65654 v2 Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 12/15/2011 1. Basic Information Project ID & Name P082429: CO-(APL1)Disaster VulnerabilityReduction Country Colombia Task Team Leader Niels B. Holm-Nielsen Sector Manager/Director Guang Zhe Chen Country Director Gloria M. Grandolini Original Board Approval Date 05/10/2005 Original Closing Date: 12/31/2011 Current Closing Date 08/31/2013 Proposed Closing Date [if applicable] 08/30/2013 EA Category C-Not Required Revised EA Category C-Not Required-Not Required EA Completion Date 05/20/2004 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 141.00 141.00 IBRD 260.00 110.00 Total 401.00 251.00 3. Borrower Organization Department Location 4. Implementing Agency Organization Department Location Ministry of Finance and Public Colombia Credit Ministry of Environment, Housing Colombia and Territorial Development i 5. Disbursement Estimates (US$m) Actual amount disbursed as of 03/29/2012 89.77 Fiscal Year Annual Cumulative 2011 3.10 92.87 2012 5.30 98.17 2013 3.15 101.32 Total 101.32 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The project's development objective is to strengthen national and local disaster risk management capacity. 7b. Revised Project Development Objectives/Outcomes [if applicable] ii