P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Services) Above or equal US$ 2 million 4. Individual (Goods) Above or equal Justification to be included US$ 10 million in the PP 5. Individual (Non Consultant Above or equal Justification to be included Services) US$ 2 million in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 5. Any Other Special Procurement Arrangements: Not Applicable 1 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) 1 Summary of 0 0 No No the ICB (Works) 2 Summary of 0 0 No No the ICB (Goods) 3 Summary of 0 0 No No the NCB (Works) 4 Summary of 1.5 18 No Post the NCB (Goods) 5 Summary of 0.74 2 No Prior the NCB (Non- Consultant Services) 6 Summary of 0.51 16 No Post the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 Competitive Methods (Individual) Above or equal US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 1.7 8 Prior LCS; SSS; number of CQS; contracts that Individual; will be let under other methods 2 Summary of 2 72 Post SSS; CQS; number of Individual contracts that will be let under other methods 3 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-02-14 2020-01-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240, IDA / 62230, IDA / D2980 Executing Agency(ies): UNITE DE GESTION DU PROJET FILETS SOCIAUX WORKS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-26069-CW- Laying the Foundations of RFQ / Aménagement des a Safety Net System and Demande de Single Stage - 2018-04- 2018-04- 2018-05- IDA / 52240 A posteriori Limited 8,300.00 7,209.40 Achevé bureaux de l'antenne Supporting Project prix One Envelope 01 24 15 régionale du Nord ouest Management GOODS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-5831-GO- Laying the Foundations of RFB / fourniture du a Safety Net System and Single Stage - 2017-01- 2017-01- 2017-03- 2017-04- 2017-05- 2017-11- matériel informatique, de IDA / 52240 A posteriori Appel d'offres Open - National 253,000.00 243,616.43 Achevé Supporting Project One Envelope 24 29 12 11 16 12 téléphonie, et d'équipement Management de bureau (en 3 lots distincts) CM-UGP-PFS-6172-GO- RFQ / Fourniture du matériel de la phase 3 Public Works Program Demande de Single Stage - 2017-02- 2017-04- 2017-05- des THIMO dans 2 IDA / 52240 A posteriori Limited 188,000.00 159,198.65 Achevé Pilot prix One Envelope 18 15 15 communes de la région de l'Extrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO- RFQ / Fourniture des boîtes à pharmacie de la phase 3 des THIMO pour Public Works Program Demande de Single Stage - 2017-02- 2017-04- 2017-05- IDA / 52240 A posteriori Limited 29,000.00 31,172.51 Achevé 2 communes de la région Pilot prix One Envelope 20 17 01 de l'Extrême Nord et 2 communes de la région de l'Est CM-UGP-PFS-6307-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-03- 2017-05- 2018-05- IDA / 52240 A posteriori Limited 60,000.00 0.00 Annulé fournitures de bureau au Supporting Project prix One Envelope 20 15 10 Projet Filets Sociaux Management CM-UGP-PFS-7392-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Single Stage - 2017-05- 2017-06- 2017-07- 2017-08- 2017-09- 2017-10- IDA / 52240 A posteriori Appel d'offres Open - National 130,000.00 0.00 Annulé consommables Supporting Project One Envelope 31 05 17 16 20 20 informatiques Management CM-UGP-PFS-16931-GO- Laying the Foundations of RFQ / fourniture des a Safety Net System and Demande de Single Stage - 2017-06- 2017-08- 2017-08- pièces de rechange pour IDA / 52240 A posteriori Open - National 37,500.00 32,502.70 Achevé Supporting Project prix One Envelope 19 14 28 véhicules et motos du Management Projet Filets Sociaux CM-UGP-PFS-23000-GO- RFQ / fourniture des boites à pharmacie pour Public Works Program Demande de Single Stage - 2017-08- 2017-10- 2018-04- la phase 4 des THIMO IDA / 52240 A posteriori Limited 25,100.00 21,014.35 Achevé Pilot prix One Envelope 15 13 11 dans 2 communes de la région de l'Adamaoua et 1 commune de la région du Nord CM-UGP-PFS-25708-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2017-11- 2017-12- 2018-01- IDA / 52240 A posteriori Limited 8,300.00 6,813.69 Achevé mobilier de bureau de Supporting Project prix One Envelope 09 12 02 l'antenne du Nord-Ouest Management CM-UGP-PFS-25990-GO- RFQ / Fourniture des boites à pharmacie de la Public Works Program Demande de Single Stage - 2017-10- 2017-11- 2017-12- phase 5 des THIMO pour IDA / 52240 A posteriori Limited 25,100.00 20,966.02 Achevé Pilot prix One Envelope 12 10 01 2 communes de la région de l'Est et 2 communes de la région du Nord ouest CM-UGP-PFS-26037-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-09- 2017-10- 2017-10- autocollants pour voitures IDA / 52240 A posteriori Limited 2,000.00 2,081.57 Achevé Supporting Project prix One Envelope 27 16 30 et motos au Projet Filets Management Sociaux CM-UGP-PFS-23003-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2017-09- 2017-10- 2017-10- IDA / 52240 A posteriori Limited 100,000.00 90,128.08 Achevé de travail pour la phase 4 Pilot prix One Envelope 11 03 24 des THIMO dans 2 communes de la région de l'Adamaoua CM-UGP-PFS-25561-GO- Laying the Foundations of RFB / Fourniture du a Safety Net System and Single Stage - 2017-09- 2017-09- 2017-09- 2017-09- 2017-09- 2017-10- matériel roulant autos et IDA / 52240 A posteriori Appel d'offres Open - National 162,000.00 143,614.65 Signé Supporting Project One Envelope 01 01 01 01 08 08 motos au projet Filets Management Sociaux en deux lots distincts CM-UGP-PFS-25477-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2017-10- 2017-11- 2017-11- IDA / 52240 A posteriori Limited 38,000.00 26,101.20 Achevé seaux au Projet Filets Measures to Boost prix One Envelope 09 06 27 Sociaux Household Productivity CM-UGP-PFS-25475-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2017-09- 2017-09- 2017-10- IDA / 52240 A posteriori Limited 61,000.00 50,255.93 Achevé de travail pour la phase 4 Pilot prix One Envelope 02 24 15 des THIMO dans la région du nord , commune de Touboro CM-UGP-PFS-47595-GO- RFQ / Fourniture du matériel de la phase 6 Public Works Program Demande de Single Stage - 2018-06- 2018-07- 2018-08- IDA / 52240 A posteriori Limited 80,275.00 65,428.39 Achevé des THIMO du Projet Pilot prix One Envelope 18 30 29 Filets Sociaux dans les communes de Dembo et Bashéo, région du Nord CM-UGP-PFS-47606-GO- RFB / Fourniture et paramétrage d'un progiciel Cash Transfer Program de gestion intégré pour la with Accompanying Single Stage - 2018-06- 2018-06- 2018-07- 2018-08- 2018-09- 2019-03- planification, la IDA / 52240 A posteriori Appel d'offres Open - National 167,500.00 0.00 Annulé Measures to Boost One Envelope 21 26 27 17 14 13 programmation, la Household Productivity budgétisation, le suivi évaluation et la production des rapports et indicateurs CM-UGP-PFS-47608-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2018-03- 2018-05- 2018-05- IDA / 52240 A posteriori Limited 48,400.00 0.00 Annulé logiciels informatiques au Measures to Boost prix One Envelope 27 08 29 projet Filets Sociaux Household Productivity CM-UGP-PFS-16933-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2017-06- 2017-08- 2017-09- seaux, Tee shirt, IDA / 52240 A posteriori Open - National 193,700.00 0.00 Annulé Measures to Boost prix One Envelope 20 15 14 casquettes autocollants Household Productivity pour véhicules estampillés Projet Filets Sociaux CM-UGP-PFS-25989-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2018-04- 2018-05- 2018-06- de travail pour la phase 5 IDA / 52240 A posteriori Limited 80,275.00 72,952.92 Achevé Pilot prix One Envelope 06 05 04 des THIMO dans 2 communes de la région du Nord ouest (Oku et Ako) CM-UGP-PFS-25987-GO- RFQ / Fourniture du matériel et des matériaux Public Works Program Demande de Single Stage - 2018-04- 2018-05- 2018-06- de travail pour la phase 5 IDA / 52240 A posteriori Limited 80,275.00 65,815.47 Achevé Pilot prix One Envelope 06 05 04 des THIMO dans 2 communes de la région de l'EST (Bétaré OYA et Batouri) Page 1 CM-UGP-PFS-25491-GO- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2018-04- 2018-05- 2019-05- IDA / 52240 A posteriori Limited 30,000.00 0.00 Annulé matériel de pause café au Supporting Project prix One Envelope 19 24 24 Projet Filets Sociaux Management CM-UGP-PFS-47578-GO- Cash Transfer Program RFQ / Fourniture des with Accompanying Demande de Single Stage - 2018-06- 2018-07- 2018-08- IDA / 52240 A posteriori Limited 28,400.00 24,340.71 Achevé pneus de recharge pour Measures to Boost prix One Envelope 04 16 06 des autos et motos du Household Productivity Projet CM-UGP-PFS-25476-GO- Cash Transfer Program RFQ / Fourniture des tee- with Accompanying Demande de Single Stage - 2017-12- 2017-12- 2018-01- IDA / 52240 A posteriori Limited 99,000.00 68,943.69 Achevé shirts et casquettes Measures to Boost prix One Envelope 02 26 16 estampillés au Projet Household Productivity Filets Sociaux CM-UGP-PFS-25488-GO- Laying the Foundations of RFQ / fourniture des a Safety Net System and Demande de Single Stage - 2018-01- 2018-02- 2019-02- IDA / 52240 A posteriori Limited 100,000.00 83,622.13 Achevé encres pour imprimantes Supporting Project prix One Envelope 03 10 10 et photocopieurs Management CM-UGP-PFS-25487-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-09- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 60,000.00 0.00 Annulé fournitures de bureau au Supporting Project prix One Envelope 16 11 11 Projet Filets sociaux Management CM-UGP-PFS-67485-GO- RFQ / Fourniture du Laying the Foundations of matériel informatique et a Safety Net System and Demande de Single Stage - 2018-07- 2018-08- 2018-09- IDA / 52240 A posteriori Limited 8,250.00 6,993.13 Achevé de bureautique de Supporting Project prix One Envelope 15 19 02 l'antenne régionale du Management projet du Nord Ouest CM-UGP-PFS-67490-GO- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2018-07- 2018-08- 2019-08- IDA / 52240 A posteriori Limited 8,250.00 3,525.35 Achevé polices d'assurance aux 40 Supporting Project prix One Envelope 10 14 14 premières motos du projet Management CM-UGP-PFS-47597-GO- RFQ / Fourniture des Public Works Program Demande de Single Stage - 2018-09- 2018-09- 2018-10- boîtes à pharmacie de la IDA / 52240 A posteriori Limited 8,360.00 7,383.31 Achevé Pilot prix One Envelope 09 30 07 phase 6 des THIMO du Projet Filets Sociaux CM-UGP-PFS-75801-GO- Cash Transfer Program RFQ / Fourniture du with Accompanying Demande de Single Stage - 2018-09- 2018-10- 2018-10- IDA / 52240 A posteriori Limited 8,360.00 7,144.10 Achevé matériel pour les crèches Measures to Boost prix One Envelope 15 10 17 temporaires au PFS Household Productivity CM-UGP-PFS-130190-GO- RFQ / Fourniture des licences pour la plateforme Laying the Foundations of tomate ( Licence a Safety Net System and Demande de Single Stage - 2019-10- 2019-12- 2020-06- IDA / 62230 A posteriori Limited 34,000.00 29,607.05 Signé Multiprojet, Monosite et Supporting Project prix One Envelope 10 13 10 Multiposte Tom2pro, Management Tom2monitoring, Tom2paie et Tom2marché) CM-UGP-PFS-121205-GO- Laying the Foundations of RFB / Fourniture des a Safety Net