75357 THE KYRGYZ REPUBLIC Rural Water Supply and Sanitation Project-2 PROCUREMENT PLAN - for August 19 2009 - 31 May, 2013 PROCUREMENT PLAN - Tresholds (Date of PP: 7 December 2011; Update No#1; Date of WB NOL: 13.12.2011) (Date of PP: 23 May 2012; Update No#2; Date of WB NOL: 23.08.2012) (Date of PP: 23 August 2012; Update No#3; Date of WB NOL: 24.08.2012) (Date of PP: 06 February 2013; Update No#5; Date of WB NOL: ) Expenditure Contract Value Procurement Method Contracts Subjects to Prior Review (US$) Category Threshold (US$) >=100,000 ICB All ICB contracts Goods <100,000 Shopping First Shopping contract NA DC All DC contracts <1 000 000 NCB First 2 NCB contracts Works <100,000 Shopping First Shopping contract NA DC All DC contracts >=200,000 QCBS/QBS/LCS/FBS a/ b/ Consultant Services <200,000 CQS >=100,000 for firms; all SSS contracts; all TORs (including training) NA SSS NA IC >=50,000 for individuals; all SSS contracts; all TORs ICB – International Competitive Bidding NCB – National Competitive Bidding DC – Direct Contracting QCBS – Quality and Cost Based Selection QBS – Quality Based Selection LCS – Least Cost Selection FBS – Fixed Budget Selection CQS – Selection Based on Consultants’ Qualifications SSS – Single Source Selection IC – Individual Consultants THE KYRGYZ REPUBLIC Rural Water Supply and Sanitation Project-2 PROCUREMENT PLAN - for August 19 2009 - 31 May, 2013 PROCUREMENT PLAN - Summary (Date of PP: 7 December 2011; Update No#1; Date of WB NOL: 13.12.2011) (Date of PP: 23 May 2012; Update No#2; Date of WB NOL: 23.08.2012) (Date of PP: 23 August 2012; Update No#3; Date of WB NOL: 24.08.2012) (Date of PP: 06 February 2013; Update No#5; Date of WB NOL: ) Grant agreement (US $) â„– Description IDA 1 WORKS 9,170,937 2 GOODS 499,000 3 Consulting Services 2,048,522 4 Trainings 340,000 5 ADDITIONAL PROJECT COSTS (OPERATIONAL EXPENSES) - 1,859,348 Total 13,917,807 THE KYRGYZ REPUBLIC Rural Water Supply and Sanitation PROCUREMENT PLAN - for August PROCUREMENT PLAN - GOODS and WORKS (Date of PP: 7 December 2011; Update No#1; Date of WB NOL: 13.12.2011) (Date of PP: 23 May 2012; Update No#2; Date of WB NOL: 23.08.2012) (Date of PP: 23 August 2012; Update No#3; Date of WB NOL: 24.08.2012) (Date of PP: 06 February 2013; Update No#5; Compon WB WB No- Cost Date of WB No- Date of Bid Date of Date of ent Plan vs Procu. Review Date of Bid objection to Item â„– Table Contract Ref. â„– Contract Description Draft BD objection Invitation Evaluation Contract Contract Remarks Referenc Actual Method (Prior/ Opening Contract Codes to WB to BD to Bids Report Signing Completion e as per Post) Award GOODS/ТОВÐ?РЫ Plan Shopping Post 4/7/2009 n/a 4/14/2009 4/28/2009 5/4/2009 n/a 5/8/2009 5/22/2009 RWSSP-2/Furniture-1 Office furniture 1 Actual Shopping Post 1/26/2010 n/a 1/26/2010 2/10/2010 2/27/2010 n/a 3/15/2010 4/14/2010 ОÑ?