and or cultural sites or other high environment, social or economic values such as National Parks, Nature Parks, Natural Monuments, Nature Protection Areas, Wild Animals Development Areas, Cultural Heritage, Natural Heritage, Sites, Protected Areas, Biogenetic Reserve Areas, Tourism Areas or Centers and other Protected Areas. 8 Dilek Peninsula-Büyük Menderes Basin National Park is located between Kuşadası and Söke, where as towns of Aydın. The proposed Project area is located about 78,5 km away from the west of the park and therefore, the geothermal power plant will not have an adverse environmental impact on the park. The flora and fauna of the project region is prepared by expert biologists with the data acquired as a result of field studies and literature based studies. Flora and fauna related studies; Field works were carried out on the project area by expert biologists on March 5th-6th 2010. Amphibian, reptile, bird and mammal life were observed in the wildlife of the region. Their samples of nest, stools, foot print etc. were investigated. After then, identified plant samples in the field were diagnosed, observed for their tracks and wildlife members are classified. Floristic and faunistic scientific studies (literature studies) have been made within territory and nearby and all the data has been evaluated. FLORA The following publications were used for the detection of Flora: -P.H.DAVIS, “Flora of Turkey 1-10� -DONNER,J., “Verbreitungskarten Zu P.H.DAVIS “Flora of Turkey 1- 9� -TUBİTAK, “Turkish Plants Data Service� As a result of field and literature studies, no endemic or threatened flora species was identified at the project site and its vicinity in accordance with the Bern Convention (Convention on the Conservation of European Wildlife and Natural Habitats) and “Red Data Book of Turkish Plants� which presents IUCN’s Red List Categories. It was observed that there are mountain tea, stinging nettle, fig, poplar, olive, orange, bitter orange, bitter vetch, clover, liverwort in activity area and around. FAUNA The following publications were used for the detection of Fauna: -DEMİRSOY, “Mammals�, “Amphibians� and “Reptiles� -DEMİRSOY, “General and Turkey Zoogeography� -KURU, “Vertebrates� -TÜBİTAK, “Turkey Vertebrate Species List� -C.S.ROSELAAR, “Taxonomy, morphology, and distribution of the Songbirds of Turkey: an atlas of biodiversity of Turkish passerine birds� 9 -Environment Foundation of Turkey, “Turkey's wetlands� -Ministry of Environment,“ Bird paradises of Turkey� Society For The Protection Of Nature,“ Important Bird Areas in Turkey� As a result of field and literature studies, no endemic or threatened fauna species (amphibians, reptiles, birds and mammals) was identified at the project site and its vicinity in accordance with the Red Data Books, Bern Convention, IUCN Red List and Central Hunting Commission Decisions. There were non-endemic frog, snake, magpie, moles, foxes, and weasels at activity area and around. 1.2.5. Potential Impacts: Geothermal energy is one of the alternative and renewable energy More information on anticipated resources; which has the potential to compete with fossil energy environmental impacts of the project. resources. The proposed geothermal power plant will be operated with a Binary System (O.R.C. Organic Rankine Cycle) technology and will be completely closed-circuit system. Geothermal fluid obtained from the wells will be pumped back to reservoir with re-injection wells to avoid potential damage to the environment. Geothermal fluid will not contact with the atmosphere during this process. During the operation period 99% natural CO2 gas (raw gas) was formed. The CO2 gas collected in a closed-circuit system in DORA-1 and DORA-2 GPP was sold to two industrial gas suppliers in Turkey, HABAS and LINDE. The CO2 gas collected in DORA-3 GPP will either be sold to these gas suppliers or will be collected in the closed-circuit system and then will be directly re-injected to the underground with the re- injected geothermal water. All studies are complied with the provisions of the “Control of Industrial Air Pollution Regulations� published in Official Gazette, dated on July 03th, 2009 with Nr. 27277. Vegetative top soil will be stripped and stored separately on site. Then, it will be used during the rehabilitation of the project site after the construction is finished. The access roads will be sprayed with water by water trucks during the construction phase in the project area as a mitigation measure for potential dust emissions. Since the existing cadastral roads and village roads will be used, no new access road will be constructed in the scope of this project. The existing roads will be rehabilitated and widened where necessary. The lands that are required for the widening operations are all belong to the project owner. To prevent exhaust gas emissions, machines to be used will be provided as per new and quality state-of-the-art technology, and 10 vehicle inspections and exhaust measurement of the construction equipment will be regularly executed. The oil change of the construction machines will be performed on an impermeable location at the construction site by a mechanic or a service expert. The waste oil will be collected in barrels and these barrels will be stored on an impervious place in a secondary containment, The daily, weekly and monthly maintenances of the machinery will be conducted regularly and oil leaks will be prevented by using drip pans. All provisions of “Control of Hazardous Wastes Regulation" issued in Official Gazette no. 25755 and dated March 14th, 2005 as well as all provisions of "Control of Waste Oil Regulation" that entered into force by being published in the Official Gazette no. 26952 and dated July 30th, 2008. Release of any type of waste into any receiving environment such as soil, sea, surface or groundwater will be absolutely prevented. Solid wastes, which are classified as recyclable (plastic, glass, paper, metal etc.) formed due to personnel to be employed during construction and operation phases, will be stored separately by considering their recyclability according to the “Solid Waste Control Regulation� that entered into force by being published in the Official Gazette no.20814 dated on March 14th 1991. Wastewaters that will result from the personnel working at construction and operation phases will be gathered in an impermeable cesspit in compliance with the provisions of the “Regulation on the Pits to be Built in Locations, where it is not possible to Construct Sewage Course�, which entered into force upon promulgation in the Official Gazette dated on March 19th 1971 and numbered 13783. A protocol will be signed with Köşk Municipality for the disposal of wastewater in the cesspit with a vacuum truck, regularly.. All construction machines will not be operated at the same time. The daily, weekly and monthly maintenances of the machinery will be conducted regularly. The construction works will take place during daytime between 07:00 and 19:00 hours. Local people will be notified in advance if there is any noise creating activity during construction. During the construction stage, precautions will be taken according to "The Control and Management of Noise Regulations" published in Official Gazette, dated on June 4th, 2010 with Nr. 27601. In order to prevent accidents that may occur during the construction and operation, specific occupational health and safety measures will be taken within the framework of the ISO 18001 OHSAS by the EPC contractor and operator. Geothermal fluid used for power production will be disposed of through re-injection for the sake of continuity of the geothermal 11 system. The system is a closed cycle and the geothermal water will be transferring only its thermal energy. This geothermal water is not considered as waste water. For that reason geothermal fluid that is used in the power plant will be injected to the underground for feeding of the reservoir. The vehicles used in transporting construction materials will be covered. The work sites will be watered under warm, dry and windy weather conditions. In particular, water sprinkler systems will be used in crushing and seizing units in order to prevent dust. During the construction stage, precautions will be taken according to "The Control and Management of Noise Regulations" published in Official Gazette, dated on June 4th, 2010 with Nr. 27601. Under normal operational conditions, 100% of geothermal fluid will be injected into the reservoir. For