System and Demande de Single Stage - 2019-10- 2019-11- 2020-03- IDA / 52240 A posteriori Limited 80,000.00 62,547.39 Signé consommables Supporting Project prix One Envelope 05 23 22 informatiques au Projet Management Filets Sociaux CM-UGP-PFS-121383-GO- RFQ / Acquisition des Laying the Foundations of fournitures de bureaux et a Safety Net System and Demande de Single Stage - 2019-10- 2019-12- 2020-04- IDA / 62230 A posteriori Limited 40,000.00 26,447.17 Signé des produits d'entretien de Supporting Project prix One Envelope 14 16 14 bureau en deux lots Management distincts CM-UGP-PFS-120445-GO- UN / FOURNITURE DE 756 TABLETTES BIOMETRIQUES Laying the Foundations of Passation de MOBILES et 756 a Safety Net System and marchés auprès 2019-11- 2019-12- 2020-02- 2020-08- IDA / 62230 A posteriori Direct 660,808.00 660,808.00 Signé BATTERIE EXTERNES Supporting Project des agences de 30 14 02 20 TYPES POWERBANK ET Management l'ONU 756 SACS PHOTOVOLTAÏQUES en deux tranches de 400 et 356 chacune NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Loan / Credit Market Procurement Prequalificatio Process Prequalification Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Signed Contract Contract Completion No. Approach Process n (Y/N) Status Evaluation Report as Issued / Opening / Minutes Recommendation for (US$) (US$) Documents Justification / Invitation Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6232-NC- RFQ / Recrutement des Public Works Program Demande de Single Stage - 2017-02- 2017-04- 2017-12- agences de paiement pour IDA / 52240 A posteriori Limited 60,000.00 61,263.97 Signé Pilot prix One Envelope 15 12 08 les phases 3 et 4 des THIMO en lots CM-UGP-PFS-6233-NC- RFQ / Recrutement des agences de paiement pour le paiement de 19500 ménages bénéficiaires du Cash Transfer Program cycle 2 des transferts with Accompanying Demande de Single Stage - 2017-03- 2017-05- 2019-04- IDA / 52240 A priori Limited 351,000.00 0.00 Annulé monétaires dont 7500 Measures to Boost prix One Envelope 07 05 25 dans la région de Household Productivity l'Extrême Nord, 5500 dans les régions du Nord et de l'Adamaoua, et 6500 dans les régions de l'Est, du Nord Cash Transfer Program CM-UGP-PFS-6315-NC- with Accompanying Demande de Single Stage - 2017-02- 2017-04- 2017-05- RFQ / Impression des IDA / 52240 A posteriori Limited 70,000.00 22,001.63 Achevé Measures to Boost prix One Envelope 25 22 06 documents du Projet Household Productivity CM-UGP-PFS-6306-NC- Laying the Foundations of RFQ / fourniture des a Safety Net System and Demande de Single Stage - 2017-03- 2017-04- 2018-04- IDA / 52240 A posteriori Limited 123,900.00 58,410.90 Achevé polices d'assurance Supporting Project prix One Envelope 03 28 23 maladie Management CM-UGP-PFS-7385-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-03- 2017-04- 2018-04- IDA / 52240 A posteriori Limited 31,100.00 18,329.45 Achevé polices d'assurance Supporting Project prix One Envelope 03 28 23 automobile Management CM-UGP-PFS-14464-NC- Laying the Foundations of RFQ / Renouvellement du a Safety Net System and Demande de Single Stage - 2017-06- 2017-06- 2018-06- IDA / 52240 A posteriori Limited 8,250.00 3,553.09 Signé contrat d'assurance des 40 Supporting Project prix One Envelope 13 19 14 motos en circulation Management Laying the Foundations of CM-UGP-PFS-25608-NC- a Safety Net System and Demande de Single Stage - 2017-10- 2017-10- 2018-10- RFQ / Maintenance Autos IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé Supporting Project prix One Envelope 04 31 31 UGP pour 1 an Management CM-UGP-PFS-25616-NC- Laying the Foundations of RFQ / Maintenance a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé matériel bureautique et Supporting Project prix One Envelope 07 07 07 informatique UGP pour 1 Management an CM-UGP-PFS-25623-NC- Laying the Foundations of RFQ / Maintenance froid a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 8,300.00 0.00 Annulé et climatisation UGP Supporting Project prix One Envelope 11 09 09 pour 1 an Management CM-UGP-PFS-25711-NC- Laying the Foundations of RFQ / Fourniture du a Safety Net System and Demande de Single Stage - 2017-12- 2018-01- 2019-01- IDA / 52240 A posteriori Limited 6,000.00 8,986.03 Signé service de gardiennage Supporting Project prix One Envelope 09 09 09 pour l'antenne régionale Management du Nord Ouest CM-UGP-PFS-25729-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2017-12- systèmes de sécurité et de IDA / 52240 A posteriori Limited 4,000.00 1,315.18 Achevé Supporting Project prix One Envelope 15 15 15 GPS et du service de Management tracking pour les autos CM-UGP-PFS-25892-NC- Laying the Foundations of RFQ / Confection et la a Safety Net System and Demande de Single Stage - 2017-09- 2017-11- 2017-12- pose des plaques IDA / 52240 A posteriori Open - National 4,000.00 7,636.09 Achevé Supporting Project prix One Envelope 30 10 01 signalétiques (7 plaques Management directionnelles + 3 panneaux) CM-UGP-PFS-25980-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Limited 6,000.00 14,850.36 Signé de l'agence de gardiennage Supporting Project prix One Envelope 11 23 23 de l'antenne régionale du Management Nord Page 2 CM-UGP-PFS-25981-NC- Laying the Foundations of RFQ / Avenant au contrat a Safety Net System and Demande de Single Stage - 2017-09- 2017-09- 2018-09- de l'agence de gardiennage IDA / 52240 A posteriori Limited 5,000.00 16,374.35 Signé Supporting Project prix One Envelope 11 23 23 de l'antenne régionale de Management l'Extrême Nord CM-UGP-PFS-25983-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance du personnel a Safety Net System and Demande de Single Stage - 2017-09- 2017-10- 2018-08- IDA / 52240 A posteriori Limited 39,000.00 24,386.04 Achevé en vu de la prise en Supporting Project prix One Envelope 15 16 12 compte du personnel Management nouvellement recruté CM-UGP-PFS-30748-NC- DIR / recrutement d'une agence de paiement Cash Transfer Program chargée d'assurer les Passation de with Accompanying 2017-10- 2017-10- 2017-11- 2018-11- transferts monétaires des IDA / 52240 A posteriori marché de gré Direct 36,000.00 30,643.76 Signé Measures to Boost 04 09 16 16 bénéficiaires de la phase 2 à gré Household Productivity des transferts monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-37510-NC- RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/P Passation de FS/UGP/CAPM/2017 du 26 Public Works Program 2017-12- 2017-12- 2018-01- 2018-05- IDA / 52240 A posteriori marché de gré Direct 6,000.00 22,354.79 Signé mai 2017 de l'agence de Pilot 18 25 15 15 à gré paiement pour la réalisation des paiements des 6000 bénéficiaires des THIMO 5 dont 3000 dans le Nord-Ouest et 3000 dans l'Est CM-UGP-PFS-37511-NC- RFQ / Avenant au contrat Laying the Foundations of d'assurance véhicule Passation de a Safety Net System and 2017-12- 2017-12- 2018-01- 2018-07- LETTRE DE MARCHE IDA / 52240 A posteriori marché de gré Direct 4,000.00 1,207.48 Signé Supporting Project 18 23 09 08 N°011/LM/MINEPAT/CTS/P à gré Management FS/UGP/CAPM/2017 DU 08 JUIN 2017 CM-UGP-PFS-25853-NC- DIR / Avenant au contrat de l'agence de paiement chargée des transferts monetaires du cycle 2 à Public Works Program Demande de Single Stage - 2017-09- 2017-11- 2018-05- l'Est, le Nord ouest, IDA / 52240 A posteriori Limited 23,400.00 22,232.85 Signé Pilot prix One Envelope 25 20 19 Douala et Yaoundé pour la phase 5 des THIMO dont 3000 dans la région de l'Est et 3000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC- Cash Transfer Program RFQ / Fourniture de with Accompanying Demande de Single Stage - 2018-03- 2018-05- 2019-05- IDA / 52240 A posteriori Limited 28,000.00 14,785.79 Signé polices d'assurance autos Measures to Boost prix One Envelope 31 26 26 au projet Filets Sociaux Household Productivity CM-UGP-PFS-47582-NC- Cash Transfer Program RFQ / Confection et pause with Accompanying Demande de Single Stage - 2018-04- 2018-06- 2018-07- des plaques signalétiques IDA / 52240 A posteriori Limited 8,250.00 7,009.83 Achevé Measures to Boost prix One Envelope 30 11 11 des réalisations du Projet Household Productivity Filets Sociaux dans les communes CM-UGP-PFS-47593-NC- RFQ / Agence de paiement chargée d'assurer Cash Transfer Program le paiement des 3000 with Accompanying Demande de Single Stage - 2018-05- 2018-07- 2019-07- bénéficiaires de la phase 3 IDA / 52240 A posteriori Limited 19,170.00 0.00 Annulé Measures to Boost prix One Envelope 23 18 18 des transferts monétaires Household Productivity d'urgence du du Projet Filets Sociaux dans le Nord Ouest CM-UGP-PFS-47602-NC- DIR / Avenant au contrat de l'agence de paiement chargée d'assurer les paiement des transfert Passation de monétaires du cycle 2 Public Works Program 2018-06- 2018-06- 2018-07- 2019-01- IDA / 52240 A posteriori marché de gré Direct 11,700.00 10,227.50 Achevé dans le Nord et Pilot 21 26 31 27 à gré l'Adamaoua pour les paiements de 3000 bénéficiaire de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC- Laying the Foundations of RFQ / Maintenance froid a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé et climatisation EN et Supporting Project prix One Envelope 09 07 07 NO pour 1 an Management CM-UGP-PFS-25610-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos de Supporting Project prix One Envelope 04 31 31 l'Extrême-Nord Management CM-UGP-PFS-25612-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos du Projet Supporting Project prix One Envelope 03 30 30 du Nord Management CM-UGP-PFS-25618-NC- Laying the Foundations of RFQ / Maintenance a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé matériel bureautique et Supporting Project prix One Envelope 07 03 03 informatique EN et NO Management pour 1 an CM-UGP-PFS-47255-NC- Cash Transfer Program RFQ / Production et with Accompanying Demande de Single Stage - 2018-03- 2018-04- 2018-04- multiplication des IDA / 52240 A posteriori Limited 7,567.00 7,132.71 Achevé Measures to Boost prix One Envelope 16 10 24 documents des Pratiques Household Productivity familiales essentielles CM-UGP-PFS-26101-NC- Laying the Foundations of RFQ / Maintenance des a Safety Net System and Demande de Single Stage - 2017-10- 2017-11- 2018-11- IDA / 52240 A posteriori Limited 5,000.00 0.00 Annulé Autos et Motos du Nord- Supporting Project prix One Envelope 11 13 13 Ouest Management CM-UGP-PFS-6311-NC- Laying the Foundations of RFQ / Fourniture de a Safety Net System and Demande de Single Stage - 2018-04- 2018-05- 2019-05- IDA / 52240 A posteriori Limited 8,250.00 3,228.19 Achevé police d'assurance pour 20 Supporting Project prix One Envelope 06 11 06 motos Management CM-UGP-PFS-26060-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2018-05- 2018-06- 2018-06- IDA / 52240 A posteriori Limited 8,500.00 1,867.92 Achevé Systèmes de sécurité pour Supporting Project prix One Envelope 01 01 22 les motos du projet (20) Management CM-UGP-PFS-37512-NC- RFQ / Avenant N°2 au contrat d'assurance du Cash Transfer Program personnel pour la prise en Passation de with Accompanying 2018-03- 2018-04- 2018-05- 2018-10- compte des relais IDA / 52240 A posteriori marché de gré