ОО "Кабинет" Plan Shopping Prior 4/7/2009 4/13/2009 4/14/2009 4/28/2009 5/4/2009 5/11/2009 5/12/2009 5/25/2009 RWSSP-2/Shopping01/2010 Office equipment 2 Actual Shopping Prior 12/23/2009 1/11/2010 1/14/2010 1/28/2010 6/10/2010 6/16/2010 6/21/2010 7/19/2010 ОÑ?ОО "Ermex Group" Plan/План ICB Prior 2/29/2012 3/14/2012 3/28/2012 5/12/2012 6/26/2012 7/10/2012 8/7/2012 11/5/2012 Supply of maintenance equipment 3 A2 IDA-RWSSP-G-2011-1 (multiple contracts) Actual/Факт ICB Prior Plan/План Shopping Post n/a n/a 2/28/2013 3/14/2013 4/13/2013 n/a 4/27/2013 7/26/2013 Supply of computer equipment and 4 A2 IDA-RWSSP-G-2011-2 data base Actual/Факт Shopping Post WORKS Plan/План Rehabilitation of water supply system NCB Prior 8/25/2008 9/8/2008 9/22/2008 10/22/2008 11/21/2008 12/5/2008 1/2/2009 7/1/2010 1 A1 RWSSP-2/WNCB/IK5-2-09 JSC "Yug-Stroiservis" in Korumdu. Actual/Факт NCB Prior 3/19/2011 3/28/2011 4/1/2011 4/29/2011 6/2/2011 6/9/2011 6/23/2011 Rehabilitation of water supply system Plan/План Lot#1-Consortium:"FMU- NCB Prior n/a n/a 8/19/2011 9/19/2011 10/19/2011 10/26/2011 11/16/2011 11/15/2012 2 A1 IDA-RWSSP-CW-2011-1 in Temir&Kashat villages, Issyk-Kul 1"Ltd.&"Bior"Ltd.; Lot#2- oblast Actual/Факт "Minur"Ltd. NCB Prior 8/25/2011 8/29/2011 8/19/2011 9/19/2011 10/28/2011 12/12/2011 12/29/2011 Plan/План Rehabilitation of water supply system ICB Prior 3/7/2012 4/13/2012 4/20/2012 6/4/2012 8/3/2012 8/17/2012 8/24/2012 11/22/2013 Consortium:JSC"Yug- 3 A1 IDA-RWSSP-CW-2011-2 in Chelpek. Stroiservis"+JSC"Usta" Actual/Факт ICB Prior 3/7/2012 4/13/2012 4/20/2012 6/4/2012 6/28/2012 7/6/2012 8/3/2012 Plan/План Consortium: JSC "Talas- Rehabilitation of water supply system NCB Post n/a n/a 12/29/2011 1/28/2012 2/27/2012 n/a 3/19/2012 3/19/2013 4 A1 IDA-RWSSP-CW-2011-3 MSPMK"+ JSC"MPMK- in Uch-Emchek Actual/Факт NCB Post n/a n/a 1/6/2012 2/7/2012 2/22/2012 n/a 3/22/2012 Talas"+ JSC "Jolchu" Plan/План NCB Post n/a n/a 12/16/2011 1/15/2012 2/14/2012 n/a 3/6/2012 3/6/2013 Rehabilitation of water supply system Consortium:KSK+EMG- 5 A1 IDA-RWSSP-CW-2011-4 in Tugol-Sai Story Actual/Факт NCB Post n/a n/a 12/2/2011 1/16/2012 4/20/2012 n/a 5/18/2012 Ak-Kochkor - work includes drilling Plan/План of well (100 m depth), construction of NCB Post n/a n/a 10/30/2011 11/30/2011 12/30/2011 n/a 1/20/2012 1/19/2013 Consortium: 6 A1 IDA-RWSSP-CW-2011-5 150 m3 tank, laying of 800 lm trunk JSC"Remservis"&"MNK" main and distribution system Actual/Факт NCB Post n/a n/a 10/28/2011 11/29/2011 12/13/2011 n/a 1/10/2012 Plan/План Rehabilitation of water supply system NCB Post n/a n/a 10/30/2011 11/30/2011 12/30/2011 n/a 1/20/2012 1/19/2013 "Minur"Ltd. 7 A1 IDA-RWSSP-CW-2011-6 in Jele-Dobo v. Actual/Факт NCB Post n/a n/a 10/28/2011 11/29/2011 12/13/2011 n/a 12/29/2011 Plan/План Rehabilitation of water supply system NCB Post n/a n/a 10/30/2011 11/30/2011 12/30/2011 n/a 1/20/2012 1/19/2013 8 A1 IDA-RWSSP-CW-2011-7 JSC "Yug-Stroiservis" in Baltabai v. Actual/Факт NCB Post n/a n/a 10/28/2011 11/29/2011 12/13/2011 n/a 12/29/2011 Plan/План NCB Post n/a n/a 12/16/2011 6/1/2012 7/1/2012 n/a 7/22/2012 10/20/2013 Consotium: Rehabilitation of water supply system 9 A1 IDA-RWSSP-CW-2011-8 in Koochu v. "Enesai"Ltd.