Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 11, 2010]: Revision of Updated Procurement Plan, February 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: 18 months after effectiveness II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P106975 08/25/2014 issued by PEEDU 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank (Prior / Post) July 9, 2010 US$ Prefere million nce (yes/no) Summary of the ICB (Works) Summary of 65 11 No Prior the ICB (Goods) Summary of 4.7 1 No Post the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 2.4 3 Prior number of contracts that will be let under QCBS July 9, 2010 Summary of 0. 3 3 Post CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Congo, Republic of : Rep. of Congo - Water, Electricity & Urban Development SIL (LEN) PLAN General Information Country: Congo, Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-07-27 2020-01-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P106975 GPN Date: Project Name: Rep. of Congo - Water, Electricity & Urban Development SIL (LEN) Loan / Credit No: IBRD / 84450, IDA / 55410, IDA / 47010 Executing Agency(ies): CG-Water, Electricity and Urban Developement WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-33-T-SED / REPARATION DES DEGATS Passation de ENVIRONNEMENTAUX Urban Infrastructure and IDA / 47010 A posteriori marché de gré à Direct 170,000.00 142,375.79 Achevé 2018-12-05 2018-12-10 2019-01-14 2019-07-13 SUR LA PROPRIETE DE Services gré LA FAMILLE BOLAMIGNELE GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-001-F-AOI-17 / Fournitures 50 postes et lignes - Fournitures et construction de 50 postes Electricity Sector Reform, Open - Single Stage - One de transformation électriques IBRD / 84450 Commercial and Electricity A priori Appel d'offres 14,250,000.00 0.00 Annulé 2017-10-19 2017-10-24 2017-12-05 2018-01-04 2018-02-08 2019-02-08 International Envelope MT/BT et lignes MT Supply Systems Upgrade. associées du réseau électrique à BZV et PNR (2 lots) CG-PEEDU-007-F-AOI / Réhabilitation 40 postes- Electricity Sector Reform, Open - Single Stage - One Fournitures réhabilitation de IBRD / 84450 Commercial and Electricity A priori Appel d'offres 1,800,000.00 11,187,608.93 Signé 2017-02-09 2017-02-14 2017-03-28 2017-08-10 2017-12-29 2018-11-24 International Envelope 40 postes et lignes MT/BT Supply Systems Upgrade. Bzv et Pnr CG-PEEDU-22-F-AON / Acquisition d'un véhicule Electricity Sector Reform, laboratoire et de deux Single Stage - One IBRD / 84450 Commercial and Electricity A posteriori Appel d'offres Open - National 515,130.00 0.00 Annulé 2018-04-26 2018-05-01 2018-06-12 2018-07-12 2018-08-16 2019-02-12 valises de détection des Envelope Supply Systems Upgrade. défauts pour la société nationale d'électricité (SNE) CG-PEEDU-23-F-AON / Acquisition des équipements médicaux des centres de Urban Infrastructure and Single Stage - One IDA / 47010 A posteriori Appel d'offres Open - National 500,000.00 274,706.17 Achevé 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 santé intégrés (Indzouli à Services Envelope Brazzaville, Siafoumou et Saint Joseph à Pointe-Noire) Page 1 CG-PEEDU-026-F-AOI / FOURNITURE ET TRAVAUX DE Electricity Sector Reform, CONSTRUCTION DE 20 Open - Single Stage - One IBRD / 84450 Commercial and Electricity A priori Appel d'offres 5,580,000.00 5,056,039.10 Signé 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-09-04 NOUVEAUX POSTES DE International Envelope Supply Systems Upgrade. TRANSFORMATION ÉLECTRIQUE MT/BT ET LIGNES A BRAZZAVILLE CG-PEEDU-029-F-AOI / Spé cifications