Direct 30,000.00 34,099.31 Signé Measures to Boost 30 06 04 31 communautaires recrutés à gré Household Productivity dans le cadre de la sensibilisation sur les pratiques familiales essentielles CM-UGP-PFS-47572-NC- Cash Transfer Program RFB / Fourniture des with Accompanying Demande de Single Stage - 2018-05- 2018-07- 2019-07- IDA / 52240 A posteriori Limited 130,000.00 127,074.00 Signé polices d'assurance au Measures to Boost prix One Envelope 07 02 02 personnel du Projet Filets Household Productivity Sociaux CM-UGP-PFS-72576-NC- RFQ / Multiplication de certains documents pour la collecte des données sur Laying the Foundations of les PFE de la phase a Safety Net System and Demande de Single Stage - 2018-09- 2018-10- 2018-11- pilote pour une période de IDA / 52240 A posteriori Limited 8,250.00 7,116.25 Achevé Supporting Project prix One Envelope 16 28 11 6 mois et des Management questionnaires et autres documents pour la collecte des données dans le cadre de la première évaluation interne du Projet CM-UGP-PFS-92192-NC- RFQ / Multiplication de Cash Transfer Program certains documents de with Accompanying Demande de Single Stage - 2019-01- 2019-02- 2020-02- IDA / 52240 A posteriori Limited 6,500.00 5,551.26 Signé collecte de données des Measures to Boost prix One Envelope 15 26 26 PFE pour une période Household Productivity d'un an MOF-CM-UGP-PFS-6233- NC-RFQ / Recrutement Cash Transfer Program des agences de paiement with Accompanying Demande de Single Stage - 2017-02- 2017-05- 2019-10- pour le paiement de IDA / 52240 A posteriori Limited 351,000.00 142,058.17 Signé Measures to Boost prix One Envelope 27 01 28 19500 menages Household Productivity beneficiaires du cycle 2 des transferts monetaires en 3 lots Page 3 CM-UGP-PFS-121194-NC- Laying the Foundations of RFQ / Fourniture des a Safety Net System and Demande de Single Stage - 2019-09- 2019-11- 2020-11- polices d'assurance pour IDA / 62230 A posteriori Limited 28,000.00 0.00 Annulé Supporting Project prix One Envelope 10 05 04 les autos du Projet Filets Management Sociaux CM-UGP-PFS-121367-NC- RFB / FOURNITURE D’UNE POLICE Laying the Foundations of D'ASSURANCE MALADIE a Safety Net System and Single Stage - En cours 2019-08- 2019-09- 2019-10- 2019-11- 2019-12- 2020-12- POUR UN AN EN IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 0.00 Supporting Project One Envelope d'exécution 30 14 26 25 23 22 FAVEUR DU Management PERSONNEL DU PROJET FILETS SOCIAUX ET LEURS FAMILLES (2019-2020) CM-UGP-PFS-152342-NC- RFQ / FOURNITURE Laying the Foundations of DES POLICES a Safety Net System and Demande de Single Stage - En attente 2020-02- 2020-04- 2021-04- IDA / 62230 A posteriori Open - National 28,000.00 0.00 D'ASSURANCE POUR SIX Supporting Project prix One Envelope d'exécution 10 14 14 (06) VEHICULES DU Management PROJET FILETS SOCIAUX CM-UGP-PFS-143140-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase Public Works Program Demande de Single Stage - En attente 2020-03- 2020-06- 2020-12- 7 des Travaux à Haute IDA / D2980 A posteriori Limited 22,500.00 0.00 Pilot prix One Envelope d'exécution 20 06 03 Intensité de Main d'œuvre du PFS dont 1000 dans la commune de Dir région de l'Adamaoua et 4000 dans la commune deTouboro, région du Nord CM-UGP-PFS-143142-NC- RFQ / Recrutement d'une agence de paiement pour le paiement des bénéficiaires de la phase Public Works Program Demande de Single Stage - En attente 2020-03- 2020-05- 2020-11- 7 des Travaux à Haute IDA / D2980 A posteriori Limited 9,000.00 0.00 Pilot prix One Envelope d'exécution 20 31 27 Intensité de Main d'œuvre du PFS dans la région de l'Est dont 1000 dans la commune de Ngoura, et 1000 dans la commune de Mandjou CM-UGP-PFS-143130-NC- RFQ / Recrutement d'une agence de paiement pour le transfert des paiements Public Works Program Demande de Single Stage - En attente 2020-03- 2020-05- 2020-11- aux 3000 bénéficiaires IDA / D2980 A posteriori Limited 13,500.00 0.00 Pilot prix One Envelope d'exécution 20 31 27 de la phase 7 des Travaux à Haute Intensité de Main d'œuvre dans la commune de Mokolo CONSULTING FIRMS Activity Reference No. Actual Short List and Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of / Description Component Review Type Method Amount Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS- CQS / ONG pour THIMO: 7000 bénéficiaires dans 2 communes de l'Extrême Sélection fondée Nord, 2 communes de Public Works Program sur les 2017-02- 2017-04- 2017-05- 2017-06- 2017-12- IDA / 52240 A posteriori Open - National 429,190.00 367,605.09 Achevé 2017-02-07 l'Est pour la phase 3 et Pilot qualifications 28 13 13 17 14 6000 bénéficiaires: 2 des consultants communes Adamaoua, 1 commune Nord pour la phase 4 en 2017 (1 ONG par région) CM-UGP-PFS-54735-CS- CQS / Consultant pour le Cash Transfer Program Sélection fondée développement d'un with Accompanying sur les 2018-06- 2018-08- 2018-09- 2018-10- 2019-04- IDA / 52240 A posteriori Open - National 167,500.00 135,528.54 Signé 2018-05-30 progiciel de gestion intégré Measures to Boost qualifications 20 03 02 07 05 pour le système Household Productivity des consultants d'information du Projet Filets Sociaux INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 12,950.00 10,372.40 Signé 2017-02-06 Measures to Boost 27 17 22 16 l'enregistrement à Household Productivity Blangoua du cycle 2 des transferts monetaires CM-UGP-PFS-6334-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 12,950.00 10,368.36 Signé 2017-02-06 Measures to Boost 27 17 22 16 l'enregistrement à Goulfey Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6337-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 15,500.00 12,422.62 Signé 2017-02-06 Measures to Boost 27 17 22 21 l'enregistrement à Makari Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6339-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé 2017-02-06 Measures to Boost 27 17 22 16 l'enregistrement à GOBO Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6340-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 Measures to Boost 27 17 22 16 l'enregistrement à Household Productivity BOURRHA du cycle 2 des transferts monetaires CM-UGP-PFS-6341-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-03- 2017-04- 2017-05- 2017-06- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 Measures to Boost 27 17 22 16 l'enregistrement à Koza du Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6342-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé 2017-02-06 Measures to Boost 13 14 24 21 l'enregistrement à Mogodé Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6344-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 15,500.00 11,613.54 Signé 2017-02-06 Measures to Boost 13 14 24 26 l'enregistrement à Banyo Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6346-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 10,381.76 Signé 2017-02-06 Measures to Boost 13 14 24 21 l'enregistrement à Tcheboa Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6347-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 9,829.76 Signé 2017-02-06 Measures to Boost 13 14 24 21 l'enregistrement à Mayo Household Productivity Oulo du cycle 2 des transferts monetaires CM-UGP-PFS-6348-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 9,707.50 Signé 2017-02-06 Measures to Boost 24 26 28 25 l'enregistrement à Rey Household Productivity Bouba du cycle 2 des transferts monetaires CM-UGP-PFS-6349-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-02- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 9,716.26 Signé 2017-02-06 Measures to Boost 09 10 12 09 l'enregistrement à Touboro Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6350-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-03- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 11,772.77 Signé 2017-02-06 Measures to Boost 18 28 04 29 l'enregistrement à Kette Household Productivity du cycle 2 des transferts monetaires Page 4 CM-UGP-PFS-6351-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-03- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 9,713.75 Signé 2017-02-06 Measures to Boost 18 28 04 29 l'enregistrement à Belo du Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6352-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-03- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 12,500.00 9,703.73 Signé 2017-02-06 Measures to Boost 18 28 04 29 l'enregistrement à Household Productivity Menchum Valley du cycle 2 des transferts monetaires CM-UGP-PFS-6353-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-03- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 15,500.00 9,020.07 Achevé 2017-02-06 Measures to Boost 18 28 04 29 l'enregistrement à Douala Household Productivity 3 du cycle 2 des transferts monetaires CM-UGP-PFS-6354-CS- Cash Transfer Program INDV / Consultant pour with Accompanying 2017-02- 2017-02- 2017-03- 2017-03- le ciblage et IDA / 52240 A posteriori Individuel Open 15,500.00 9,264.24 Signé 2017-02-06 Measures to Boost 18 28 04 29 l'enregistrement à Yaoundé Household Productivity du cycle 2 des transferts monetaires CM-UGP-PFS-6355-CS- INDV / Consultant chargé d'améliorer les modules du volet économique notamment formation en Cash Transfer Program AGR ( agriculture, petit with Accompanying 2017-02- 2017-03- 2017-03- 2017-04- IDA / 52240 A posteriori Individuel Open 26,260.00 22,361.04 Achevé 2017-02-10 commerce, gestion de Measures to Boost 25 02 12 17 l'argent, élevage) et former Household Productivity les bénéficiaires dans ces modules à l'Extrême Nord dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : Cash Transfer Program formation en AGR ( with Accompanying 2017-02- 2017-03- 2017-03- 2017-04- agriculture,petit commerce, IDA / 52240 A posteriori Individuel Open 28,460.00 24,278.93 Achevé 2017-02-10 Measures to Boost 25 02 12 17 gestion de l'argent, Household Productivity élevage) et former les bénéficiaires dans ces modules dans le Nord et l'Adamaoua dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS- INDV / Consultant chargé d'améliorer les modules du volet économique : formation en AGR ( Cash Transfer Program agriculture,petit commerce, with Accompanying 2017-02- 2017-03- 2017-03- 2017-04- IDA / 52240 A posteriori Individuel Open 31,400.00 26,919.25 Achevé 2017-02-10 gestion de l'argent, Measures to Boost 25 02 12 17 élevage) et former les Household Productivity bénéficiaires dans ces modules dans le Nord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS- Public Works Program 2017-04- 2017-04- 2017-06- 2017-11- INDV / Expert IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-02-17 Pilot 07 28 02 29 environnemental et social du PFS Laying the Foundations of CM-UGP-PFS-6423-CS- a Safety Net System and 2017-03- 2017-04- 2017-05- 2017-06- INDV / Assistant IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 Supporting Project 28 18 23 28 Comptable Management Laying the Foundations of CM-UGP-PFS-6424-CS- a Safety Net System and 2017-03- 2017-04- 2017-05- 2017-06- IDA / 52240 A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 INDV / Assistant SPM Supporting Project 28 18 23 28 Management CM-UGP-PFS-6327-CS- Cash