the potential emergency situations, a “Discharge Pool� will be constructed in the facility area in order to maintain the production continuity in case of a technical malfunction that may occur in the system or in the reinjection wells that will prevent reinjection of the geothermal fluid. The volume of the discharge pool will be about 250 – 300 m3 for emergencies will be constructed to store geothermal fluid. Then geothermal fluid will be pumped via an extra pump into the reinjection wells. Since the 100% of the extracted water should be re-injected back to the reservoir, this mode of operation has been made a legal obligation in several countries, where geothermal power is utilized. Although no endemic or threatened fauna species were identified at the project site and its vicinity, still there will be some impacts on fauna species during the land preparation and construction stages. During the stripping of the vegetation cover and excavation activities at the project site, a risk may arise for animals such as tortoises, hedgehogs, lizards and snakes which use soil for nesting. Therefore, visual controls will be carried out before stripping and fauna elements will be removed from these areas to similar habitats by appropriate means of methods. Besides, some fauna elements may leave their habitats as a result of noise or construction vehicle disturbance. However, all these impacts will occur on a limited area and time period. Also it is most likely that animals leaving their habitats will find similar habitats around. Therefore no significant adverse impact is expected to occur on fauna elements during the construction activities. In addition, drilled wells do not pose a risk to the fauna elements during the operation since as the wells are drilled, they are cemented and there will be drilling rig at the well heads. Therefore there will be no risk for the animals to fall into these drilled wells. 1.2.6.Activities Conducted According to the 17 the article of the EIA Regulation, which came 12 into force published in the Official Gazette with the number of 26939 and with the date of July 17th 2008, a Project Description Report was prepared and submitted to the Aydın Provincial Directorate of Environment and Forestry, and an “EIA is not Required� decision was obtained on April 16, 2010. 1.2.7.Cumulative Impact of the GPPs DORA-1 GPP and DORA-2 GPP have been operated in J-550 Salavatlı Geothermal Field since 2006 and 2010, respectively. The proposed DORA-3 GPP is also planned to be constructed in the same geothermal field as shown in Figure-1. DORA-3 GPP is located about 860 m to Köşk Town and about 1,670 m to Yavuzköy Village. Since this proposed project will be the third GPP and there are two other geothermal power plant projects operating around the Project site, a limited cumulative impact assessment is performed by taking the other projects into consideration in order to predict whether there will be any additional impacts at the nearest settlements associated with the other projects. The cumulative impacts of DORA-3 GPP and other two projects are evaluated based on the distances between each project. Since DORA-3 GPP is located far away from DORA-2 GPP (about 1,480 m) and DORA-1 GPP (about 2,690 m); it can be stated that there will be no additional impact on the settlements around the each existing project. In addition, the closest residential area to the existing and the proposed plants is Yavuzköy Village, which is located about 1,120 m to DORA-1, about 890 m to DORA-2 and about 1,670 m to DORA-3. Therefore, a cumulative noise impact assessment is considered in order to estimate whether the cumulative noise levels at Yavuzköy Village comply both Turkish RAMEN limits and IFC/WB Guidelines. According to the noise measurements given in the “Noise Monitoring Report� prepared for DORA-2 GPP in March 2010; the noise levels measured at the fence of the plant (Leq) was recorded as 64.4 dBA, 61.9 dBA and 57.7 dBA during daytime, eveningtime and nighttime, respectively. Due to the distance between Yavuzköy and the existing and the proposed geothermal power plants; about 1,120 m to DORA-1, 890 m to DORA-2 and 1,670 m to DORA-3; the cumulative noise impact of these three plants at Yavuzköy Village is calculated as 12 dBA and the noise levels during construction and operation phase comply with both the Turkish noise regulation limits and IFC/WB Guidelines. 13 THE NOISE IMPACT ASSESSMENT OF DORA-3 GPP Construction Phase Construction inevitably creates some degree of noise emissions at locations in close vicinity of the construction activities. However, construction noise is temporary and transient in nature. The noise levels generated by construction works would have the potential to impact on noise sensitive receptors. Noise levels during construction at a receptor depends on several factors such as number and type of equipment and machinery used, the distance between noise sensitive receptor and the construction site and level of attenuation likely due to ground absorption, air absorption and barrier effects. AECOM assumes that typical number and type of construction equipments will be used during construction activities and their total equivalent noise level generated by all noise sources is estimated as 110 dBA (i.e. Backhoe loader, Dumper truck, Dozer and Digger). In order to assess the noise impacts of construction activities, the noise sensitive receptors (NSR) are selected as Köşk Town and Yavuzköy Village, which are located with a distance of 860 m and 1670 m, respectively. Air absorption is assumed as 0 in order to simulate worst case situation, and thus, the following formula (RAMEN, Annex-I) is used to calculate the noise levels of construction works at the noise sensitive receptor; ⎛ Q ⎞ L P = Leq + 10 × log⎜ ⎟ � 4.π .r ⎠ 2 where; Lp: Noise power level at the receptor (dBA); Q: ground absorption coefficient (assumed as 1); r: distance between the source and the receptor. The noise levels at different distances are calculated using the above formula and the results are given in Table-1, below. Table -1 Noise Levels at NSR and Different Distances Distance (m) Lp (dBA) 50 65 100 59 200 53 300 49.5 400 47 500 45 870 (NSR-1, Köşk Town) 40 1000 39 1500 35.5 1670 (NSR-2, Yavuzköy Village) 34.5 2000 33 As can be seen in Table-1, the noise level generated during the construction activities at the NSR is calculated as 34.5 dBA and the noise levels during construction phase comply with both the Turkish noise regulation limits and IFC/WB Guidelines. 14 THE CUMULATIVE NOISE IMPACT ASSESSMENT OF DORA-1, DORA-2 and DORA-3 GPPs Operation Phase According to the noise measurements given in the “Noise Monitoring Report� prepared for DORA-2 GPP in March 2010; the noise levels measured at the fence of the plant was recorded as 64.4 dBA, 61.9 dBA and 57.7 dBA during daytime, eveningtime and nighttime, respectively. Thus, in order to assess the cumulative noise impact at the NSR, Yavuzköy, AECOM assumes that the noise level at DORA-1, DORA-2 and DORA-3 GPP will be the recorded noise level during daytime at DORA-2 facility (64.4 dBA). Due to the distance of the GPPs to the NSR, (about 1,120 m to DORA-1, 890 m to DORA-2 and 1,670 m to DORA-3) the predicted noise levels for each GPP and also the cumulative noise impact of all GPPs at the NSR will be negligible. As a summary, this noise assessment study has demonstrated that the noise level during the construction and the operation phase of DORA-3 GPP will not exceed the Turkish noise regulation and IFC/WB daytime and nighttime noise limits. 