techniques :  Véhicule la localisatio n de défauts sur câbles MT/ BT souterrains Electricity Sector Reform, Single Stage - One  2 valises la localisatio IBRD / 84450 Commercial and Electricity A posteriori Demande de prix Limited 650,000.00 522,838.32 Achevé 2018-07-29 2018-09-23 2019-03-22 Envelope n de défauts sur câbles MT/ Supply Systems Upgrade. BT souterrains - Camions laboratoire de recherche de défaut électriqu e - Accessibles à tous endr oits. CG-PEEDU-31-F-SED / Electricity Sector Reform, Passation de MISE A JOUR TOM2 PRO IBRD / 84450 Commercial and Electricity A posteriori marché de gré à Direct 16,000.00 13,432.06 Achevé 2018-09-13 2018-09-18 2018-10-23 2019-04-21 VERSION 2 Supply Systems Upgrade. gré CG-PEEDU-34-T-SED / ENTENTE DIRECTE AVEC LE BCBTP POUR LES TRAVAUX DE GENIE CIVIL EQUIPEMENT Passation de HYDROMECANIQUE ET IDA / 47010 Urban Water Supply A posteriori marché de gré à Direct 500,000.00 765,749.03 Signé 2019-02-08 2019-02-13 2019-03-20 2019-09-16 ELECTRIQUE DES gré FORAGES FP1 TCHIMAGNI ET FP2 KM8 LOUSSALA POUR LA SNDE A POINTE- NOIRE CG-PEEDU-41-F-ED / acquisition du matériel de réserve pour le Electricity Sector Reform, Passation de fonctionnement des 9 feeders En attente IBRD / 84450 Commercial and Electricity A posteriori marché de gré à Direct 488,470.00 0.00 2020-01-30 2020-02-04 2020-03-10 2020-09-06 souterrains 20 KV construits d'exécution Supply Systems Upgrade. gré à Pointe Noire au titre du PEEDU à partir du poste source MGK1 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-003 BIS-C- SFQC / Supervision 16 feeders et 40 postes - Firme pour contrôle et supervision Electricity Sector Reform, Sélection fondée Open - des fournitures et travaux IBRD / 84450 Commercial and Electricity A priori sur la qualité et 1,376,973.00 1,318,640.75 Signé 2015-04-11 2015-11-26 2016-07-26 2017-05-03 2017-05-25 2017-06-19 2017-07-19 2018-12-11 International de construction de 16 Supply Systems Upgrade. le coût feeders souterrains et Réhabilitation de 40 postes et lignes MT-BT à BZV et PNR Page 2 CG-PEEDU-008 BIS-C-QC / Sélection fondée Electricity Sector Reform, Enquête Satisfaction SNE - sur les Open - IBRD / 84450 Commercial and Electricity A posteriori 160,000.00 165,909.46 Achevé 2017-05-04 2017-05-17 2017-07-17 2017-09-06 2017-09-08 2017-12-07 Enquête de satisfaction de qualifications des International Supply Systems Upgrade. base de la clientèle SNE consultants CG-PEEDU-29275-CS-CQS / Réalisation d'une notice Sélection fondée d'impact environnemental et Urban Infrastructure and sur les Open - IBRD / 84450 A priori 300,000.00 204,477.74 Achevé 2017-02-23 2017-03-16 2017-04-29 2017-05-29 2017-07-03 2017-12-30 social (NIES) pour la Services qualifications des International construction de 7 feeders à consultants Brazzaville CG-PEEDU-003-C-SFQC-17 / Supervision 16 feeders et 40 postes - Firme pour contrôle et supervision des Electricity Sector Reform, Sélection fondée fournitures et travaux de Open - IBRD / 84450 Commercial and Electricity A priori sur la qualité et 1,376,973.00 0.00 Annulé 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-11-26 2017-12-31 2018-02-04 2019-02-04 construction de 16 feeders International Supply Systems Upgrade. le coût souterrains et Réhabilitation de 40 postes et lignes MT-BT à BZV et PNR CG-PEEDU-008-C-QC / Sélection fondée Electricity Sector Reform, Enquête Satisfaction SNE - sur les Open - IBRD / 84450 Commercial and Electricity A posteriori 160,000.00 0.00 Annulé 2017-05-04 2017-07-12 2017-09-04 2017-10-04 2017-11-09 2018-05-08 Enquête de satisfaction