Transfer Program Sélection de CDS / protocole d'accord with Accompanying 2017-02- 2017-03- 2017-09- IDA / 52240 A priori consultants par Direct 900,000.00 0.00 Annulé 2017-02-06 avec l'INS pour le Measures to Boost 16 03 29 entente directe dénombrement et l'enquête Household Productivity PMT du cycle 2 CM-UGP-PFS-14406-CS- INDV / Opérateur Terrain Cash Transfer Program commune Mayo Moskota with Accompanying 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 12,960.00 7,006.15 Signé 2017-05-19 (Extrême Nord) pour les Measures to Boost 04 11 21 21 transferts monetaires Household Productivity d'urgence CM-UGP-PFS-14407-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2017-05- 2017-05- 2019-05- IDA / 52240 A posteriori Individuel Open 24,000.00 55,333.37 Signé 2017-05-08 du contrat de l'Assistante Supporting Project 09 10 10 10 du Coordonnateur du Management Projet CM-UGP-PFS-14409-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2017-05- 2017-05- 2019-05- du contrat de la IDA / 52240 A posteriori Individuel Open 19,200.00 44,266.70 Signé 2017-05-05 Supporting Project 06 07 07 07 Secrétaire de l'Unité de Management Gestion du Projet CM-UGP-PFS-14410-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2017-05- 2017-05- 2019-05- contrat Chauffeur 1 de IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 Supporting Project 06 07 07 07 l'Unité de Gestion du Management Projet CM-UGP-PFS-14411-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2017-05- 2017-05- 2019-05- IDA / 52240 A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 contrat Chauffeur 2 Supporting Project 06 07 07 07 Unité de Gestion du Management Projet CM-UGP-PFS-14412-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-05- 2017-05- 2017-05- 2019-05- du contrat de l'Agent de IDA / 52240 A posteriori Individuel Open 16,800.00 32,191.68 Signé 2017-05-05 Supporting Project 06 07 07 07 liaison de l'Unité de Management Gestion du Projet CM-UGP-PFS-14463-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 12,960.00 0.00 Annulé 2017-06-09 contrat de l'operateur de Supporting Project 12 13 15 15 terrain de Yaoundé 7 Management CM-UGP-PFS-14460-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori Individuel Open 3,240.00 0.00 Annulé 2017-06-09 contrat de l'opératrice de Supporting Project 12 13 15 12 terrain de la commune de Management Douala 2 CM-UGP-PFS-14490-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 16,800.00 0.00 Annulé 2017-06-15 contrat de Technicienne de Supporting Project 23 25 29 29 surface de l'UGP Management CM-UGP-PFS-14454-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 19,200.00 34,575.36 Résilié 2017-06-09 contrat du point focal de Supporting Project 12 13 15 15 la ville de Douala Management CM-UGP-PFS-16811-CS- Laying the Foundations of INDV / renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- contrat opérateur de IDA / 52240 A posteriori Individuel Direct 12,960.00 25,629.07 Signé 2017-06-09 Supporting Project 11 12 13 03 terrain 1 commune de Management MOKOLO CM-UGP-PFS-16814-CS- Laying the Foundations of INDV / renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- contrat opérateur de IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 Supporting Project 12 13 14 04 terrain 2 commune de Management MOKOLO CM-UGP-PFS-16821-CS- Laying the Foundations of INDV / Renouvellement de a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- contrat de l'opérateur de IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 Supporting Project 12 13 15 05 terrain de la commune de Management MAGA CM-UGP-PFS-16823-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2017-12- du contrat de l'opérateur IDA / 52240 A posteriori Individuel Direct 3,240.00 22,483.20 Signé 2017-06-09 Supporting Project 10 11 12 09 de terrain de la commune Management de Kar Hay Laying the Foundations of CM-UGP-PFS-16925-CS- a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- INDV / Avenant au IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-12 Supporting Project 15 19 21 11 contrat du SPM du Projet Management Page 5 Laying the Foundations of CM-UGP-PFS-14451-CS- a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- INDV / Renouvellement IDA / 52240 A priori Individuel Open 46,000.00 0.00 Annulé 2017-06-09 Supporting Project 10 14 15 15 du contrat Comptable Management CM-UGP-PFS-14446-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- du contrat de l'Expert IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-09 Supporting Project 09 10 15 15 Informatique et Management Responsable SIG du Projet CM-UGP-PFS-14452-CS- Laying the Foundations of INDV / Renouvellement a Safety Net System and 2017-06- 2017-06- 2017-06- 2019-06- IDA / 52240 A priori Individuel Direct 38,400.00 0.00 Annulé 2017-06-09 du contrat du Responsable Supporting Project 12 13 15 15 Régional Extrême Nord Management CM-UGP-PFS-25501-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and 2017-09- 2017-10- 2017-10- 2018-10- responsable régional du IDA / 52240 A posteriori Individuel Open 19,200.00 46,457.14 Signé 2017-08-31 Supporting Project 26 03 13 13 Nord ouest du projet Management Filets Sociaux CM-UGP-PFS-25504-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2017-09- 2017-10- 2017-10- 2018-04- de la Conception et l' IDA / 52240 A posteriori Individuel Open 21,500.00 80,692.20 Signé 2017-09-01 Supporting Project 29 06 16 19 appui à la mise en œuvre Management du plan de communication CM-UGP-PFS-25520-CS- INDV / Recrutement de 4 consultants pour le ciblage des bénéficiaires de la phase 2 des transferts Laying the Foundations of monetaires d'urgence dans a Safety Net System and 2017-10- 2017-10- 2017-10- 2017-11- IDA / 52240 A posteriori Individuel Open 36,400.00 30,128.36 Achevé 2017-09-07 les département du Supporting Project 12 19 27 16 Logone et Chari Management (Communes de Blangoua, Goulfey, Makari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS- Laying the Foundations of INDV / Avenant N°01 au a Safety Net System and 2017-09- 2017-09- 2017-09- 2018-09- contrat de l'Expert IDA / 52240 A posteriori Individuel Open 38,095.25 157,236.52 Signé 2017-09-06 Supporting Project 09 10 11 11 informatique et Management responsable SIG UGP CM-UGP-PFS-25786-CS- Laying the Foundations of INDV / Avenant N°02 au a Safety Net System and 2017-09- 2017-09- 2017-09- 2018-09- contrat du Spécialiste en IDA / 52240 A posteriori Individuel Open 38,095.25 71,473.92 Signé 2017-09-06 Supporting Project 09 10 11 11 passation des Marchés de Management l'UGP CM-UGP-PFS-25787-CS- Laying the Foundations of INDV / Avenant N°1 au a Safety Net System and 2017-09- 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Individuel Open 35,555.57 134,620.67 Signé 2017-09-06 contrat du Comptable de Supporting Project 09 10 11 11 l'UGP Management CM-UGP-PFS-25794-CS- INDV / Avenant N°1 au Laying the Foundations of contrat du Responsable a Safety Net System and 2017-09- 2017-09- 2017-09- 2018-09- IDA / 52240 A posteriori Individuel Open 19,200.00 86,985.26 Signé 2017-09-06 régional du Projet Filets Supporting Project 09 10 11 11 Sociaux dans l'Extrême Management Nord CM-UGP-PFS-25517-CS- INDV / Consultant chargé de la sensibilisation des Cash Transfer Program bénéficiaires du Cycle 2 with Accompanying 2017-10- 2017-10- 2017-10- 2018-02- IDA / 52240 A posteriori Individuel Open 58,180.00 43,182.70 Signé 2017-09-07 (i) à l'Extrême Nord, (ii) Measures to Boost 12 19 27 24 au Nord et à l'Adamaoua, Household Productivity (iii) à l'Est, au Nord- ouest, à Douala et à Yaoundé CM-UGP-PFS-6326-CS- Cash Transfer Program Sélection de CDS / Protocole d'accord with Accompanying 2017-08- 2017-09- 2018-05- IDA / 52240 A priori consultants par Direct 500,000.00 391,776.36 Signé 2017-08-31 avec l'INS pour la Measures to Boost 31 16 14 entente directe réalisation de l'enquête de Household Productivity base CM-UGP-PFS-25509-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-12- 2018-01- 2018-01- 2019-01- dans la commune de IDA / 52240 A posteriori Individuel Open 40,800.00 49,307.71 Signé 2017-11-30 Measures to Boost 30 06 14 14 Koza, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25508-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2018-01- 2018-02- 2018-02- 2019-02- dans la commune de IDA / 52240 A posteriori Individuel Open 40,800.00 46,287.84 Signé 2017-12-30 Measures to Boost 29 03 11 11 Bourrha, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25512-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2017-12- 2018-01- 2018-01- 2019-01- dans la commune de IDA / 52240 A posteriori Individuel Open 40,800.00 69,189.81 Signé 2017-11-30 Measures to Boost 30 06 14 14 Mogode, département du Household Productivity Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25515-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2018-01- 2018-01- 2018-01- 2019-01- IDA / 52240 A posteriori Individuel Open 40,800.00 50,528.89 Signé 2017-11-30 dans la commune de Measures to Boost 02 09 17 17 Mayo-Oulo, département Household Productivity du Mayo Louti, Région du Nord CM-UGP-PFS-25516-CS- INDV / Recrutement de Cash Transfer Program 34 relais communautaires with Accompanying 2018-01- 2018-01- 2018-01- 2019-01- IDA / 52240 A posteriori Individuel Open 40,800.00 68,555.87 Signé 2017-11-30 dans la commune de Measures to Boost 04 11 19 19 Tcheboa, département de Household Productivity la Bénoué, Région du Nord CM-UGP-PFS-37431-CS- Laying the Foundations of INDV / Chauffeur de a Safety Net System and 2018-01- 2018-01- 2018-01- 2019-01- IDA / 52240 A posteriori Individuel Open 6,840.00 10,274.36 Signé 2017-12-27 l'antenne régionale du Supporting Project 20 22 29 29 Projet du Nord- Ouest Management CM-UGP-PFS-37432-CS- Laying the Foundations of INDV / Secrétaire de a Safety Net System and 2018-01- 2018-01- 2018-02- 2019-02- IDA / 52240 A posteriori Individuel Open 9,600.00 15,722.34 Signé 2017-12-28 l'antenne régionale du Supporting Project 23 28 04 04 Projet du Nord Ouest Management CM-UGP-PFS-37434-CS- Laying the Foundations of INDV / Point focal du a Safety Net System and 2017-12- 2017-12- 2017-12- 2018-12- IDA / 52240 A posteriori Individuel Open 9,600.00 14,584.42 Signé 2017-11-30 Projet de la ville de Supporting Project 22 26 28 28 Douala Management CM-UGP-PFS-25972-CS- CQS / Avenant au contrat N°001/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de la mise en œuvre des Public Works Program 2017-12- 2018-01- 2018-07- IDA / 52240 A posteriori consultants par Direct 99,042.50 93,748.34 Signé 2017-12-18 THIMO 3 dans l'Extrême Pilot 25 18 17 entente directe Nord avec 4000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région du Nord- ouest CM-UGP-PFS-25907-CS- CQS / Avenant au contrat N°002/MINEPAT/CTS/PFS/ CAPM/2017 du 23 mars 2017 de l'ONG chargée de Sélection de la mise en œuvre des Public Works Program 2017-12- 2018-01- 2018-07- IDA / 52240 A posteriori consultants par Direct 99,042.50 92,937.44 Achevé 2017-12-18 THIMO 3 dans la région Pilot 25 18 17 entente directe de l'Est avec 3000 bénéficiaires pour la mise en œuvre des THIMO 5 avec 3000 bénéficiaires dans la région de