15 Figure-1. Geothermal Projects in J-550 Salavatlı Geothermal Field 16 Figure-2 Project Locations (DORA-3 and assumed ETL Route) 17 2. ENVIRONMENTAL MANAGEMENT PLAN FOR DORA-3 GPP PROJECT 2.1 MITIGATION PLAN This section of the report determines the steps required for ensuring conformity with the Turkish Environmental Regulation during to planning, construction and operation stages of the proposed project. Phase Issue Mitigating Measure Responsibility* Project area was acquired by mutual agreement. Project Owner Aydın Provincial “EIA is not Required� decision was obtained in accordance with the EIA Directorate of Regulation. Environment Planning and Forestry (Land Preparation Admission Production license was obtained. EMRA and Pre- Construction) Construction Permission was taken. Aydın Governorship, Special Provincial Administration Drilling mud and cuttings from the well drilling will be separated and drilling mud will be reused as much as possible. Waste mud will be disposed according to its chemical content, whether it is hazardous or not, it will be disposed in accordance with Hazardous Wastes Control Regulation (Official Gazette No. 25755 dated March 14, 2005) or Solid Wastes Control Regulation (Official Gazette No. 20814 dated March 14, 1991). Cuttings will be washed and disposed in landfills approved Solid and liquid wastes generated by the local municipality in accordance with the Landfills Regulation (Official Construction from well drilling (drilling mud and Gazette No. 27533 dated March 26, 2010). Project Owner cuttings) All other solid and liquid wastes generated during construction will be collected in the impermeable containers and septic tanks transferred by the relevant Köşk Municipality periodically according to the “Water Pollution Control Regulation� (Official Gazette No. 25687 dated December 31st 2004), “Solid Wastes Control Regulation� (Official Gazette No. 20814 dated March 14th, 1991) and “Excavation, Construction and Debris Wastes Control Regulation� (Official Gazette No. 25406 18 Phase Issue Mitigating Measure Responsibility* th dated March 18 , 2004). The excavation work based drilling waste disposal will be disposed by the Köşk Municipality. To prevent the leakage and contamination of surface water and groundwater, wells will be sealed by cement and cased by steel pipe. In case of a technical malfunction, water will be collected in discharge pool and the accumulated water shall be injected into the system once again. The leakage will not be discharged Groundwater contamination during into the receiving environment. Project Owner drilling process The ground water will not be contaminated due to these mitigation measures and any contamination of groundwater is not allowed according to the Law on Groundwater published in Official Gazette dated December 23th, 1960 with Nr.10688. Construction The geothermal power plant will be operated with a Binary System (O.R.C. Organic Rankine Cycle) technology and completely closed-circuit system. Geothermal water and dissolved A totally-closed circuit system will be used in the planned geothermal power plant. gases intrusion to the surface during The CO2 gas (raw gas) produced within the close circuit system will be directly re- Project Owner drilling injected back to the ground or all of this raw gas shall be disposed, according to a contract to be executed, by allocation and delivery via a distribution pipeline in accordance with the demands of the relevant companies present at the region without any treatment. Traffic interruption during surface A traffic management plan will be prepared. The plan will be reviewed and pipeline (heat transmission / approved by the relevant Municipal authorities. Project Owner distribution) construction 19 Phase Issue Mitigating Measure Responsibility* There will not be any new access road construction within the scope of the project since there are existing roads already used to access the agricultural lands (fields, orchards, etc.). These existing roads will be used. These roads will be widened or rehabilitated where needed. If there is a need for road widening/rehabilitation on the existing roads, the loss of agricultural lands and cutting trees will be avoided. Also construction vehicles used for road widening/rehabilitation will not be allowed to pass through the surrounding agricultural lands so that the impact on the agricultural soil and the existing vegetation will be prevented. Exploratory drilling will be performed during non-growing period when agricultural activities are minimal (autumn, winter). Before starting the excavation work, the top soil will be stripped and used for the rehabilitation of the area. Damaging of soil, vegetation and road surfaces by movement of drilling Construction The main environmental impact during the construction of the switchyard and the equipment during exploration and ETL will be the habitat alteration due to land preparation and excavation activities Project Owner development, including the at the switchyard and the pylon locations. Since the ETL is relatively short (nearly construction of the switchyard and the 2.2 km) and located on agricultural lands where no endemic or threatened flora energy transmission line (ETL) species were determined in the project area, the potential environmental impact on the existing vegetation will be limited. In addition, there is no natural habitat of significant interest or natural migration pattern along the ETL route and at the proposed switchyard area. Therefore, no adverse impact is expected to occur on the natural habitat during the construction of switchyard and the ETL. Although no endemic or threatened fauna species were identified at the project site and its vicinity, there will be still some impacts on fauna species during the land preparation and construction stages. During the stripping of the vegetation cover and excavation activities at the project site, a risk may arise for animals such as tortoises, hedgehogs, lizards and snakes which use soil for nesting. Therefore, visual controls will be carried out before stripping and fauna elements will be removed from these areas to similar habitats by appropriate means of methods. Besides, some fauna elements may leave their habitats as a result of noise or 20 Phase Issue Mitigating Measure Responsibility* construction vehicle disturbance. However, all these impacts will occur on a limited area and time period. Also it is most likely that animals leaving their habitats will find similar habitats around. Therefore no adverse impact is expected to occur on fauna elements during the construction activities. Since the power plant will be constructed as close as possible to the drilling wells, the pipeline route will not cover large amount of area. Therefore natural habitat destruction will be limited for surface pipeline construction. Natural habitat destruction during Project Owner surface pipeline construction In addition, according to the flora and fauna studies, there is no natural habitat of significant interest or natural migration pattern within the pipeline route. Therefore there will be no adverse impact on natural habitat during surface pipeline construction. According to the results of the ecological survey, there are no natural habitats of Construction significant interest or natural migration pattern in the well locations. All measures regarding the drilling works that may cause environmental impacts will be taken. During the field works, flora and fauna studies, no endemic or threatened species were identified at the project site and its vicinity. Natural habitat destruction from extraction and or re-injection well Although no endemic or threatened fauna species were identified at the project site Project Owner siting and its vicinity, there will be still some impacts on fauna species during the land preparation and construction stages. During the stripping of the vegetation cover and excavation activities at the project site, a risk may arise for animals such as tortoises, hedgehogs, lizards and snakes which use soil for nesting. Therefore, visual controls will be carried out before stripping and fauna elements will be removed from these areas to similar habitats by appropriate means of methods. Besides, some fauna elements may leave their habitats as a result of noise or 21 Phase Issue Mitigating Measure Responsibility* construction vehicle disturbance. However, all these impacts will occur on a limited area and time period. Also it is most likely that animals leaving their habitats will find similar habitats around. Therefore no adverse impact is expected to occur on fauna elements during the construction activities. In addition, drilled wells do not pose a risk to the fauna elements during the construction since as the wells are drilled, they are cemented and there will be drilling rig at the well heads. Therefore there will be no risk for the animals to fall into these drilled wells. Solid and liquid wastes generated during the construction period will be collected in the impermeable containers and septic tanks are transferred by the relevant municipality periodically according to the “Water Pollution Control Regulation� Solid and liquid wastes accumulation (Official Gazette No. 25687 dated December 31st 2004), “Solid Wastes Control Project Owner from construction crews. Regulation� (Official Gazette No. 20814 dated March 14th, 1991) and “Excavation, Construction and Debris Wastes Control Regulation� (Official Gazette No. 25406 dated March 18th, 2004). Construction At the operation phase of the project, a “Discharge Pool� will be constructed in the facility area in order to maintain the production continuity in case of a technical malfunction that may occur in the system or in the re-injection wells. A discharge pool with 10m x 15m size for emergencies will be constructed and geothermal fluid stored here. Then geothermal fluid will be pumped to the re-injection wells. The water that needs to be re-injected in case of a malfunction in the re-injection Accidental discharge of geothermal system will be gathered in this pool and the accumulated water will be injected into waters to surface waters during Project Owner the system once again. This mode of operation has been made a legal obligation production testing in several countries where geothermal power is utilized. Also cooling water will be supplied from municipal water system of mainly Köşk District, Salavatlı Town and Yavuzköy Village. Therefore there will be no impact on surface waters due to cooling water supply. In addition, there will be no surface discharge of geothermal fluid. 