de qualifications des International Supply Systems Upgrade. base de la clientèle SNE consultants CG-PEEDU-003-BIS-C-SFQC / Supervision 16 feeders et 40 postes-Supervision et Electricity Sector Reform, Sélection fondée Contrôle des fournitures et Open - IBRD / 84450 Commercial and Electricity A priori sur la qualité et 500,000.00 0.00 Annulé 2015-12-17 2016-01-16 2016-08-13 2016-12-11 2017-06-07 2017-07-12 2017-08-16 2018-08-16 construction de 16 feeders International Supply Systems Upgrade. le coût etvréhabilitation de 40 postes et lignes MB/BT à BZV et PNR CG-PEEDU-002-C-SFQC-17 / supervision 50 postes et lignes - Contrôle et Electricity Sector Reform, Sélection fondée supervision des travaux de Open - IBRD / 84450 Commercial and Electricity A priori sur la qualité et 855,000.00 0.00 Annulé 2017-10-27 2017-11-17 2017-12-31 2018-01-28 2018-02-27 2018-04-03 2018-05-08 2019-06-07 50 postes de transformation International Supply Systems Upgrade. le coût électriques MT/BT et lignes MT associées du réseau électrique à BZV et PNR CG-PEEDU-016-C-QC-18 / Notice d'impact Sélection fondée Electricity Sector Reform, environnemental et social sur les Open - IBRD / 84450 Commercial and Electricity A posteriori 166,368.00 0.00 Annulé 2014-12-31 2015-12-31 2016-12-23 2017-02-15 2017-04-07 2017-10-04 (NIES) pour la construction qualifications des International Supply Systems Upgrade. de neuf feeders souterrains consultants 20 kV à Pointe Noire CG-PEEDU-004-C-SFQC / Assistance comptable SNDE Sélection fondée Open - - Assistance technique IBRD / 84450 Urban Water Supply A posteriori sur la qualité et 396,000.00 0.00 Annulé 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 International financière et comptable le coût auprès de la SNDE CG-PEEDU-005-C-SMC / Sélection au Open - Patrimoine SNDE - Audit IBRD / 84450 Urban Water Supply A priori 600,000.00 0.00 Annulé 2017-04-21 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2018-08-09 moindre coût International du patrimoine de la SNDE CG-PEEDU-006-C-SMC / Electricity Sector Reform, Sélection au Open - Patrimoine SNE-Audit du IBRD / 84450 Commercial and Electricity A priori 700,000.00 0.00 Annulé 2017-04-21 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2018-08-09 moindre coût International patrimoine de la SNE Supply Systems Upgrade. Page 3 CG-PEEDU-20-CS-SFQC / Inventaire physique des immobilisations et Sélection fondée Open - présentation d'une situation IBRD / 84450 Urban Water Supply A priori sur la qualité et 1,000,000.00 408,317.92 Signé 2018-03-28 2018-04-18 2018-06-01 2018-06-29 2018-07-29 2018-09-02 2018-10-07 2019-10-07 International bilancielle auditée et corrigée le coût de la SNDE au 31 décembre 2017 CG-PEEDU-21-CS-SFQC / Inventaire physique des immobilisations et Electricity Sector Reform, Sélection fondée Open - présentation d'une situation IBRD / 84450 Commercial and Electricity A priori sur la qualité et 1,000,000.00 437,610.60 Signé 2018-03-28 2018-04-18 2018-06-01 2018-06-29 2018-07-29 2018-09-02 2018-10-07 2019-10-07 International bilancielle auditée et corrigée Supply Systems Upgrade. le coût de la SNE au 31 décembre 2017 CG-PEEDU-24-CS-SFQC / Elaboration du fichier des Sélection fondée Open - abonnés de la société IBRD / 84450 Urban Water Supply A priori sur la qualité et 800,000.00 963,273.50 Signé 2018-05-10 2018-05-31 2018-07-14 2018-08-11 2018-09-10 2018-10-15 2018-11-19 2019-11-19 International nationale de distribution le coût d'eau (SNDE) CG-PEEDU-027-C-SFQC / CONTRÔLE ET SUPERVISION DES FOURNITURES ET Electricity Sector Reform, Sélection