+"Alex Stroi" Actual/Факт NCB Post n/a n/a 5/4/2012 6/1/2012 6/21/2012 n/a 7/26/2012 Plan/План Construction of demo sanitation Shopping Post n/a n/a 5/17/2013 6/7/2013 7/7/2013 n/a 7/21/2013 1/17/2014 10 A1 IDA-RWSSP-SH-2011-1 facilities (multiple contracts) Actual/Факт Shopping Post n/a n/a Rehabilitation of 15 remaining Plan/План 11 A1 IDA-RWSSP-CW-2011-9 problem subprojects out of 26 Shopping Post n/a n/a 1/14/2013 2/4/2013 3/6/2013 n/a 3/20/2013 9/16/2013 subprojects (multiple contracts) Actual/Факт Shopping Post n/a n/a Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 Rehabilitation of rural water supply in 12 A1 RWSSP-W-Shopping-12-1 "Minur"Ltd. Ak-Olon village, Issy-Kul oblast Actual/Факт Shopping Post n/a n/a 8/27/2012 9/10/2012 9/10/2012 n/a 9/11/2012 Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 13 A1 RWSSP-W-Shopping-12-2 JSC "Yug-stroyservis" Chon-Tash village, Issy-Kul oblast Actual/Факт Shopping Post n/a n/a 8/27/2012 9/10/2012 9/10/2012 n/a 9/11/2012 Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 14 A1 RWSSP-W-Shopping-12-3 Orgochor village, Issy-Kul oblast Actual/Факт Shopping Post n/a n/a 8/27/2012 9/10/2012 9/10/2012 n/a 9/11/2012 JSC "Yug-stroyservis" Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 15 A1 RWSSP-W-Shopping-12-4 Archa-Gul village, Talas oblast Actual/Факт Shopping Post n/a n/a 9/5/2012 9/19/2012 9/19/2012 n/a 9/20/2012 "Enesai"Ltd. Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 16 A1 RWSSP-W-Shopping-12-5 JSC"Kochkorsuukurulush" Terek village, Naryn oblast Actual/Факт Shopping Post n/a n/a 9/5/2012 9/19/2012 9/19/2012 n/a 9/20/2012 Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 17 A1 RWSSP-W-Shopping-12-6 Novo-Konstantinovka(Jergez) village, "Enesai"Ltd. Issyk-Kul oblast Actual/Факт Shopping Post n/a n/a 9/5/2012 9/19/2012 9/19/2012 n/a 9/20/2012 Rehabilitation of rural water supply in Plan/План Post n/a n/a 6/29/2012 7/20/2012 8/19/2012 n/a 9/2/2012 3/1/2013 18 A1 RWSSP-W-Shopping-12-8 JSC"Usta" Kara-Oi village, Talas oblast Actual/Факт Shopping Post n/a n/a 10/3/2012 10/17/2012 10/17/2012 n/a 10/19/2012 Rehabilitation of water supply system Plan/План JVS "Kochkorsuukurulush" 12 A1 IDA-RWSSP-CW-2011-9 NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/15/2013 6/14/2013 in v.Kara-Burgon Actual/Факт NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/16/2013 6/15/2013 Rehabilitation of water supply system Plan/План NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/15/2013 6/14/2013 JSC "Talas-MSPMK" 13 A1 IDA-RWSSP-CW-2011-10 in v.Kopuro-Bazar Actual/Факт NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/21/2013 5/29/1900 Rehabilitation of water supply system Plan/План NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/15/2013 6/14/2013 JSC "Talas-MSPMK" 14 A1 IDA-RWSSP-CW-2011-11 in v.Yntymak Actual/Факт NCB Post n/a n/a 11/6/2012 12/4/2012 12/18/2012 n/a 1/17/2013 6/16/2013 Rehabilitation of rural water supply in Plan/План n/a n/a 2/8/2013 3/11/2013 3/25/2013 n/a 4/22/2013 10/19/2013 15 A1 IDA-RWSSP-CW-2013-1 NCB Post Min-Bulak village, Talas oblast Actual/Факт Rehabilitation of rural water supply in Plan/План Suluu-Maimak village, Kuruu- n/a n/a 2/8/2013 3/11/2013 3/25/2013 n/a 4/22/2013 10/19/2013 16 A1 IDA-RWSSP-CW-2013-2 NCB Post Maimak village,Jon-Dobo village Talas oblast Actual/Факт Rehabilitation of rural water supply in Plan/План n/a n/a 2/8/2013 3/11/2013 3/25/2013 n/a 4/22/2013 10/19/2013 17 A1 IDA-RWSSP-CW-2013-3 NCB Post Bash-Kuugandy village, Naryn oblast Actual/Факт Sub Total TOTAL ** Items in grey are the contracts implemented by JPMU THE KYRGYZ REPUBLIC Rural Water Supply and Sanitation Project- PROCUREMENT PLAN - for August 19 PROCUREMENT PLAN - Consulting services (Date of PP: 7 December 2011; Update No#1; Date of WB NOL: 13.12.2011) (Date of PP: 23 May 2012; Update No#2; Date of WB NOL: 23.08.2012) (Date of PP: 23 August 2012; Update No#3; Date of WB NOL: 24.08.2012) (Date of PP: 06 February 2013; Update No#5; Date of WB NOL: ) WB Evaluation WB No- WB No- Component WB No- Request for RFP Date of Date of Firm or Select. Review report for objection to Proposal Draft Final objection Item â„– Reference as Contract Ref. Contract Description Plan vs Actual Draft TOR objection Exp. Of Issued Contract Contract Remarks Ind. Method (Prior/ Short list & RFP/ Short Submission Contract to Draft per PAD to TOR Interest (for CQS) Signing Completion Post) RFP list Contract Preparation of detailed design JSC for rural water supply systems Actual Firm 2/11/2009 6/30/2012 "Kyrgyzkommunproekt" RWSSP-2/TC-09 Kyrgyz sientific Company for optimization of Actual Firm 8/18/2010 10/20/2010 research designing standards seismic stability Social mobillization Actual Firm 11/28/2008 12/15/2009 Microcredit civil fund Individual consultants 1)E.Sadykov, (Procurement specialist, Actual Ind. SSS 7/14/2009 6/30/2010 2)U.Abdykalykova disbursement specialist, 3) G.Abdrahmanova procurement assistant) Plan Firm SSS Prior 7/13/2011 7/20/2011 n/a n/a n/a n/a 7/25/2011 8/8/2011 8/15/2011 8/22/2011 11/22/2011 1 A3 JSC KyrgyzGiproStroi Development of detailed design Review for Chelpek Actual Firm SSS 8/1/2011 8/1/2011 n/a n/a n/a n/a 8/1/2011 8/4/2011 8/4/2011 8/15/2011 11/15/2011 Plan Firm CQ 9/15/2011 11/15/2011 12/2/2011 12/16/2011 n/a 1/6/2012 1/20/2012 2/3/2012 n/a 2/3/2012 5/3/2012 Consultant for rectification of Post JSC KyrgyzGiproStroi Actual 12/2/2011 12/23/2011 n/a 12/26/2011 1/16/2011 2 A1 26 subprojects Firm CQ Review 9/15/2011 11/15/2011 1/26/2012 n/a 1/26/2012 Selection of technical Ind. IC 1/13/2012 1/27/2012 2/10/2012 3/2/2012 n/a n/a n/a 3/23/2012 n/a supervision