22 Phase Issue Mitigating Measure Responsibility* All construction machines will not be operated at the same time. The daily, weekly and monthly maintenances of the machinery shall be conducted regularly. Local people will be notified in advance. During the construction stage, precautions Noise will be taken according to the Regulation on Assessment and Management of Project Owner Environmental Noise (Official Gazette No. 27601 dated June 4, 2010). Construction machines maintenance will be made on a regular basis. The construction work will take place between 07:00 and 19:00 hours. The vehicles used in transporting construction materials will be covered. Construction sites will be watered with sprinkler systems particularly during dry and windy weather conditions in order to prevent dust generation. Dust Project Owner To prevent adverse impacts of air pollutants generated by vehicles and machines, precautions will be taken according to Industrial Air Pollution Control Regulation Construction (Official Gazette No. 27277 dated July 3, 2009). To prevent the adverse impacts of exhaust gas emissions, machines will be Exhaust provided with new and quality state-of-the-art technology. Vehicle inspections and Project Owner exhaust measurement of the construction equipment will be regularly carried out. The oil change of vehicles will be performed on an impermeable surface at the construction site by an expert mechanic or service personnel, and waste oil will be collected in barrels during oil change process and thus contamination of soil due to mineral oil shall be prevented. The daily, weekly and monthly maintenances of the Waste Oils Generated by Equipment machinery will be conducted regularly and oil leaks shall be prevented. All Project Owner and Trucks provisions of “Hazardous Wastes Control Regulation" (Official Gazette No. 25755 and dated March 14th, 2005) as well as all provisions of "Waste Oil Control Regulation" (Official Gazette No. 26952 and dated July 30th, 2008) will be followed during maintenance and oil changes of construction machinery and transportation vehicles. Release of solid wasted into any receiving environment such as soil, sea, 23 Phase Issue Mitigating Measure Responsibility* surface or ground water will be absolutely prevented. There are no cultural and archeological resources at the project site and its vicinity. If any cultural and archeological resources are found in and nearby of the surrounding area, the construction will be immediately stopped and Province Cultural properties Administration of Culture and Tourism will be informed. Cultural and archeological Project Owner resources that might be found during construction will be protected. All works related with construction will continue after approval is obtained from the Province Administration of Culture and Tourism. Pressure valves will be used for leak detection. Project Owner At the operation phase of the project, a “Discharge Pool� will be constructed in the facility area in order to maintain the production continuity in case of a technical malfunction that may occur in the system or in the re-injection wells. The discharge pool will cover an area of 150 meter squares with 10 m x 15 m dimensions. Accidental leaks of production waters The water that needs to be re-injected in case of a malfunction in the re-injection Project Owner system will be gathered in this pool and the accumulated water will be injected into Operation the system once again. This mode of operation has been made a legal obligation in several countries where geothermal power is utilized. In case of a failure at the operation phase of the re-injection, generation will be halted in the power generation plant and thermal waters will be transferred to the Discharge Pool until the repair is completed. If the repair is not possible, then generation will be stopped in order to prevent the pollution of ground waters. The nearest residential units to DORA-3 GPP are Köşk Town and Yavuzköy Villages with a distance of 860 m and 1670 m, respectively. During the operation Noise phase, the predicted noise levels at these NSRs will be negligible due to the Project Owner distance and the estimated noise levels at DORA-3 GPP with respect to the noise level measurements carried out for DORA-2 plant. The detailed calculation of the noise impact is given in the report section. 24 Phase Issue Mitigating Measure Responsibility* Geothermal fluid obtained from the wells will be sent with re-injection wells. Thus a circulation is created. Geothermal fluid will not contact with the atmosphere during this process. As a result of this circulation H2S does not interfere into the Release of dissolved hydrogen sulfide atmosphere. Project Owner gas All studies are complied with the provisions of the Industrial Air Pollution Control Regulation (Official Gazette No. 27277 dated July 3, 2009). The geothermal power plant will be operated with a Binary System (O.R.C. Organic Rankine Cycle) technology and completely closed-circuit system. Water pollution from cooled Project Owner geothermal fluid effluents Cooled geothermal fluid will be re-injected through this system to underground. Thus, the circulation will continue. Worker health and safety-exposure to H2S detection systems will be installed at locations where release is possible. hydrogen sulfide (H2S) An approved emergency plan will be prepared and distributed to the relevant authorities. Operation Enclosed facilities will be designed for adequate ventilation. Project Owner Workers will be trained about the dangers of hydrogen sulphide once a month by Occupational Health and Safety experts. To prevent accidents that may occur during the operation, specific occupational health and safety measures will be taken within the framework of the ISO 18001 OHSAS. In conclusion, through the specification of the measures required to minimize the potential negative effects of the proposed project are mentioned above, it is estimated that the activities to be carried out within the framework of the proposed project will not expected to have any significant negative impact on the environment. 