fondée TRAVAUX DE Open - En cours IBRD / 84450 Commercial and Electricity A posteriori sur la qualité et 420,000.00 248,043.99 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-12-24 CONSTRUCTION DE 20 International d'examen Supply Systems Upgrade. le coût NOUVEAUX POSTES DE TRANSFORMATION ÉLECTRIQUE MT/BT ET LIGNES A BRAZZAVILLE CG-PEEDU-30-CS-SFQC / ELABORATION DU Sélection fondée MODELE ECONOMIQUE Open - IBRD / 84450 Urban Water Supply A posteriori sur la qualité et 300,000.00 128,556.90 Signé 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-22 2019-03-29 2020-03-28 ET FINANCIER DU International le coût SECTEUR DE L HYDRAULIQUE URBAINE CG-PEEDU-32-CS-SFQC / APPUI A LA REFORME Electricity Sector Reform, Sélection fondée Open - DU SECTEUR DE IBRD / 84450 Commercial and Electricity A priori sur la qualité et 700,000.00 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-27 2019-01-26 2019-03-02 2019-04-06 2020-04-05 International L'ELECTRICITE AU Supply Systems Upgrade. le coût CONGO CG-PEEDU-004-C-QC-17 / NIES 7 feeders Bzv - Sélection fondée Réalisation d'une notice Electricity Sector Reform, sur les Open - d'impact environnemental et IBRD / 84450 Commercial and Electricity A priori 300,000.00 0.00 Annulé 2016-02-23 2016-03-15 2016-04-28 2016-05-28 2017-08-03 2017-11-01 qualifications des International social (NIES) pour la Supply Systems Upgrade. consultants construction de 7 feeders à Brazzaville CG-PEEDU-35-SFQC / Recrutement d’une firme chargée du renforcement des capacités du personnel des acteurs institutionnels du Electricity Sector Reform, Sélection fondée Open - En cours secteur de l’électricité ( IBRD / 84450 Commercial and Electricity A priori sur la qualité et 527,380.00 0.00 2019-07-16 2019-08-06 2019-09-19 2019-10-17 2019-11-16 2019-12-21 2020-01-25 2021-01-24 International d'examen (direction générale de Supply Systems Upgrade. le coût l’Energie, agence de régulation du secteur de l’électricité, agence nationale de l’électricité ---) CG-PEEDU-36-SFQC / Recrutement d’une firme Electricity Sector Reform, Sélection fondée Open - En cours chargée de l’élaboration des IBRD / 84450 Commercial and Electricity A posteriori sur la qualité et 400,000.00 0.00 2019-07-22 2019-08-12 2019-09-25 2019-10-23 2019-11-22 2019-12-27 2020-01-31 2021-01-30 International d'exécution codes réseaux du système Supply Systems Upgrade. le coût électrique congolais Page 4 CG-PEEDU-37-QC / Recrutement d’une firme chargée de cartographie des Sélection fondée auto producteurs d’eau et sur les Open - En cours IBRD / 84450 Urban Water Supply A posteriori 150,000.00 0.00 2019-06-27 2019-07-18 2019-08-31 2019-09-30 2019-11-04 2020-05-02 mise en place d’un système qualifications des International d'exécution de suivi et contrôle de leur consultants activité dans la ville de pointe noire CG-PEEDU-38-CS-SMC / 1. Recrutement d’une firme Electricity Sector Reform, Sélection fondée chargée de la realisation des Open - En cours IBRD / 84450 Commercial and Electricity A posteriori sur la qualité et 48,000.00 0.00 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2021-02-20 audits externes financiers et International d'exécution Supply Systems Upgrade. le coût comptables, exercices 2019 et 2020 du peedu INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-013-C-CI / Recrutement d'un assistant Electricity Sector Reform, en passation des marchés au IDA / 55410 Commercial and Electricity A posteriori Individuel Open 30,000.00 2,203.08 Achevé 2018-01-18 2018-03-08 2018-03-29 2018-05-03 2018-10-30 sein de l'unité de Supply