Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Rural Community-Driven Development Project (P090712) AFRICA | Guinea-Bissau | Social Protection & Labor Global Practice | IBRD/IDA | Investment Project Financing | FY 2010 | Seq No: 16 | ARCHIVED on 10-Mar-2018 | ISR31115 | Implementing Agencies: Project Coordination Unit, Ministry of Finance, The Republic of Guinea Bissau, PCU/RURAL COMMUNITY-DRIVEN DEVELOPMENT PROJECT Key Dates Key Project Dates Bank Approval Date:24-Sep-2009 Effectiveness Date:07-Jul-2010 Planned Mid Term Review Date:14-Jan-2013 Actual Mid-Term Review Date:14-Jan-2013 Original Closing Date:31-Dec-2014 Revised Closing Date:20-Sep-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to increase access to priority basic social and economic infrastructures and services in participating communities in at least two regions of Guinea-Bissau. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Name Component 5: Prevention of the Ebola epidemic:(Cost $0.50 M) Component 1: Capacity-Building for Community Development:(Cost $0.45 M) Component 2: Community-Based Micro-Projects:(Cost $21.55 M) Component 3: Project Coordination and Monitoring & Evaluation:(Cost $5.50 M) Component 4: Delivery of education and health services (new component):(Cost $9.00 M) Component 6: Pilot cash transfer program:(Cost $1.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory 3/10/2018 Public Disclosure Copy Page 1 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions The implementation of the Pilot cash transfer program has been slower than anticipated. The delays stem from challenges with the targeting methodology used to select beneficiaries and the design and implementation of the impact evaluation. These challenges have now been overcome, a targeting methodology has been adopted and the first transfers to about 400 families are expected to take place by mid-March 2018. 3/10/2018 Public Disclosure Copy Page 2 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Substantial  Substantial Macroeconomic  --  Substantial  Substantial Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Substantial  Substantial Fiduciary  --  Moderate  Moderate Environment and Social  --  Low  Moderate Stakeholders  --  Low  Low Other  --  --  -- Overall  --  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 88,113.00 119,626.00 137,000.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 Comments 110,389 are Micro-Project beneficiaries (including the projection of 960 enrolled students of 12 newly received classrooms); the remaining 9,237 are teachers and health workers whose salaries during January to June 2014 were paid for projects (7,308 and 1,929 respectively). PHINDPDOTBL  Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 3/10/2018 Public Disclosure Copy Page 3 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Value 0.00 48.50 49.21 50.00 PHINDPDOTBL  Number of people in rural areas provided with access to Improved Water Sources under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 58,447.00 69,990.00 100,000.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDPDOTBL  Students enrolled in classrooms built/rehabilitated by the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 11,029.00 12,346.00 20,000.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 Comments Including the projection of students enrolled in 12 newly received classrooms (4 schools), corresponding in two rounds to 960 students. PHINDPDOTBL  People with access to an all-season road build/rehabilitated by the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 11,250.00 33,998.00 73,000.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDPDOTBL  Beneficiaries from hydro-agricultural systems improved by the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 3/10/2018 Public Disclosure Copy Page 4 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Value 0.00 3,786.00 3,786.00 3,800.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDPDOTBL No interruption of the 2013/14 or 2014/15 school year due to the non payment of current salaries from Project effectiveness until the end of the 2014/15 school year with gradations (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Highly Value Non available -- Highly Satisfactory Satisfactory Date 07-May-2014 31-Dec-2015 30-Jun-2015 30-Jun-2015 Overall Comments This activity was completed by end-June 2015. Teachers were on strike for only 2 days (May 15–16, 2014) from the effectiveness of the first Additional Financing (when this activity was introduced) until the end of the 2013/14 school year. Intermediate Results Indicators PHINDIRITBL  Community-Development Plans completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 140.00 202.00 180.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Tabancas with a Community-Development Plans completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 708.00 1,018.00 850.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 3/10/2018 Public Disclosure Copy Page 5 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) PHINDIRITBL  Population with a Community-Development Plans completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 167,244.00 248,015.00 200,000.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Community-based sub-projects initiated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 252.00 311.00 355.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Community-based sub-projects completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 247.00 293.00 355.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Community-based sub-projects functional and properly maintained two years after completion (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.10 88.40 90.00 75.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 Comments 223 Community Micro-Projects completed two years ago or more, 23 water points are malfunctioning. 3/10/2018 Public Disclosure Copy Page 6 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) PHINDIRITBL  Improved community water points constructed or rehabilitated under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 187.00 219.00 270.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 34.50 129.07 230.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Additional classrooms built or rehabilitated at the primary level resulting from project interventions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 150.00 165.00 275.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Land benefiting from hydro-agricultural systems improved by the Project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 635.00 635.00 659.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 3/10/2018 Public Disclosure Copy Page 7 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) PHINDIRITBL  Operating ratio (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.10 18.00 17.00 20.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Technical audit of community-based sub-projects completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 3.00 Date 04-Aug-2009 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Percentage of teachers on the Folha Única whose salary has been paid by the Project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 90.00 Date 12-Feb-2014 30-Sep-2015 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Percentage of health workers on the Folha Única whose salary has been paid by the Project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 90.00 Date 12-Feb-2014 31-Dec-2015 30-Sep-2017 20-Sep-2019 3/10/2018 Public Disclosure Copy Page 8 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) PHINDIRITBL  Number of community health agents who receive training on Ebola prevention (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 346.00 346.00 1,000.00 Date 31-Aug-2014 31-Dec-2015 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Beneficiaries of social safety net programs (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 11-Jul-2016 30-Sep-2016 30-Sep-2016 20-Sep-2019 PHINDIRITBL  Beneficiaries of Safety Nets programs - Female (number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,000.00 Date 11-Jul-2016 30-Sep-2016 30-Sep-2017 20-Sep-2019 PHINDIRITBL  Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 11-Jul-2016 31-Dec-2015 30-Sep-2017 20-Sep-2019 Overall Comments 3/10/2018 Public Disclosure Copy Page 9 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P090712 IDA-D1160 Effective USD 10.00 10.00 0.00 2.81 7.71 27% P090712 IDA-H5130 Closed USD 5.00 5.00 0.00 5.06 0.00 100% P090712 IDA-H9080 Closed USD 15.00 15.00 0.00 14.62 0.03 100% P117861 TF-94746 Closed USD 5.00 5.00 0.00 5.00 0.00 100% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P090712 IDA-D1160 Effective 10-May-2016 11-May-2016 11-Jul-2016 20-Sep-2019 20-Sep-2019 P090712 IDA-H5130 Closed 24-Sep-2009 08-Oct-2009 07-Jul-2010 31-Dec-2014 31-Dec-2017 P090712 IDA-H9080 Closed 07-Feb-2014 03-Apr-2014 07-May-2014 31-Dec-2017 31-Dec-2017 P117861 TF-94746 Closed 20-Jul-2009 04-Aug-2009 04-Aug-2009 31-Aug-2013 30-Jun-2015 Cumulative Disbursements 3/10/2018 Public Disclosure Copy Page 10 of 11 Public Disclosure Copy The World Bank Implementation Status & Results Report Rural Community-Driven Development Project (P090712) Restructuring History Level Approved on 05-Apr-2011 ,Level 2 Approved on 06-Nov-2014 Related Project(s) P117861-Participatory Rural Development Project ,P146746-Rural Community-Driven Development Project Add Fin ,P151443-Second Add. Fin. to Rural Community-Driven Development Project 3/10/2018 Public Disclosure Copy Page 11 of 11