25 2.2. MONITORING PLAN This section of the report includes the “Monitoring Plan� that establishes the monitoring stages required to ensure conformity with the principles and procedures laid down in the national environmental legislation during the planning/project design, construction and operation activities of the project. Sequence of Institutional Stage Monitoring Parameter Place of Parameter Method of Monitoring Reason of Monitoring Monitoring Responsibility Condition of Drilling areas and Pre- Acquisition Property Project Owner property Project area Construction Production license and Project owner, License Pre- approval of licensing Energy Market Project area Written permission acquisition Construction procedures obtaining Regulatory from EMRA Authority (EMRA) Land Preparation Admission and Pre- Project owner, EIA Not Necessary Construction Aydın Provincial EIA Operation areas and its Pre- Decision was taken Written permission Directorate of Permission surroundings Construction within the scope of the Environment and EIA Regulations in force Forestry Project owner, Getting required Aydın Construction Pre- Project area Written permission permissions from related Governorship permission Construction authority before activities Special Provincial Administration 26 Sequence of Institutional Stage Monitoring Parameter Place of Monitoring Method of Monitoring Reason of Monitoring Monitoring Responsibility Solid and liquid wastes Protection of soil and generated from well drilling Well drilling sites Visual inspection Daily Project Owner surface waters (drilling mud and cuttings) To prevent groundwater Steel casings and cement contamination during used in the drill holes Well drilling sites Visual inspection Daily during drilling Project Owner drilling process To prevent geothermal Geothermal water and water and dissolved Construction dissolved gases during Well drilling sites Visual inspection Daily Project Owner gases intrusion to the drilling surface during drilling Traffic during surface Roads near construction, Visual inspection through To prevent traffic Daily Project Owner pipeline construction and drilling activities a traffic management plan interruption Soil and vegetation At construction site and To prevent soil and condition during movement Visual inspection Weekly Project Owner along access routes vegetation damage of drilling equipment 27 Sequence of Institutional Stage Monitoring Parameter Place of Monitoring Method of Monitoring Reason of Monitoring Monitoring Responsibility - Along proposed pipeline Condition of natural habitat route and access roads Prior and during any To prevent natural Field ecologist and during surface pipeline - At and near site Visual inspection pipeline construction habitat destruction Project Owner construction and well siting extraction and re-injection and well drilling wells Condition of natural habitat during construction of - Switchyard area To prevent natural Visual inspection Weekly Project Owner switchyard and energy - ETL route habitat destruction transmission line (ETL) Construction site To prevent soil Solid wastes from Project owner Construction temporary disposal site, Visual inspection Daily pollution, health construction crews Kosk Municipality waste containers concerns To prevent soil and surface waters Project owner Excavation wastes Construction site Visual inspection Weekly pollution, adverse Kosk Municipality impact on natural habitat To prevent soil and Project owner Domestic wastewater Septic tanks Visual inspection Monthly groundwater pollution Kosk Municipality 28 Sequence of Institutional Stage Monitoring Parameter Place of Monitoring Method of Monitoring Reason of Monitoring Monitoring Responsibility Construction equipment, To prevent soil and Waste oils Visual inspection Monthly Project Owner trucks groundwater pollution To prevent accidental Surface water quality At the location of discharge of (proper functioning of Visual inspection Weekly Project Owner Discharge Pool geothermal waters to Discharge Pool) surface water Construction and drilling Audio, consultation with For community health Noise Upon complaints Project Owner sites, vehicle routes local residents concerns Construction Daily, more frequently during Roads, settlements near Visual inspection dusty and windy the project area conditions and upon complaint For local air quality and Air quality (dust, exhaust community health Project Owner gases) concerns Exhaust measuring Construction equipment instruments Periodical exhausts 29 Sequence of Institutional Stage Monitoring Parameter Place of Monitoring Method of Monitoring Reason of Monitoring Monitoring Responsibility To prevent any damage Construction and drilling During excavation Cultural assets Visual inspection to historical and cultural Project Owner sites works assets Occupational Health and For health and safety of Whole project area Visual inspection and audit Daily Project Owner Safety construction personnel Construction Project Owner, General Directorate After the completion of Electrical Power Admission Procedures Project Area with written permission of the construction Admission processes Resources Survey work & Development Administration 30 Monitoring Sequence of Institutional Stage Place of Monitoring Method of Monitoring Reason of Monitoring Parameter Monitoring Responsibility Proper At the location of Discharge To prevent accidental leaks of functioning of Visual inspection Weekly Project Owner Pool production waters Discharge Pool Monthly or Production and reinjection upon For occupational and Noise with sound level meters Project Owner pumps, air compressors complaints by community health concerns local residents Operation Work area, particularly To prevent exposure of H2S for H2S level H2S detection systems Weekly Project Owner where H2S can accumulate workers Occupational For occupational health and Visual inspection and internal Health and Whole project area Daily safety concerns Project Owner audit Safety Drilling area and power plant Sustainability of geothermal Geothermal fluid Visual inspection Continuous Project Owner area fluid supply. Construction equipment, To prevent soil and Waste oils Visual inspection Periodical Project Owner Operation trucks groundwater pollution Solid wastes and To prevent soil pollution, health packaging Project area Visual inspection Daily Project Owner concerns wastes Domestic To prevent soil and Operation Project area Visual inspection Daily Project Owner wastewater groundwater pollution 31 2.3. Implementation Plan Implementation Plan is given below. Related responsible agency could be shown on the part 2.1 and part 2.2. During Construction After Subject Before Construction Years Construction 2010 2011 Excavation wastes Dust / air pollution Noise Exhaust Solid wastes Hazardous waste Waste oil Domestic wastewater Medical waste (N/A) Public Safety Wild Life Employment Socio-Economy Land management activities Restoration of Construction Area 32 During Construction After Subject Before Construction Years Construction 2012 2013 Excavation wastes Dust / air pollution Noise Exhaust Solid wastes Hazardous waste Waste oil Domestic wastewater Medical waste (N/A) Public Safety Wild Life Employment Socio-Economy Land management activities Restoration of Construction Area 33 During Construction After Subject Before Construction Years Construction 2014 Excavation wastes Dust / air pollution Noise Exhaust Solid wastes Hazardous waste Waste oil Domestic wastewater Medical waste (N/A) Public Safety Wild Life Employment Socio-Economy Land management activities Restoration of Construction Area 34 PROJECT SCHEDULE 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2010 - AUGUST 2010 - SEPTEMBER 2010 - OCTOBER ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 1 2 3 4 5 6 7 8 9 10 11 12 13 Planning A- PRE-CONSTRUCTION PERIOD - 16 MONTH 19.08.2010 19.12.2011 100,00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 0.492% 0.492% 0.492% 0.492% 1 01.10.2010 01.12.2011 30,00% and LOCATION LANDS of DRILLING Realized 0.492% 0.492% 0.492% 0.492% Planning 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% 0.538% Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE-CONSTRUCTION Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,538% 0,538% 0,538% 0,538% 1,030% 1,030% 1,030% 1,030% 19.08.2010 19.12.2011 100,00% (ACCORDING TO WEEKS) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,538% 0,538% 0,538% 0,538% 1,030% 1,030% 1,030% 1,030% TOTAL - COMPLETING PROJECT of PRE-CONSTRUCTION Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,538% 1,077% 1,615% 2,154% 3,184% 4,214% 5,245% 6,275% 19.08.2010 19.12.2011 100,00% (GENERAL) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,538% 1,077% 1,615% 2,154% 3,184% 4,214% 5,245% 6,275% Planning B- CONSTRUCTION PERIOD- 32 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANT Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 1/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2010 - NOVEMBER 2010 - DECEMBER 2011 – JANUARY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 14 15 16 17 18 19 20 21 22 23 24 25 26 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% 0,492% STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% 0,538% Planning 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% 0,364% Planning 0,441% 0,441% 0,441% 0,441% 0,441% 0,441% 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized 0,441% 0,441% 0,441% 0,441% 0,441% 0,441% TOTAL - COMPLETING PROJECT of PRE- Planning 1,030% 1,030% 1,030% 1,030% 1,030% 1,394% 1,394% 1,835% 1,835% 1,835% 1,835% 1,835% 1,835% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized 1,030% 1,030% 1,030% 1,030% 1,030% 1,394% 1,394% 1,835% 