Systems Upgrade. coordination du PEEDU. CG-PEEDU-010-C-CI / Etude technique et dossiers d'appels d'offres pour la Electricity Sector Reform, fourniture et l'installation du IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 100,000.00 0.00 Annulé 2018-02-05 2018-03-26 2018-04-16 2018-05-21 2018-11-17 programme de protection des Supply Systems Upgrade. revenus à la SNE, supervision et contrôle de la mise en oeuvre du PPR. CG-PEEDU-015-C-ED-18 / Prestations additionnelles à Electricity Sector Reform, Sélection de l'étude de la demande et de IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 100,928.00 8,922,731.60 Signé 2015-11-10 2015-11-20 2016-01-24 2016-07-22 la tarification de l'électricité Supply Systems Upgrade. entente directe au Congo CG-PEEDU-013-C-ED-18 / NIES 25 postes BZV- Notice d'Impact Electricity Sector Reform, Sélection de Environnemental et Social IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 85,400.00 82,143.25 Signé 2017-10-25 2017-11-07 2017-11-10 2018-02-28 pour réhabilitation de 25 Supply Systems Upgrade. entente directe postes et construction de 30 nouveaux postes de transformation à Brazzaville CG-PEEDU-014-C-ED-18 / PAR 25 postes-BZV- Plan d'Action et de Réinstallation Electricity Sector Reform, pour la construction de 30 IBRD / 84450 Commercial and Electricity A posteriori Individuel Direct 88,900.00 83,670.90 Achevé 2017-10-25 2017-11-04 2017-11-09 2017-11-10 2018-05-09 postes de transformation et Supply Systems Upgrade. la réhabilitation de 25 postes à brazzaville CG-PEEDU-011-C-CI / Consultant pour l'élaboration Electricity Sector Reform, des TDR et dossiers d'appel IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 100,000.00 0.00 Annulé 2018-04-27 2018-06-15 2018-07-06 2018-08-10 2019-02-06 d'offres pour la mise en Supply Systems Upgrade. oeuvre des diligences pour la réforme du secteur de l'eau. Page 5 CG-PEEDU-012-C-CI / Consultant pour l'élaboration des TDR et dossiers d'appel Electricity Sector Reform, d'offres pour la mise en IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 100,000.00 0.00 Annulé 2018-04-27 2018-06-15 2018-07-06 2018-08-10 2019-02-06 oeuvre des diligences pour la Supply Systems Upgrade. réforme du secteur de l'électricité CG-PEEDU-025-C-SED / Consultant individuel chargé d'appuyer la mise en place Electricity Sector Reform, d'un programme de IBRD / 84450 Commercial and Electricity A posteriori Individuel Direct 100,000.00 79,860.00 Résilié 2018-04-23 2018-05-03 2018-05-24 2018-06-28 2018-12-25 protection de revenus (PPR) Supply Systems Upgrade. au sein de la Société Nationale d'Electricité (SNE) CG-PEEDU-39-CS-INDV / Electricity Sector Reform, En attente Cartographie des activités IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 14,000.00 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2020-12-01 d'exécution réalisées par le PEEDU Supply Systems Upgrade. CG-PEEDU-43-CS-IND / Electricity Sector Reform, Recrutement du consultant En attente IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 48,000.00 0.00 2020-03-10 2020-04-28 2020-05-19 2020-06-23 2020-12-20 pour élaborer le rapport d'exécution Supply Systems Upgrade. d'achèvement du PEEDU CG-PEEDU-40-CS-ED / Notice d'impact Electricity Sector Reform, Sélection de environnement et social des En attente IDA / 55410 Commercial and Electricity A posteriori consultants par Direct 70,000.00 0.00 2020-01-20 2020-01-30 2020-04-04 2020-10-01 liaisons des 20 nouveaux d'exécution Supply Systems Upgrade. entente directe postes de transformation électrique à Brazzaville Page 6