l'Est CM-UGP-PFS-47367-CS- INDV / Consultant individuel chargé Public Works Program 2018-04- 2018-04- 2018-04- 2018-05- IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-03-30 d'actualiser la carte des Pilot 04 18 28 28 THIMO du Projet Filets Sociaux Page 6 CM-UGP-PFS-47368-CS- INDV / Consultants Cash Transfer Program individuels (3) chargés du with Accompanying 2018-05- 2018-05- 2018-06- 2018-07- ciblage des bénéficiaires IDA / 52240 A posteriori Individuel Open 20,256.00 0.00 Annulé 2018-04-06 Measures to Boost 09 23 02 17 de la phase 3 des Household Productivity transferts monétaires d'urgence dans la région du Nord Ouest CM-UGP-PFS-47363-CS- INDV / Consultants individuels (03) chargés de Cash Transfer Program compléter et d'améliorer with Accompanying 2018-04- 2018-04- 2018-05- 2019-05- les manuels de formation IDA / 52240 A posteriori Individuel Open 63,040.00 87,765.09 Signé 2018-03-09 Measures to Boost 14 28 12 12 et de former les Household Productivity bénéficiaires sur les AGR pour le cycle 2 des transferts monétaires du Projet Filets CM-UGP-PFS-47362-CS- Cash Transfer Program INDV / Consultant with Accompanying 2018-04- 2018-04- 2018-04- 2019-04- individuel chargé de la IDA / 52240 A posteriori Individuel Open 8,250.00 7,158.24 Signé 2018-03-15 Measures to Boost 17 24 30 30 traduction des documents Household Productivity du projet en anglais CM-UGP-PFS-25526-CS- INDV / Consultant chargé Laying the Foundations of de l'accompagnement en a Safety Net System and 2017-10- 2017-10- 2017-10- 2018-10- IDA / 52240 A posteriori Individuel Open 12,000.00 0.00 Annulé 2017-09-15 TOM2PRO, TOM2PAIE, Supporting Project 11 16 24 24 TOM2MONITORING et Management TOM2MARCHE CM-UGP-PFS-25881-CS- Laying the Foundations of INDV / Consultant chargé a Safety Net System and 2018-05- 2018-05- 2018-06- 2018-12- IDA / 52240 A posteriori Individuel Open 8,250.00 7,201.62 Achevé 2018-04-17 du développement du site Supporting Project 13 20 17 14 WEB Management CM-UGP-PFS-16899-CS- Laying the Foundations of INDV / Avenant au a Safety Net System and 2017-10- 2017-10- 2017-10- 2019-10- IDA / 52240 A posteriori Individuel Open 76,190.00 71.57 Signé 2017-10-02 contrat de l'auditeur Supporting Project 13 18 23 13 interne Management Cash Transfer Program CM-UGP-PFS-47928-CS- with Accompanying 2018-05- 2018-06- 2018-07- 2019-07- INDV / Assistant au suivi IDA / 52240 A posteriori Individuel Open 12,000.00 10,966.15 Signé 2018-04-20 Measures to Boost 30 13 04 04 évaluation Household Productivity CM-UGP-PFS-47923-CS- Cash Transfer Program INDV / Recrutement d'un with Accompanying 2018-05- 2018-05- 2018-06- 2019-06- IDA / 52240 A posteriori Individuel Open 12,000.00 26,092.28 Signé 2018-04-04 Spécialiste en Passation Measures to Boost 07 21 18 18 des Marché Assistant Household Productivity CM-UGP-PFS-54610-CS- INDV / consultant Cash Transfer Program individuel pour l'assistance with Accompanying 2018-04- 2018-05- 2018-06- 2018-12- à la migration comptable IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-16 Measures to Boost 21 12 16 13 vers le nouveau référentiel Household Productivity comptable SYSCOHADA révisé CM-UGP-PFS-54615-CS- INDV / consultant pour Cash Transfer Program assister l'UGP à with Accompanying 2018-04- 2018-05- 2018-06- 2019-06- IDA / 52240 A posteriori Individuel Limited 8,250.00 10,408.76 Signé 2018-04-20 l'utilisation optimale des Measures to Boost 25 16 20 20 logiciels TOM2PRO, Household Productivity TOM2PAIE et TOM2MARCHE CM-UGP-PFS-54616-CS- INDV / Consultant pour la conception du masque Cash Transfer Program de saisie, la supervision with Accompanying 2018-04- 2018-05- 2018-06- 2018-12- IDA / 52240 A posteriori Individuel Limited 8,250.00 7,097.50 Signé 2018-04-25 de la saisie et l'analyse Measures to Boost 30 21 25 22 des données de la Household Productivity première évaluation interne du Projet IDA CM-UGP-PFS-47366-CS- INDV / Consultant Cash Transfer Program individuel chargé with Accompanying 2018-05- 2018-05- 2018-05- 2018-06- d'actualiser la carte de IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-30 Measures to Boost 05 19 29 28 pauvreté pour les Household Productivity transferts monétaires du Projet Filets Sociaux CM-UGP-PFS-47370-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat du point focal du with Accompanying 2018-04- 2018-05- 2018-10- IDA / 52240 A posteriori consultants par Direct 3,600.00 3,181.63 Signé 2018-04-20 Projet dans le Measures to Boost 27 03 30 entente directe Département du Mberé, Household Productivity région de l'Adamaoua CM-UGP-PFS-25974-CS- CQS / Contrat ONG pour Sélection de la phase 6 des THIMO Public Works Program 2018-06- 2018-07- 2019-01- IDA / 52240 A posteriori consultants par Direct 99,042.50 85,366.88 Achevé 2018-05-30 pour 3000 bénéficiaires Pilot 09 30 26 entente directe dans 2 communes de la région du Nord CM-UGP-PFS-47376-CS- INDV / Avenant au contrat de l'opérateur de Cash Transfer Program Sélection de terrain de la commune de with Accompanying 2018-04- 2018-05- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé 2018-04-24 la commune de la Measures to Boost 28 04 31 entente directe commune de kai kai Household Productivity département du Mayo Danay, région de l'extrême Nord CM-UGP-PFS-47377-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2018-04- 2018-05- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 terrain de la commune de Measures to Boost 28 04 31 entente directe Méri, département du Household Productivity Diamaré, région de l'Extrême Nord CM-UGP-PFS-47378-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain de la commune de IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 Ndoukoula, département entente directe Household Productivity du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47379-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2018-04- 2018-05- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,169.08 Signé 2018-04-24 terrain de la commune de Measures to Boost 28 04 31 entente directe Guider, département du Household Productivity Mayo Louti, région du Nord CM-UGP-PFS-47430-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat de l'opérateur de with Accompanying 2018-04- 2018-05- 2018-10- IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 terrain de la commune de Measures to Boost 28 04 31 entente directe Lagdo, département de la Household Productivity Bénoué, région du Nord CM-UGP-PFS-47431-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N° 1 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 commune de Bibemi entente directe Household Productivity (ADAMOU Bienvenu), département de la Bénoué, région du Nord CM-UGP-PFS-47432-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N° 2 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 commune de Bibemi entente directe Household Productivity (GOUDOUM GRANA Dieunedort), département de la Bénoué, région du Nord CM-UGP-PFS-47433-CS- INDV / Avenant au contrat de l'opérateur de Cash Transfer Program terrain de la commune de Sélection de with Accompanying 2018-04- 2018-04- 2019-04- Kar Hay pour la IDA / 52240 A posteriori consultants par Direct 8,100.00 8,495.18 Signé 2018-04-18 Measures to Boost 22 28 28 commune de Makary dans entente directe Household Productivity le département du Logone et Chari, région de l'Extrême Nord CM-UGP-PFS-47434-CS- Cash Transfer Program INDV / Avenant au Sélection de with Accompanying 2018-04- 2018-05- 2019-12- contrat de la secrétaire de IDA / 52240 A posteriori consultants par Direct 16,800.00 15,497.59 Signé 2018-04-24 Measures to Boost 28 04 30 l'antenne régionale de entente directe Household Productivity l'Extrême Nord Page 7 CM-UGP-PFS-47435-CS- Cash Transfer Program INDV / Avenant au with Accompanying 2018-03- 2018-03- 2018-03- 2019-12- IDA / 52240 A posteriori Individuel Direct 11,340.00 7,980.91 Signé 2018-03-05 contrat du chauffeur de Measures to Boost 12 17 25 15 l'antenne régionale du Household Productivity Nord CM-UGP-PFS-47369-CS- INDV / Avenant au Cash Transfer Program Sélection de contrat du point focal du with Accompanying 2018-04- 2018-05- 2018-11- IDA / 52240 A posteriori consultants par Direct 3,600.00 3,188.07 Signé 2018-04-25 département du Diamaré Measures to Boost 29 05 01 entente directe dans la région de Household Productivity l'Extrême Nord CM-UGP-PFS-47371-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N°1 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 commune de DIR entente directe Household Productivity (HEBGASSO Jean Baptiste) département du Mbéré, région de l'Adamaoua CM-UGP-PFS-47372-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N° 2 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 Commune de Dir entente directe Household Productivity (HOULAO Pierre) département du Mbéré, région de l'Adamoua CM-UGP-PFS-47375-CS- INDV / Avenant au Cash Transfer Program contrat de l'opérateur de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N°2 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 commune de BOGO( entente directe Household Productivity Wanie Bernard) département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS- INDV / Avenant au Cash Transfer Program contrat de l'opératrice de Sélection de with Accompanying 2018-04- 2018-05- 2018-10- terrain N°1 de la IDA / 52240 A posteriori consultants par Direct 2,430.00 2,147.60 Signé 2018-04-24 Measures to Boost 28 04 31 commune de BOGO, entente directe Household Productivity département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-59671-CS- Cash Transfer Program Sélection de CDS / Opérateur de with Accompanying 2018-05- 2018-05- 2018-11- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,391.05 Signé 2018-04-30 terrain de la commune de Measures to Boost 10 19 15 entente directe Douala 4 Household Productivity CM-UGP-PFS-59673-CS- Cash Transfer Program INDV / Recrutement du with Accompanying 2018-06- 2018-06- 2018-06- 2019-06- Responsable régional de IDA / 52240 A posteriori Individuel Open 19,200.00 16,630.56 Signé 2018-05-04 Measures to Boost 06 13 22 22 l'antenne du Nord du Household Productivity Projet Filets Sociaux CM-UGP-PFS-59789-CS- CDS / Audit financier et comptable des comptes du Projet de Remise à niveau Cash Transfer Program des Réseaux de Transport Sélection de with Accompanying 2018-04- 2018-05- 2020-05- d'Electricité et Réforme du IDA / 52240 A posteriori consultants par Direct 54,000.00 46,581.42 Signé 2018-04-26 Measures to Boost 30 14 13 Secteur (PRRTERS): entente directe Household Productivity exercices 2017-2018 - 2019 et du Projet Filets Sociaux (PFS) : exercices 2017-2018 CM-UGP-PFS-67474-CS- CDS / Avenant au contrat Laying the Foundations of Sélection de de l'opérateur de terrain a Safety Net System and 2018-07- 2018-07- 2019-01- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 de la commune de Supporting Project 03 09 05 entente directe Yaoundé 1er NGO SICK Management ELEANOR RHOLY épouse KAM CM-UGP-PFS-67475-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2018-07- 2018-07- 2019-01- de la commune de IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 Supporting