1,835% 1,835% 1,835% 1,835% 1,835% TOTAL - COMPLETING PROJECT of PRE- Planning 7,305% 8,335% 9,366% 10,396% 11,426% 12,820% 14,214% 16,049% 17,884% 19,719% 21,554% 23,389% 25,224% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized 7,305% 8,335% 9,366% 10,396% 11,426% 12,820% 14,214% 16,049% 17,884% 19,719% 21,554% 23,389% 25,224% Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 2/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2011 - FEBRUARY 2011 – MARCH 2011 – APRIL ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 27 28 29 30 31 32 33 34 35 36 37 38 39 Planning A- PRE-CONSTRUCTION PERIOD – 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT – ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL – COMPLETING PROJECT of PRE- Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 25,224 Planning 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% TOTAL – COMPLETING PROJECT of PRE- % 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) 25,224 Realized 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% % Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized Planning 9 STUDIES of PERFORMANCE TESTS and TAKING INTO 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL – COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL – COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 3/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2011 - MAY 2011 - JUNE 2011 - JULY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 40 41 42 43 44 45 46 47 48 49 50 51 52 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 25,224 25,224 Planning 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% TOTAL - COMPLETING PROJECT of PRE- % % 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) 25,224 25,224 Realized 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% % % Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized Planning 2 TEST STUDIES AND REPORTS of PRODUCTION and RE- 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 4/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2011 - AUGUST 2011 - SEPTEMBER 2011 - OCTOBER ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 1 2 3 4 5 6 7 8 9 10 11 12 13 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized Planning 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% TOTAL - COMPLETING PROJECT of PRE- Planning 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 5/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2011 - NOVEMBER 2011 - DECEMBER 2012 - JANUARY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 0,000% 25,224 Planning 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% TOTAL - COMPLETING PROJECT of PRE- % 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) 25,224 Realized 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% 25,224% % Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 6/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2012 – FEBRUARY 2012 – MARCH 2012 – APRIL ORDER NO: WORKING GROUPS Starting Date Ending Date % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Percentage State 28 29 30 31 32 33 34 35 36 37 38 39 40 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized Planning 2 TEST STUDIES AND REPORTS of PRODUCTION and RE- 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized Planning 9 STUDIES of PERFORMANCE TESTS and TAKING INTO 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 7/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2012 – MAY 2012 – JUNE 2012 – JULY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 41 42 43 44 45 46 47 48 49 50 51 52 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized Planning 2 TEST STUDIES AND REPORTS of PRODUCTION and RE- 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANT Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 8/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2012 – AUGUST 2012 - SEPTEMBER 2012 – OCTOBER ORDER NO: WORKING GROUPS Starting % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Ending Date Date Percentage State 1 2 3 4 5 6 7 8 9 10 11 12 13 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 9/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2012 - NOVEMBER 2012 - DECEMBER 2013 – JANUARY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 14 15 16 17 18 19 20 21 22 23 24 25 26 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized Planning 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 10/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2013 – FEBRUARY 2013 – MARCH 2013 – APRIL ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 27 28 29 30 31 32 33 34 35 36 37 38 39 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized Planning 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 11/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2013 – MAY 2013 – JUNE 2013 – JULY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 40 41 42 43 44 45 46 47 48 49 50 51 52 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized Planning 2 TEST STUDIES AND REPORTS of PRODUCTION and RE- 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION Planning 7 01.06.2012 01.06.2013 15,00% FABRICATON BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 12/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2013 – AUGUST 2013 – SEPTEMBER 2013 – OCTOBER ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 1 2 3 4 5 6 7 8 9 10 11 12 13 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 01.10.2010 01.12.2011 30,00% CONNECTION and LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized Planning 7 MECHANICAL-ELECTRICAL and AUTOMATION 01.06.2012 01.06.2013 15,00% FABRICATON BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 13/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2013 – NOVEMBER 2013 – DECEMBER 2014 – JANUARY ORDER WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Week Week NO: Starting Date Ending Date Percentage State 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION Planning 7 01.06.2012 01.06.2013 15,00% FABRICATON BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 14/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2014 – FEBRUARY 2014 – MARCH 2014 - APRIL ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 29 30 31 32 33 34 35 36 37 38 39 40 41 42 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized Planning 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized Planning 2 TEST STUDIES AND REPORTS of PRODUCTION and RE- 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON Planning 7 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 15/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2014 - MAY 2014 – JUNE 2014 – JULY ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 43 44 45 46 47 48 49 50 51 52 1 2 3 4 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY CONNECTION Planning 1 and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized Planning 2 STUDIES of GEOPHYSICS-CSMAT- LOCATION DETERMINATION 01.09.2010 01.12.2011 35,00% Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized Planning 5 TRANSPORTATION and INSTALLATION of PLANT FABRICATION 01.06.2012 15.08.2013 15,00% Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized Planning 7 MECHANICAL-ELECTRICAL and AUTOMATION FABRICATON 01.06.2012 01.06.2013 15,00% BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized Planning 8 FABRICATION of CONNECTION POINT of PLANT and SYSTEM 15.06.2011 15.06.2012 15,00% Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 16/17 1- LICENCE DATE : 19 AUGUST 2010 2- LICENCE PERIOD : 20 YEAR AYDIN - SALAVATLI 3- END OF WORK DATE : 19 AUGUST 2014 DORA -3 GEOTHERMAL POWER PLANT PROJECT 4- PRODUCTION DATE : 02 AUGUST 2014 PROJECT SCHEDULE Date Date Date Work 2014 – AUGUST 2014 - SEPTEMBER ORDER NO: WORKING GROUPS % Activity Week Week Week Week Week Week Week Week Starting Date Ending Date Percentage State 5 6 7 8 9 10 11 12 Planning A- PRE-CONSTRUCTION PERIOD - 12 MONTH 19.08.2010 19.12.2011 100.00% Realized ALTERNATIVE STUDIES of PLANT - ELECTRICITY Planning 1 CONNECTION and 01.10.2010 01.12.2011 30,00% LOCATION LANDS of DRILLING Realized STUDIES of GEOPHYSICS-CSMAT- LOCATION Planning 2 01.09.2010 01.12.2011 35,00% DETERMINATION Realized Planning 3 MAP SURVEY STUDIES 01.12.2010 19.12.2011 20,00% Realized Planning 4 EXPROPRIATION STUDIES 15.12.2010 15.08.2011 15,00% Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (ACCORDING TO WEEKS) Realized TOTAL - COMPLETING PROJECT of PRE- Planning 19.08.2010 19.12.2011 100,00% CONSTRUCTION (GENERAL) Realized Planning B- CONSTRUCTION PERIOD- 