engineers (multiple - Plan 3/23/2012 3/23/2013 A3 one engineer per subproject) (cost estimate for each individual is less USD Actual Ind. IC Post 3 50 000) Review Consultant for UN Firm 11/16/2011 11/23/2011 n/a n/a n/a n/a n/a 12/7/2011 12/21/2011 1/4/2012 B Hygiene&sanitation Standards Plan agencies 1/3/2013 UN Prior Promotion Actual Firm 11/16/2011 4 agencies Review Selection of ARIS staff: Ind. SSS 9/1/2011 9/15/2011 n/a n/a n/a n/a n/a 10/1/2011 10/1/2011 10/1/2011 1) A.Satybekov; Plan 5/30/2013 2)D.Temirbaeva 1) Deputy of Executive D Director/Coordinator of RWSSP-2; 2) Procurement Actual Ind. SSS 9/30/2011 9/30/2011 n/a n/a n/a n/a n/a 9/30/2011 9/30/2011 10/1/2011 Prior specialist; 5 Review 12/31/2011 Selection of ARIS staff Ind. IC 8/1/2011 8/15/2011 8/19/2011 9/9/2011 n/a n/a n/a 9/30/2011 n/a (individual) (cost estimete for Plan 9/30/2011 5/30/2013 each individual is less USD 50 Actual Ind. IC Post 8/19/2011 9/9/2011 n/a n/a n/a 10/10/2011 n/a 10/10/2011 12/31/2011 6 D 000)*** Review Plan Firm CQ 1/18/2013 2/1/2013 2/1/2012 2/15/2012 n/a 3/7/2012 3/28/2012 4/11/2012 n/a 4/11/2012 Development of web-site (GIS Prior 7 C system) Actual Firm CQ Review 1/15/1900 Plan Ind. IC 12/28/2011 1/11/2012 1/25/2012 2/8/2012 n/a n/a n/a 2/22/2012 n/a 2/22/2012 12/31/2012 Consultant on analysis of Post Actual 8/22/2012 9/3/2012 n/a n/a n/a 8 C legislation Ind. IC Review 8/16/2012 8/21/2012 9/3/2012 n/a 9/3/2012 Mahamadjan Iminov Plan Ind. IC 8/13/2012 8/27/2012 9/3/2012 9/17/2012 n/a n/a n/a 10/1/2012 n/a 10/1/2012 1/21/2013 Consultant on development of Prior Mr.Simon James Actual 9/3/2012 11/2/2012 n/a n/a n/a 9 C strategy on rural water supply Ind. IC Review 8/23/2012 11/13/2012 11/13/2012 11/19/2012 Gordon-Walker Preparartion of Detailed 5/8/2013 5/22/2013 6/5/2013 7/5/2013 n/a 7/19/2013 8/9/2013 8/23/2013 n/a 8/30/2013 11/28/2013 Plan Firm CQ Design for demo-sanitation Post facilities Actual Review Ind. IC Post 4/19/2012 4/20/2012 8/19/2011 4/27/2012 n/a n/a n/a 5/1/2012 n/a Safeguard specialist Plan 5/1/2012 5/1/2013 Review 12 Actual Ind. IC 4/19/2012 4/20/2012 8/19/2011 4/27/2012 n/a n/a n/a 5/1/2012 n/a 5/1/2012 5/1/2013 Kanybek Jumaliev Consultation services on Plan Firm CQ Post 4/16/2012 5/14/2012 5/15/2012 6/5/2012 n/a n/a 5/29/2012 6/12/2012 n/a 6/12/2012 6/12/2013 holding awareness campaign Actual Review 4/16/2012 5/14/2012 5/15/2012 6/29/2012 n/a n/a 7/5/2012 7/16/2012 n/a 13 7/16/2012 "PR Consult" Consultant for development of Ind. IC Post 1/20/2012 2/3/2012 2/17/2012 4/2/2012 n/a n/a n/a 4/16/2012 n/a 4/16/2012 1/15/2013 Plan training material Review training material Review 14 Actual Ind. IC 9/14/2012 10/10/2012 n/a n/a n/a 10/15/2012 n/a 10/15/2012 Elmira Ubysheva Plan Firm CQ Post 7/21/2013 8/4/2013 8/18/2013 10/2/2013 n/a 10/23/2013 11/13/2013 11/27/2013 n/a 11/27/2013 3/27/2014 C Impact Assesment 16 Actual Firm CQ Review Plan Firm LCS 11/22/2011 12/6/2011 12/23/2011 