Project 03 09 05 Funfong, département du entente directe Management Boyo région du Nord Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS- CDS / Avenant au contrat de l'opérateur de terrain Laying the Foundations of Sélection de de la commune de a Safety Net System and 2018-07- 2018-07- 2019-01- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 Balikumbat département Supporting Project 03 09 05 entente directe du Ngo Ketungja région Management du Nord Ouest TAJIPUKU ALPHONSE TAMIGHANG CM-UGP-PFS-67478-CS- CDS / avenant au contrat de l'opérateur de terrain Laying the Foundations of Sélection de N1 de la commune de a Safety Net System and 2018-07- 2018-07- 2019-01- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,831.73 Signé 2018-06-29 Messamena département Supporting Project 03 09 05 entente directe du Haut Nyong région de Management l'Est TSALA MVOGO BERNARD JEAN CM-UGP-PFS-67479-CS- Laying the Foundations of CDS / Avenant au contrat Sélection de a Safety Net System and 2018-07- 2018-07- 2019-01- du point focal du IDA / 52240 A posteriori consultants par Direct 4,800.00 4,195.15 Signé 2018-06-29 Supporting Project 03 09 05 département du Haut entente directe Management Nyong région de l'Est MBILLA Pierre Valery CM-UGP-PFS-67481-CS- CDS / avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2018-07- 2018-07- 2018-11- N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 2,160.00 1,887.82 Signé 2018-07-02 Supporting Project 06 12 09 Messamena ESSOMBA entente directe Management YANNICK ALBERT NGUEM CM-UGP-PFS-67482-CS- CDS / Avenant au contrat Laying the Foundations of de l'opérateur de terrain Sélection de a Safety Net System and 2018-07- 2018-07- 2018-08- N°2 de la commune de IDA / 52240 A posteriori consultants par Direct 540.00 471.95 Achevé 2018-06-29 Supporting Project 03 08 07 Lagdo, département de la entente directe Management Bénoué, région du Nord SIRINA ELVIS CM-UGP-PFS-67517-CS- Laying the Foundations of Sélection de INDV / Responsable a Safety Net System and 2018-07- 2018-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 38,095,248.00 0.00 Annulé 2018-06-29 Administratif et Financier Supporting Project 04 11 11 entente directe du Projet Management CM-UGP-PFS-72586-CS- Laying the Foundations of INDV / Recrutement d'un a Safety Net System and 2018-09- 2018-09- 2018-10- 2019-10- IDA / 52240 A posteriori Individuel Direct 5,940.00 5,136.94 Signé 2018-08-23 opérateur de terrain pour Supporting Project 02 23 28 28 la commune de Koza Management CM-UGP-PFS-81429-CS- INDV / consultants national sénior chargé Laying the Foundations of d'appuyer la Banque a Safety Net System and 2018-10- 2018-11- 2018-12- 2019-03- mondiale et le Projet IDA / 52240 A posteriori Individuel Limited 24,600.00 21,307.91 Achevé 2018-10-18 Supporting Project 25 15 20 20 Filets Sociaux dans la Management préparation d'une évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-83718-CS- Laying the Foundations of INDV / Responsable a Safety Net System and 2018-12- 2019-01- 2019-02- 2021-02- IDA / 52240 A posteriori Individuel Open 38,096.00 32,568.58 Signé 2018-11-11 Administratif et Financier Supporting Project 30 20 24 23 du Projet Filets Sociaux Management CM-UGP-PFS-83719-CS- Laying the Foundations of INDV / Expert en a Safety Net System and 2018-12- 2019-01- 2019-02- 2020-02- IDA / 52240 A posteriori Individuel Open 38,095.00 25,544.73 Signé 2018-11-11 sauvegardes sociales du Supporting Project 30 20 24 24 Projet Filets Sociaux Management CM-UGP-PFS-83720-CS- Laying the Foundations of INDV / coach du a Safety Net System and 2019-01- 2019-01- 2019-03- 2019-08- responsable des activités IDA / 52240 A posteriori Individuel Open 38,095.00 19,480.26 Résilié 2018-11-18 Supporting Project 06 27 03 30 d'accompagnement du Management Projet Filets Sociaux CM-UGP-PFS-83722-CS- Laying the Foundations of INDV / Assistant en a Safety Net System and 2019-01- 2019-01- 2019-03- 2020-03- IDA / 52240 A posteriori Individuel Open 14,400.00 10,329.66 Signé 2018-11-18 Gestion des Ressources Supporting Project 06 27 03 02 Humaines et du matériel Management CM-UGP-PFS-83723-CS- Laying the Foundations of INDV / Assistant au a Safety Net System and 2019-01- 2019-01- 2019-03- 2020-03- Responsable du Systeme IDA / 52240 A posteriori Individuel Open 14,400.00 9,119.51 Signé 2018-11-18 Supporting Project 06 27 03 02 d'Information Management du Projet Filets Sociaux Page 8 MOF-CM-UGP-PFS-14460- Laying the Foundations of Sélection de CS-CDS / Avenant au a Safety Net System and 2017-06- 2017-06- 2017-12- IDA / 52240 A posteriori consultants par Direct 3,240.00 2,785.30 Signé 2017-06-09 contrat de l'opératrice de Supporting Project 13 16 13 entente directe terrain de la commune de Management Douala 2 MOF-UGP-PFS-14463-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2017-06- 2017-06- 2019-06- IDA / 52240 A posteriori consultants par Direct 12,960.00 25,147.34 Signé 2017-01-12 de l'operateur de terrain Supporting Project 12 23 23 entente directe de Yaoundé 7 Management MOF-UGP-PFS-14490-CS- Laying the Foundations of Sélection de CDS / Avenant au contrat a Safety Net System and 2017-06- 2017-07- 2019-07- IDA / 52240 A posteriori consultants par Direct 16,800.00 14,442.29 Signé 2017-06-15 de Technicienne de surface Supporting Project 23 02 02 entente directe de l'UGP Management MOF-CM-UGP-PFS-6421- Laying the Foundations of CS-INDV / Expert a Safety Net System and 2017-04- 2017-04- 2017-06- 2019-06- IDA / 52240 A posteriori Individuel Open 63,840.00 81,486.50 Signé 2017-02-17 environnemental et social Supporting Project 07 28 02 02 du PFS Management Laying the Foundations of MOF-CM-UGP-PFS-6423- a Safety Net System and 2017-03- 2017-04- 2017-05- 2018-05- CS-INDV / Assistant IDA / 52240 A posteriori Individuel Open 9,600.00 27,305.89 Signé 2017-02-07 Supporting Project 28 18 23 23 Comptable Management Laying the Foundations of MOF-CM-UGP-PFS-6424- a Safety Net System and 2017-03- 2017-04- 2017-05- 2018-05- IDA / 52240 A posteriori Individuel Open 9,600.00 6,156.07 Résilié 2017-02-07 CS-INDV / Assistant SPM Supporting Project 28 18 23 23 Management Laying the Foundations of CM-UGP-PFS-108883-CS- a Safety Net System and 2019-06- 2019-07- 2019-08- 2020-08- INDV / Auditeur interne IDA / 52240 A posteriori Individuel Open 45,714.00 29,878.57 Signé 2019-04-19 Supporting Project 16 07 04 03 du Projet Filets Sociaux Management CM-UGP-PFS-111619-CS- CDS / Avenant N°01 au Cash Transfer Program contrat de l'Opérateur de Sélection de with Accompanying 2019-06- 2019-08- 2019-12- Terrain 1 de la Commune IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 Measures to Boost 01 05 05 de Banyo, Département du entente directe Household Productivity Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111629-CS- CDS / Avenant Contrat de Cash Transfer Program l'Opérateur de Terrain 2 Sélection de with Accompanying 2019-06- 2019-08- 2019-12- de la Commune de Banyo, IDA / 52240 A posteriori consultants par Direct 2,160.00 1,845.59 Signé 2019-05-22 Measures to Boost 01 05 05 Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111638-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2019-06- 2019-08- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 2,459.26 Signé 2019-05-22 la Commune de Bélo, Measures to Boost 01 05 16 entente directe Département du Boyo, Household Productivity Région du Nord-Ouest CM-UGP-PFS-111640-CS- Cash Transfer Program CDS / Avenant au contrat Sélection de with Accompanying 2019-06- 2019-08- 2020-01- de l'Opérateur de Terrain IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 Measures to Boost 01 05 16 1 de Douala IIIe, Ville de entente directe Household Productivity Douala CM-UGP-PFS-111642-CS- Cash Transfer Program CDS / Avenant de Sélection de with Accompanying 2019-06- 2019-08- 2020-01- l'Opérateur de Terrain 2 IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 Measures to Boost 01 05 16 de la Commune de Douala entente directe Household Productivity IIIe, Ville de Douala CM-UGP-PFS-111643-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 with Accompanying 2019-06- 2019-08- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 de la Commune de Ketté, Measures to Boost 01 05 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111658-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain 2 with Accompanying 2019-06- 2019-08- 2020-01- IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 de la Commune de Ketté, Measures to Boost 01 05 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111662-CS- Cash Transfer Program CDS / Avenant contrat de Sélection de with Accompanying 2019-06- 2019-08- 2020-01- l'Opératrice de Terrain 1 IDA / 52240 A posteriori consultants par Direct 2,898.00 15,181.83 Signé 2019-05-22 Measures to Boost 01 05 16 de la Commune de entente directe Household Productivity Yaoundé IIe, Ville de Yaoundé CM-UGP-PFS-111664-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2019-11- la Commune de Blangoua, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême-Nord CM-UGP-PFS-111670-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2019-11- la Commune de Bourha, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111678-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2019-11- la Commune de Gobo, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême-Nord CM-UGP-PFS-111681-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2019-11- la Commune de Goulfey, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême-Nord CM-UGP-PFS-111685-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2019-11- la Commune de Koza, IDA / 52240 A posteriori consultants par Direct 1,620.00 1,374.74 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111688-CS- CDS / Avenant contrat de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2020-05- la Commune de Makari, IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 Measures to Boost 01 05 06 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême-Nord CM-UGP-PFS-111691-CS- CDS / Avenant de Cash Transfer Program l'Opérateur de Terrain de Sélection de with Accompanying 2019-06- 2019-08- 2020-05- la Commune de Mogodé, IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 Measures to Boost 01 05 06 Département du Mayo entente directe Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111692-CS- CDS / Avenant contrat de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2019-06- 2019-08- 2019-12- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 la Commune de Mayo Measures to Boost 01 05 05 entente directe Oulo, Département du Household Productivity Mayo Louti, Région du Nord CM-UGP-PFS-111696-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2019-06- 2019-08- 2020-05- IDA / 52240 A posteriori consultants par Direct 4,860.00 4,124.22 Signé 2019-05-22 la Commune de Rey Measures to Boost 01 05 06 entente directe Bouba, Département du Household Productivity Mayo Rey, Région du Nord CM-UGP-PFS-111698-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain de with Accompanying 2019-06- 2019-08- 2020-05- IDA / 52240 A posteriori consultants par Direct 4,898.00 4,124.22 