24 MONTH 19.12.2011 19.08.2014 100,00% Realized Planning 1 OPENING PRODUCTION and RE-INJECTION WELLS 15.01.2011 15.06.2012 20,00% Realized TEST STUDIES AND REPORTS of PRODUCTION and RE- Planning 2 01.03.2011 15.07.2012 20,00% INJECTION WELLS Realized Planning 3 DESIGN STUDIES of BINARY PLANT 01.08.2011 15.12.2011 5,00% Realized Planning 4 ORDER of PLANT 01.01.2012 01.06.2012 5,00% Realized TRANSPORTATION and INSTALLATION of PLANT Planning 5 01.06.2012 15.08.2013 15,00% FABRICATION Realized Planning 6 ASSEMBLING OF PLANT 15.08.2013 15.03.2014 10,00% Realized MECHANICAL-ELECTRICAL and AUTOMATION Planning 7 01.06.2012 01.06.2013 15,00% FABRICATON BETWEEN B.O.P. KUYUBAŞI and PLANTI Realized FABRICATION of CONNECTION POINT of PLANT and Planning 8 15.06.2011 15.06.2012 15,00% SYSTEM Realized STUDIES of PERFORMANCE TESTS and TAKING INTO Planning 9 15.03.2014 15.08.2014 5,00% OPERATION Realized TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (ACCORDING TO WEEKS) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% TOTAL - COMPLETING CONSTRUCTION PERIOD Planning 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 19.12.2011 19.08.2014 100,00% (GENERAL) Realized 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 17/17 PROCESS FLOW PUBLIC CONSULTATION 5. PUBLIC CONSULTATION Invitation Announcement in Yavuzköy Village and Yeni Kıroba Newspaper: announcing the date, time, location and agenda for upcoming stakeholder consultation meeting for DORA-3 Geothermal Power Project in Yavuzköy, Köşk, Aydın on 28th of October 2011. English Translation of announcement: “Announcement: There will be an Assessment and Information Meeting Regarding DORA-3 Geothermal Power Project Which is planned to be developed by Menderes Geothermal Elektrik Üretim A.Ş near Yavuzköy of Köşk District in Aydın Province. Place : Primary School of Yavuzköy, Köşk / Aydın Date : On Friday, 28 October 2011 Time : 11:00 The stakeholder meeting was held on 28st of October 2011 in one of class of primary school in Yavuzköy village, Köşk / Aydın. At the meeting besides project developers, there were four representatives from local state institutions, many participants from the villages and head of the village. Although NGOs are proactively invited to the meeting and invited to deliver their comments, they have refrained to express comments and regret that they cannot participate in the meeting due to lack of staff. The place of meeting was chosen to be the closest place to the project area and closest village which was Yavuzköy. All local people are informed about meeting in advance by local announcements. Additionally, one week before the meeting village mayor was visited and announcement of upcoming meeting was done. Before presentation, agenda of the meeting and non-technical PDD was distributed to the participants for broader view. Project presentation and description was made by representative of FutureCamp Turkey and Aktif Çevre including information about project developers, the technology and operation of the power plant, estimated emission reduction amount of the plant, the importance of revenue from emission reduction and the project characteristics which makes this project different from other power plant projects in Turkey. Before passing to blind sustainable development exercise, question and comments were taken from participants about further clarification of project. During and after presentation some questions were raised by participants, which were answered by project general Manager Mr. Haluk Tüfekçioğlu and the presenter. One of the most important topics raised during the meeting was whether it could be possible to benefit from hot geothermal fluid for agricultural purposes. Villagers demanded that in DORA-3 GPP, after using hot water, the fluid should be passed to local people for greenhouse production. The concern of local people was answered by the project developer if the demand from local people regarding usage of hot water comes in an organized demand than it can be discussed internally. However it should be clear that the project developer can supply hot geothermal fluid at some cost. During the meeting, representative of local governmental institutions expressed their support for renewable energy project of DORA-3 GPP. While the project is in the planning phase, all feedbacks are important for better understanding of demand from local people. Questions and comments raised by participants were addressed in assessment of the comments. The meeting was closed by a general support from participants. Assessment of all comments and questions Stakeholder comment and Questions Explanation (Why? How?) Representative from Agricultural Directorate It would be very much beneficial for project developer to of Aydın City: Do you have any concern to employee local people for the project if their qualifications employee local people in the project? are met. However you know that this is not always possible, but priority will be given to Yavuzköy and local residents. Representative from Agricultural Directorate The work for having emission reduction certificates of Aydın City: Does this project have already continues, and it will take more than two years to get the emission reduction certificates or you mean project registered. After project is commissioned than the that this project will apply for it? certificates will be generated. Representative from Agricultural Directorate As you can see from Dora-1 and Dora-2 all pipe lines of Aydın City: Does this project have any carrying hot fluid are jacketed for isolation. This is logical for loss of heat? Or does this project cause geothermal energy production, because we would like to heating of air? benefit from hot fluid as possible as we can. As you can see from the presentation, geothermal fluid is used in a totally closed circuit. Thus, project contribution to heat the environment and air is minimized. Representative from Agricultural Directorate If villagers are organized to have greenhouse agricultural of Aydın City: If I want to benefit from hot production and come to us with such of demand, then we water as a farmer, would you provide me the can discuss this. And possibly we can provide. hot fluid? Representative from Agricultural Directorate As project developer we are also investing in greenhouses of Aydın City: But as far as I know it is not for agricultural production and it is possible to re-inject the possible to re-inject hot fluid when it is colder fluid after usage in greenhouses. that some Celsius, how are you going to provide farmers with geothermal fluid than? Representative from Agricultural Directorate It changes according to the geography of the area, for us it of Aydın City: Could you please tell us how is between 1200 – 3000 metres. much deep is the drilling wells? Representative from Agricultural Directorate All the wells up to 900 metres are piped to prevent any of Aydın City: One more question, how can mixtures. This is done to preserve geothermal fluid you assure that underground water will not temperature and to prevent mixture of geothermal fluid in be mixed with geothermal fluids? underground water. Eyyup Derin: Why we are not working to You are so right in bringing your concerns for building a build Yavuz village to Yavuz city benefiting heating system for the village. As it is clear that project from geothermal resources? For example to developer cannot initiate such system when there is no build a modern heating system for the demand from local people as an organized structure. We houses in village which will reduce emission cannot just provide one house with heating system, but in the region? when your village comes with a project then this can be discussed of course. Evaluation forms No:1 Name Dr. Engin Tan What is your impression of the meeting? The meeting hall could have been better, but it is assumed that it has been chosen for easier local participation. Anyway the hall was used appropriately for the meeting What do you like about the project? It is very positive to hear that geothermal fluid will be re-injected in a binary cycle. Although the approach for farmers are weak till now, it is positive with new declarations as farmers. Most important thing is that the technology is foreigner, this should be reversed. Another positive approach could be heating of houses with geothermal fluid which gives more efficiency to the villagers. What do you not like about the project? Nothing NO: 2 Name Galip Kışla What is your impression of the