2/1/2012 2/15/2012 2/29/2012 3/21/2012 4/4/2012 4/18/2012 5/2/2012 8/30/2012 C Audit for 2012-2013* Prior 17 Actual Firm LCS Review 11/22/2011 12/2/2011 Plan Firm CQ 8/8/2011 8/31/2011 CJSC "Grant Thornton" Audit for RWSSP-2 Prior 18 Actual Firm CQ Review Plan Ind. SSS 12/6/2012 12/26/2012 n/a n/a n/a n/a n/a n/a n/a 1/1/2013 12/31/2013 Disbursement specialist**** Prior 19 D Actual Ind. SSS Review 12/6/2012 12/26/2012 n/a n/a n/a n/a n/a n/a n/a 1/1/2013 12/31/2013 Raxat Junushova Monitoring and Evaluation Plan Ind. SSS 12/6/2012 12/26/2012 n/a n/a n/a n/a n/a n/a n/a 1/1/2013 12/31/2013 Prior specialist Actual Ind. SSS 12/6/2012 12/26/2012 n/a n/a n/a n/a n/a n/a n/a 1/1/2013 20 D Review 12/31/2013 Ulan Baigonchokov TOR was agreed with Plan/План n/a n/a 11/01/13 28/01/13 n/a n/a n/a n/a n/a 01/02/13 31/12/13 WB August 9,2013 21 Lawyer**** Ind IC post review Actual/Факт D Sub total TOTAL: Annual audit will be made for the all WB funded projects implemented by ARIS and the total amount of contract will be divided accordingly ** Items in grey are the contracts implemented by JPMU ***The list of ARIS staff individuals is attached in separate ****Thise position including in Administrative pool Kyrgyz Republic Rural Water Supply and Sanitation Project-2 PROCUREMENT PLAN - Training Category August 19, 2009 - 31 May 2013 (Date of PP: 7 December 2011; Update No#1; Date of WB NOL: 13.12.2011) (Date of PP: 23 May 2012; Update No#2; Date of WB NOL: 23.08.2012) (Date of PP: 23 August 2012; Update No#3; Date of WB NOL: 24.08.2012) (Date of PP: 06 February 2013; Update No#5; Date of WB NOL: ) WB Evaluation WB No- WB No- Component WB No- Request for Date of Date of Cost Table Contract Contract Firm or Select. Review report for objection RFP Issued Proposal Draft Final objection Item â„– Reference as Plan vs Actual Draft TOR objection to Exp. Of Contract Contract Remarks Codes Ref. Description Ind. Method (Prior/ Short list & to RFP/ (for CQS) Submission Contract to Draft per PAD TOR Interest Signing Completion Post) RFP Short list Contract training and Planned/План n/a n/a Post n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a IDA- promotion (acivity 1 RWSSP-Tr- will be designated 1 Actual/Факт in future) TOTAL: RWSSP Staff Position A.Satybekov ARIS Deputy of executive director/Coordinator B.Doolotbaev Senior infrastructure engineer S.Viktorov Infrastructure engineer Ch.Chynaliev Institutional development specialist G.Amanalieva Sanitation and hygiene specialist K.Jumaliev Sageguard specialist A.Sultangaziev Infrastructure engineer B.Abdykadyrov Institutional development specialist for Talas oblast D.Aitkojoev Institutional development specialist for Issyk-Kul oblast O.Japarov Institutional development specialist for Naryn oblast D.Temirbaeva Senior procurement specialist Z.Ashirbekov Assistant of procurment specialist U.Baigoncokov M&E Specialist R.Junushova Disbursement specialist Lawyer