Signé 2019-05-22 la Commune de Tchéboa, Measures to Boost 01 05 06 entente directe Département de la Household Productivity Bénoué, Région du Nord Page 9 CM-UGP-PFS-111699-CS- CDS / Avenant de Cash Transfer Program Sélection de l'Opérateur de Terrain 1 with Accompanying 2019-06- 2019-08- 2019-12- IDA / 52240 A posteriori consultants par Direct 2,160.00 1,832.99 Signé 2019-05-22 de la Commune de Measures to Boost 01 05 05 entente directe Touboro, Département du Household Productivity Mayo Rey, Région du Nord CM-UGP-PFS-111725-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet with Accompanying 2019-06- 2019-08- 2020-01- IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé 2019-05-22 Filets Sociaux dans le Measures to Boost 01 05 16 entente directe Département de la Kadey, Household Productivity Région de l'Est CM-UGP-PFS-111726-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2019-06- 2019-08- 2020-05- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé 2019-05-22 Measures to Boost 01 05 06 Département du Logone et entente directe Household Productivity Chari, Région de l'Extrême-Nord CM-UGP-PFS-111727-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2019-06- 2019-08- 2019-12- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 3,200.00 2,715.54 Signé 2019-05-22 Measures to Boost 01 05 05 Département du Mayo entente directe Household Productivity Banyo, Région de l'Adamaoua CM-UGP-PFS-111735-CS- CDS / Avenant contrat Cash Transfer Program Point Focal du Projet Sélection de with Accompanying 2019-06- 2019-08- 2019-11- Filets Sociaux dans le IDA / 52240 A posteriori consultants par Direct 2,400.00 2,036.65 Signé 2019-05-22 Measures to Boost 01 05 04 Département du Mayo entente directe Household Productivity Danay, Région de l'Extrême-Nord CM-UGP-PFS-111737-CS- CDS / Avenant contrat Cash Transfer Program Sélection de Point Focal du Projet with Accompanying 2019-06- 2019-08- 2020-05- IDA / 52240 A posteriori consultants par Direct 7,200.00 6,109.96 Signé 2019-05-22 Filets Sociaux dans le Measures to Boost 01 05 06 entente directe Département Mayo Household Productivity Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111739-CS- Cash Transfer Program CDS / Avenant contrat Sélection de with Accompanying 2019-06- 2019-08- 2020-01- Point Focal du Projet IDA / 52240 A posteriori consultants par Direct 4,293.00 22,491.60 Signé 2019-05-22 Measures to Boost 01 05 16 Filets Sociaux dans la entente directe Household Productivity Ville de Yaoundé CM-UGP-PFS-121795-CS- CDS / Consultant chargé de l'élaboration de la Laying the Foundations of Sélection de méthodologie de choix et a Safety Net System and En cours 2019-12- 2020-02- 2020-03- IDA / 62230 A posteriori consultants par Direct 28,000.00 0.00 2019-11-30 d’opérationnalisation du Supporting Project d'exécution 19 13 14 entente directe choix des communes Management bénéficiaires du Projet Filets Sociaux CM-UGP-PFS-141188-CS- INDV / Recrutement d'un Laying the Foundations of point Focal dans la a Safety Net System and 2020-02- 2020-02- 2020-03- 2022-03- ville de Douala, région du IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé 2019-12-10 Supporting Project 04 25 31 31 littoral pour la phase 3 Management des Transferts Monétaires ordinaires CM-UGP-PFS-141191-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans la ville a Safety Net System and 2020-02- 2020-02- 2020-03- 2022-03- IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé 2019-12-10 de Yaoundé pour la Supporting Project 04 25 31 31 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141758-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1000 bénéficiaires de Laying the Foundations of la Phase 3 des TMU du a Safety Net System and En cours 2020-01- 2020-02- 2020-03- 2020-10- IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2019-11-29 Projet Filets Sociaux dans Supporting Project d'exécution 24 14 20 16 la commune de Waza, Management département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-143558-CS- INDV / Recrutement de l'enquêteur Chercheur Laying the Foundations of N°1 de l'équipe a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- septentrionale dans le IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé 2019-11-29 Supporting Project 20 03 07 06 cadre de la préparation Management d'une évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143560-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143562-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 5,394.00 4,942.86 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143563-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe septentrionale a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 5,394.00 7,719.29 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143564-CS- INDV / Recrutement de l'enquêteur Chercheur N°1 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143565-CS- INDV / Recrutement de l'enquêteur Chercheur N°2 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143567-CS- INDV / Recrutement de l'enquêteur Chercheur N°3 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,902.00 4,529.24 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun CM-UGP-PFS-143568-CS- INDV / Recrutement de l'enquêteur Chercheur N°4 Laying the Foundations of de l'équipe Adamaoua-Est a Safety Net System and 2019-12- 2020-01- 2020-02- 2020-06- dans le cadre de la IDA / 62230 A posteriori Individuel Limited 4,394.00 4,529.24 Signé 2019-11-29 Supporting Project 20 03 07 06 préparation d'une Management évaluation qualitative sur les Violences Basées sur le Genre (VBG) au Cameroun Page 10 CM-UGP-PFS-152346-CS- INDV / RECRUTEMENT DU CONSULTANT CHARGE D’INSTALLER Laying the Foundations of ET DE PARAMETRER a Safety Net System and En attente 2020-02- 2020-02- 2020-04- 2020-07- LES LOGICIELS IDA / 62230 A posteriori Individuel Limited 7,500.00 0.00 2020-01-31 Supporting Project d'exécution 07 28 04 03 TOM2PRO, Management TOM2MARCHE ET TOM2PAIE D’UNE PART ET D’AUTRE PART DE RENFORCER LES CAPACITES DE L’UGP CM-UGP-PFS-141804-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des1500 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 2020-02-05 cycle 3 des TMO du Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Douala V , Ville de Douala CM-UGP-PFS-142945-CS- CDS / Recrutement d'une ONG pour la mise en Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- œuvre des activités de la IDA / D2980 A posteriori consultants par Direct 99,042.00 0.00 2020-02-10 Pilot d'exécution 29 04 30 Phase 7 des THIMO dans entente directe la région de l'Extrême Nord, commune de Mokolo CM-UGP-PFS-142946-CS- CDS / Recrutement d'une ONG pour la mise en Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- œuvre des activités de la IDA / D2980 A posteriori consultants par Direct 132,056.00 0.00 2020-02-10 Pilot d'exécution 29 04 30 Phase 7 des THIMO dans entente directe la région du Nord , commune de Touboro CM-UGP-PFS-142944-CS- CDS / Recrutement d'une ONG pour la mise en œuvre des activités de la Sélection de Public Works Program En attente 2020-02- 2020-05- 2020-12- Phase 7 des THIMO IDA / D2980 A posteriori consultants par Direct 99,042.00 0.00 2020-02-10 Pilot d'exécution 29 04 30 dans les régions de entente directe l'Adamaoua (commune de Dir) et de l'Est (Communes de Ngoura et de Mandjou) CM-UGP-PFS-141718-CS- INDV / Recrutement de l'Opérateur de Terrain I Laying the Foundations of de la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-05 Meiganga, département du Supporting Project d'exécution 01 22 27 27 Mbéré, région de Management l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141159-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet Filets Laying the Foundations of Sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-05 Commune de Moulvoudaye Supporting Project d'exécution 01 22 27 27 , département du Mayo Management Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141771-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Limbé III, département du Fako, région du Sud-Ouest CM-UGP-PFS-141767-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Limbé I , département du Fako, région du Sud-Ouest CM-UGP-PFS-141193-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Bétaré Oya , département du Lom et Djérem, région de l'Est CM-UGP-PFS-141793-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 3000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 12,950.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Touboro, département du Mayo-Rey, région du Nord CM-UGP-PFS-141812-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1500 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 2020-02-05 cycle 3 des TMO du Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Yaoundé III , Ville de Yaoundé CM-UGP-PFS-141785-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Moulvoudaye , département du Mayo Kani, région de l'Extrême- Nord CM-UGP-PFS-141196-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Madringrin , département du Mayo-Rey, région du Nord CM-UGP-PFS-141794-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune d' Ebolowa II, département de la Mvila, région du Sud CM-UGP-PFS-141765-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- la Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Bamenda III , département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141192-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1000 bénéficiaires de Laying the Foundations of la Phase 3 des TMU du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2020-02-05 Projet Filets Sociaux dans Supporting Project d'exécution 01 22 27 23 la commune de Fotokol, Management département du Logone et Chari, région de l'Extrême- Nord CM-UGP-PFS-141800-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Meyomessala, département du Dja et Lobo, région du Sud Page 11 CM-UGP-PFS-141780-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Meiganga , département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141787-CS- INDV / Recrutement d'un Consultant pour le ciblage des 1500 bénéficiaires du Laying the Foundations of cycle 3 des TMO du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- IDA / D2980 A posteriori Individuel Open 7,850.00 0.00 2020-02-05 Projet Filets Sociaux dans Supporting Project d'exécution 01 22 27 27 la commune de Logone Management Birni, département du Logone et Chari, région de l'Extrême-Nord CM-UGP-PFS-141735-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°2 de la la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Madingring , département IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires CM-UGP-PFS-141755-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Ngaoui, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141763-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Bamenda II , département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141791-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 2000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Garoua Boulaï , département du Lom et Djérem, région de l'Est