meeting? Positive. It was an informing and enlightening meeting. What do you like about the project? Renewable energy, Benefit of the project is so much that cannot be counted. What do you not like about the project? Nothing NO: 3 Name Okan Yavuz What is your impression of the meeting? We thank a lot to the project developer for informing us about the project What do you like about the project? We are happy that they provide opportunities to us in sense of employment and repair of the village roads What do you not like about the project? Nothing NO: 4 Name Serap Çıtak What is your impression of the meeting? Presentation and responding of questions were positive What do you like about the project? Employment and support for greenhouses farming What do you not like about the project? Nothing NO: 5 Name Erdal Saraçoğlu What is your impression of the meeting? Presentation was informing. What do you like about the project? Harmless to the environment, Production of electricity that Turkey needs, Renewable energy, What do you not like about the project? Nothing In total there were 19 original evaluation forms gathered in the meeting, but for the report 5 of them is translated and original copies are attached in Annex 4. When it is gone through the evaluation forms, it becomes clear that there is a positive approach of local people for DORA-3 GPP. Besides being positive and supportive for the project, local people had expectations for possible use of geothermal fluid for agricultural and house heating usages. Another expectations of local people were employment of young generation in the project, which is also a concern of project developer. APPENDIX Version: 1 . 0 Effective Date: 17/08/2007 SAFETY DATA SHEET Previous Date: SCALETROL PDC9332 1 IDENTIFICATION OF PREPARATION AND OF COMPANY 1.1 Identification of the substance or preparation Product : SCALETROL PDC9332 1.2 Use of substance/preparation Deposit control agent 1.3 Company/undertaking identification GE Betz S.r.l. Strada Consortile, 7 03013 FERENTINO (FR) Tel : +39 07753911 e-mail : emea.productstewardship@ge.com 1.4 Emergency telephone Centro Antiveleni Ospedale Niguarda 0039 0266101029 Milano 2 HAZARDS IDENTIFICATION Important hazards - Health/physical hazard Not considered hazardous to health. - Symptoms of exposure Prolonged or repeated exposure may cause transient irritation. - Environmental hazards The product is not classified as dangerous for the environment. 3 COMPOSITION / INFORMATION ON INGREDIENTS Chemical description Phosphate and Phosphonate in water Hazardous component(s) EINECS/ELINCS # CAS # Conc. None. 4 FIRST AID MEASURES Skin contact Wash immediately with plenty of water. Eye contact Flush immediately with plenty of running water. Inhalation Remove to fresh air. Ingestion Rinse mouth with water. Product : SCALETROL PDC9332 Page : 1/ 5 Version: 1 . 0 Effective Date: 17/08/2007 SAFETY DATA SHEET Previous Date: SCALETROL PDC9332 5 FIRE-FIGHTING MEASURES Extinguishing Media - Suitable Carbon dioxide, dry chemicals, foam, water spray (fog). Special protective equipment for Self contained breathing apparatus. (CEN : EN 137) fire fighters Protective clothing (CEN : EN 469) Protective gloves (CEN : EN 659) Helmet (CEN : EN 443) Special exposure hazards Oxides of carbon, nitrogen and phosphorus evolved in fire. 6 ACCIDENTAL RELEASE MEASURES Personal precautions Protective clothing Please refer also to section no. 8 'Exposure controls' for further information. Environmental precautions Prevent from entering sewers or the immediate environment. Accidental release of large quantities into the aquatic environment may harm aquatic organisms. Methods for Cleaning Up - on soil Absorb onto inert material and dispose of according to Controlled Waste Regulations. Remove small spills with plenty of water. 7 HANDLING AND STORAGE 7.1 Handling Normal chemical handling. 7.2 Storage Store containers closed when not in use. Store in dry, cool, well ventilated area. 7.3 Specific use(s) Only for professional and industrial users Maximum storage stability (days) 720 8 EXPOSURE CONTROLS/PERSONAL PROTECTION Exposure controls - Recommended engineering Ensure good ventilation. controls - Respiratory protection Not required. - Hand protection Protective gloves (Plastic, impervious) (Protection against unintentional short-term contact) CEN : EN 420 - Eye protection Safety goggles. CEN : EN 166 - Skin protection Protective clothing if splashing or repeated contact with product is likely. CEN : EN 340 - Environmental exposure controls Prevent from entering in public sewers or the immediate environment. 9 PHYSICAL AND CHEMICAL PROPERTIES 9.1 General information Appearance Liquid Product : SCALETROL PDC9332 Page : 2/ 5 Version: 1 . 0 Effective Date: 17/08/2007 SAFETY DATA SHEET Previous Date: SCALETROL PDC9332 9.1 General information Colour Colourless to yellow Odour Slight 9.2 Important health, safety and environmental info pH in aqueous solution 7,8 (5%) Flash point (Pensky/Martens) (°C) > 100 Explosive properties Not applicable Oxidising properties Not classified as an oxidiser Density at 20°C (kg/m3) 1413 Solubility in water (% weight) Completely soluble Viscosity at 20°C (mPas) 100 Vapour density (air=1) <1 Evaporation rate (ether=1) <1 9.3 Other information Melting point, (°C) -16 Pour point, (°C) -13 10 STABILITY AND REACTIVITY 10.1 Conditions to avoid None known. 10.2 Materials to avoid Avoid contact with strong oxidisers. 10.3 Hazardous decomposition Oxides of carbon, nitrogen and phosphorus evolved in fire. products 11 TOXICOLOGICAL INFORMATION Mammalian Test Data - Oral LD50, rat (mg/kg) > 2000 (estimated value) - Dermal LD50, rabbit (mg/kg) > 2000 (estimated value) Exposure hazard - Inhalation Prolonged or repeated exposure may cause transient irritation. - Skin contact Prolonged or repeated contact may cause transient irritation. - Eye contact Prolonged or repeated contact may cause transient irritation. - Ingestion May cause slight gastrointestinal irritation. Product : SCALETROL PDC9332 Page : 3/ 5 Version: 1 . 0 Effective Date: 17/08/2007 SAFETY DATA SHEET Previous Date: SCALETROL PDC9332 12 ECOLOGICAL INFORMATION Ecotoxicity - Fathead minnow (mg/l) NOEL : 5000 (Calculated data) 96 hour Acute Toxicity - Daphnia Magna (mg/l) LC50 : 2450 (Calculated data) NOEL : 1560 (Calculated data) 48 hour Acute Toxicity Persistence and degradability - COD (mgO2/g) 180 (calculated data) - BOD 5 (mgO2/g) 0 (calculated data) - BOD 28 (mgO2/g) 0 (calculated data) - Closed Bottle Test (% Degradation 0 (calculated data) in 28 days) - Zahn-Wellens Test (% 5 (calculated data) Degradation in 28 days) - TOC (mg C/g) 60 (calculated data) Summary The product is not classified as dangerous for the environment. 13 DISPOSAL CONSIDERATIONS Disposal of product According to Controlled Waste Regulations. EWC ( European Waste Code ) recommendation : 16 03 06 16 Wastes not otherwise specified in the list. 16 03 Off-specification batches and unused products. 16 03 06 Organic wastes Depending on the origin and state of the waste, other EWC numbers may be applicable too. Disposal of packaging According to Controlled Waste Regulations. EWC ( European Waste Code ) recommendation : 15 01 02, 15 01 04 15 Waste packaging; absorbents, wiping cloths, filter materials and protective clothing not otherwise specified. 15 01 Packaging (including separately collected municipal packaging waste). 15 01 02 Plastic packaging. 15 01 04 Metallic packaging. Depending on the origin and state of the waste, other EWC numbers may be applicable too. 14 TRANSPORT INFORMATION Substance id.no. (SIN) (UN No.) Not applicable. Correct shipping name Not applicable. Land transport - RID/ADR classification Not classified under this legislation. Product : SCALETROL PDC9332 Page : 4/ 5 Version: 1 . 0 Effective Date: 17/08/2007 SAFETY DATA SHEET Previous Date: SCALETROL PDC9332 Maritime transport - IMO-IMDG class Not classified under this legislation Air transport - ICAO/IATA classification Not classified under this legislation 15 REGULATORY INFORMATION EEC labelling information - Symbol(s) None. - R Phrase(s) No Risk phrases assigned. - S Phrase(s) No Safety phrases assigned. - EINECS number All ingredients of this product are listed in EINECS or ELINCS, unless specifically exempted under the EEC Directive 67/548/EEC. 16 OTHER INFORMATION Nature of revision Correction in Section: 1,2,3,7,15 Based on EC Directive / 1999/45/EC Regulations 2001/58/EC 2001/118/EC (EC) No 1907/2006 (REACH) Product : SCALETROL PDC9332 Page : 5/ 5