CM-UGP-PFS-141731-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet Filets Laying the Foundations of Sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Commune de Moulvoudaye Supporting Project d'exécution 06 27 01 01 , département du Mayo Management Kani, région de l'Extrême- Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141725-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°2 du Projet Filets a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Sociaux de la Commune IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 de Meiganga, département Management du Mbéré, région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141729-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet filets Laying the Foundations of sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Commune de Garoua- Supporting Project d'exécution 06 27 01 01 Boulaï, département du Management Lom et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141167-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Meiganga, département du Supporting Project d'exécution 06 27 01 01 Mbéré, région de Management l'Adamaoua pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141179-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Limbé II, département de Supporting Project d'exécution 06 27 01 01 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141141-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°1 du Projet Filets a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Sociaux de la Commune IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 de Meiganga, département Management du Mbéré, région de l'Adamaoua pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141164-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Ma'am, Département de la IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 Vallée du Ntem, région Management du Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141171-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- Fotokol, département du IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 Logone et Chari, région Management de l'Extrême Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141752-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires de a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- la Phase 3 des TMU du IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Meiganga, département du Mbéré, région de l'Adamaoua CM-UGP-PFS-141168-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Ngaoui, département du Supporting Project d'exécution 06 27 01 01 Mbéré, région de Management l'Adamaoua pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141091-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-04- 2020-05- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2020-02-20 la Région de l'Est pour la Supporting Project d'exécution 16 07 11 11 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141160-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°1 de la la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Madingring , département IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 du Mayo Rey, région du Management Nord pour le cycle 3 des Transferts Monetaires Ordinaires Page 12 CM-UGP-PFS-141143-CS- INDV / Recrutement de l' Opérateur de Terrain N°1 du Projet Filets Laying the Foundations of Sociaux de la Commune a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 de Logone Birni, Supporting Project d'exécution 06 27 01 01 département du Logone et Management Chari, région de l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141197-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Bamenda I, département de la Mezam, région du Nord- Ouest CM-UGP-PFS-141162-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Meyomessala, Département IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 du Dja et Lobo, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141801-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 1000 bénéficiaires du a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2022-05- cycle 3 des TMO du IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 27 Projet Filets Sociaux dans Management la commune de Ma'an , département de la Valée du Ntem, région du Sud CM-UGP-PFS-141178-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Limbé I, département de Supporting Project d'exécution 06 27 01 01 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141769-CS- INDV / Recrutement d'un Consultant pour le ciblage Laying the Foundations of des 500 bénéficiaires de la a Safety Net System and En attente 2020-04- 2020-04- 2020-05- 2020-12- Phase 3 des TMU du IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 2020-02-05 Supporting Project d'exécution 01 22 27 23 Projet Filets Sociaux dans Management la commune de Limbé II, département du Fako, région du Sud-Ouest CM-UGP-PFS-141176-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- Bamenda III, département IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141161-CS- INDV / Recrutement de 3 Opérateurs de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Touboro, département du IDA / D2980 A posteriori Individuel Open 38,880.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 Mayo-Rey, région du Nord Management pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141163-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 d'Ebolowa II, département Supporting Project d'exécution 06 27 01 01 de la Mvila, région du Management Sud pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141180-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Limbé III, département de Supporting Project d'exécution 06 27 01 01 Fako, région du Sud- Management Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141107-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-04- 2020-05- 2020-06- 2022-06- la Région du SUD-OUEST IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 2020-02-20 Supporting Project d'exécution 16 07 11 11 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141727-CS- INDV / Recrutement de l'Opérateur de Terrain N°2 du Projet Filets Laying the Foundations of Sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Commune de Bétaré Oya, Supporting Project d'exécution 06 27 01 01 département du Lom et Management Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141184-CS- INDV / Recrutement d'un Laying the Foundations of Point Focal dans le a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- département du Mayo IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 Rey, région du Nord pour Management la cycle 3 des Transferts Monétaires ordinaires CM-UGP-PFS-141155-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet filets Laying the Foundations of sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Commune de Garoua- Supporting Project d'exécution 06 27 01 01 Boulaï, département du Management Lom et Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141097-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-04- 2020-05- 2020-06- 2022-06- IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 2020-02-20 la Région du SUD pour la Supporting Project d'exécution 16 07 11 11 cycle 3 des Transferts Management Monétaires ordinaires CM-UGP-PFS-141174-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Bamenda II, département Supporting Project d'exécution 06 27 01 01 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141170-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- Waza, département du IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 Logone et Chari, région Management de l'Extrême Nord pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141717-CS- INDV / Recrutement de l'Opérateur de Terrain Laying the Foundations of N°2 de la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- Logone Birni, département IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Supporting Project d'exécution 06 27 01 01 du Logone et Chari, Management région de l'Extrême Nord pour le cycle 3 des Transferts Monétaires Ordinaires Page 13 CM-UGP-PFS-141145-CS- INDV / Recrutement de l'Opérateur de Terrain N°1 du Projet Filets Laying the Foundations of Sociaux dans la a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-02-10 Commune de Bétaré Oya, Supporting Project d'exécution 06 27 01 01 département du Lom et Management Djérem, région de l'Est pour le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141187-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Mayo a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-02-10 Kani, région de l'Extrême Supporting Project d'exécution 06 27 01 01 Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141084-CS- INDV / Recrutement d'un Laying the Foundations of Responsable Régional dans a Safety Net System and En attente 2020-04- 2020-05- 2020-06- 2022-06- la Région de l'Adamaoua IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2020-02-20 Supporting Project d'exécution 16 07 11 11 pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141173-CS- INDV / Recrutement d'un Opérateur de Terrain Laying the Foundations of dans la Commune de a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2021-06- IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2020-02-10 Bamenda I, département Supporting Project d'exécution 06 27 01 01 de MEZAM, région du Management Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141183-CS- INDV / Recrutement d'un Point Focal dans le Laying the Foundations of département du Logone et a Safety Net System and En attente 2020-04- 2020-04- 2020-06- 2022-06- IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-02-10 Chari, région de l'Extrême Supporting Project d'exécution 06 27 01 01 Nord pour la cycle 3 des Management Transferts Monétaires ordinaires CM-UGP-PFS-141118-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141134-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Adamaoua Management du Projet Filets Sociaux CM-UGP-PFS-141123-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale du Sud-Ouest du Management Projet Filets Sociaux CM-UGP-PFS-141131-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Chauffeur de l'antenne IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Est du Management Projet Filets Sociaux CM-UGP-PFS-141129-CS- Laying the Foundations of INDV / Recrutement du a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Chauffeur de l'antenne IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale Sud du Projet Management Filets Sociaux CM-UGP-PFS-141130-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Est du Management Projet Filets Sociaux CM-UGP-PFS-141133-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Secrétaire de l'antenne IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale de l'Adamaoua Management du Projet Filets Sociaux CM-UGP-PFS-141124-CS- Laying the Foundations of INDV / Recrutement de la a Safety Net System and En attente 2020-06- 2020-07- 2020-08- 2022-08- Secrétaire de l'antenne IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-04-30 Supporting Project d'exécution 25 16 20 20 régionale Sud du Projet Management Filets Sociaux Page 14