Procurement Plan Additional Financing for the Water Sector Capacity Building and Advisory Services Project (WCAP) I. General 1. Bank’s approval Date of the procurement Plan: January 6,2107 2. Date of General Procurement Notice: Aug 24, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year June 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Value Procurement Contracts Subject to Category (Threshold) Method Prior Review US $ US$ thousands 1. Goods Works & >600,000 ICB All Non-consulting <600,000 NCB First Contract and all subsequent contracts Services estimated to cost > 200,000 <100,000 Shopping First Contract Regardless of value Direct Contracting All 2. Consulting All TOR and Training Programs to be prior Services (Firms) reviewed by Association’s TTL regardless of value and review threshold >300,000 QCBS/QBS /FBS/LCS First contract ( remaining contracts > $ 500,000 shall be mandatorily post reviewed <300,000 CQS, First contract  25,000 Single Source Selection All First Contract only. Subsequent contracts shall have a technical sign-off of justification only on condition: (i) if it was provided in approved Procurement Plan ≤25,000 Single Source Selection and (ii) not representing a slice of an otherwise larger project and; shall be mandatorily post reviewed regardless of the sample of selected contracts Individual > 100,000 Comparison of 3 CVs First contract Consultants < 100,000 Comparison of 3 CVs First contract  10,000 Single Source Selection, Contracts All. for: procurement of Project Coordinator, Procurement/FM Specialists, Procurement Agent and Legal Expert (as applicable) All TOR to be technically reviewed by the Association July 9, 2010 First Contract only. Subsequent contracts shall have a technical sign-off of justification only on condition: (i) if it was provided in approved Procurement Plan ≤10,000 Single Source Selection and (ii) not representing a slice of an otherwise larger project and; shall be mandatorily post reviewed regardless of the sample of selected contracts ICB = International Competitive Bidding; NCB = National Competitive Bidding; QCBS=Quality- and Cost-Based Selection; CQS = Selection Based on Consultants' Qualifications. 2. Prequalification. Bidders for _Not applicable_ [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 July 9, 2010 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Water Sector Capacity Building & Advisory Services Project (WCAP) PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2017-01-30 2019-04-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P110099 GPN Date: Project Name: Water Sector Capacity Building & Advisory Services Project (WCAP) Loan / Credit No: IDA / 57600 Executing Agency(ies): WATER SECTOR CAPACITY BUILDING and ADVISORY SERVICES PROJECT WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5889-CW-RFB / Minor works for Up gradation & Rehabilitation Pending Single Stage - One & for installation of Soil IDA / 57600 Prior Request for Bids Open - National 0.00 Implementati 2017-03-02 2017-03-07 2017-04-18 2017-05-18 2017-06-22 2017-12-19 Envelope Mechanics and Hydraulics on Laboratory Hyderabad (Section-C) PK-WCAP AF-5892-CW-RFQ / Minor Work associated with Installation & Pending Upgradation of Existing Request for Single Stage - One IDA / 57600 Post Open - National 0.00 Implementati 2017-03-06 2017-05-01 2017-10-28 Rooms for Survey/ Computer Quotations Envelope on and Soil Testing Labs Irrigation Department in Balouchistan. PK-WCAP AF-5893-CW-RFQ / Minor Work associated in Pending Request for Single Stage - One Upgradation of Lahore IDA / 57600 Post Open - National 0.00 Implementati 2017-03-06 2017-05-01 2017-10-28 Quotations Envelope Hydraulic Laborite on Gujranwala Punjab. PK-WCAP AF-107097-CW- RFB / Provision of Civil Works for Concrete & Soil Testing Lab Quetta(Balochistan) Soil Pending Open - Single Stage - One Mechanics & Hydraulics IDA / 57600 Post Request for Bids 0.00 Implementati 2019-04-10 2019-04-22 2019-06-06 2019-07-05 2019-08-16 2020-05-12 International Envelope Research Lab, Hyderabad on (Sindh) & Material(Soil, Concrete) Testing Lab, Mardan (Khyber Pakhtunkhwa) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5866-GO-RFQ / Purchase of Lot-I hardwares ( Laptops 10 Desktop 10 ) , softwares ( Pending Windows ,antivirus Internet Request for Single Stage - One IDA / 57600 Post Open - National 0.00 Implementati 2017-01-30 2017-03-27 2017-09-23 Acessories , networking Quotations Envelope on equipment for establishment of Data Center at FFC Islamabad Component = C Page 1 PK-WCAP AF-5868-GO-RFQ / Purchase of LOT-II pheripheral Goods ,Office Equipment (Scanners 2, UPS, Binding Machine, Pending Paper shreders,) etc. Request for Single Stage - One IDA / 57600 Post Open - National 0.00 Implementati 2017-01-30 2017-03-27 2017-09-23 ,Furniture (Colour Printer 2, Quotations Envelope on Laser Printer 10, Mulipurpose Colour Photocopy Machine 2) for establishment of Data Center at FFC Islamabad. PK-WCAP AF-5870-GO-RFQ / PMPIU Office IT equipment ,Installation of Audio Conference, IT Equipment, Accounting Pending Request for Single Stage - One Management Software (1.06 IDA / 57600 Post Open - National 0.00 Implementati 2017-04-08 2017-06-03 2017-11-30 Quotations Envelope million ) and Accessories, on and Installation of Security System and Equipment (Security Camras, Digital Camras, etc) PK-WCAP AF-5872-GO-RFQ / Purchase & Installation of Office Equipment (AC, LED TV, Water Boilers, Room Pending Request for Single Stage - One Heater, White Board, IDA / 57600 Post Open - National 0.00 Implementati 2017-05-10 2017-07-05 2018-01-01 Quotations Envelope Refrigerators, Water on Dispensers, Electric Geysers, Purchase of Office Furniture Sets along with Accessories. PK-WCAP AF-5881-GO-RFQ / Purchase of Heavy Duty Boat for Flow Request for Single Stage - One IDA / 57600 Prior Open - National 31,535.89 Completed 2017-01-30 2017-03-27 2017-09-23 measurement under flood Quotations Envelope Telemetric netwok for H&R Dir. Component-B1 PK-WCAP AF-5883-GO-RFB / CMTL Up-gradtion of Cement, Soil, Steel Sections Open - Single Stage - One IDA / 57600 Post Request for Bids 622,940.34 Completed 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 (Lot wise: total lots 03) and International Envelope CMTL Up-gradtion, Component-B1 PK-WCAP AF-5871-GO-RFQ / Purchase of Field Vehicle (4x4) = 02 RS 10.00 Request for Single Stage - One Million and Purchase of IDA / 57600 Prior Open - National 0.00 Canceled 2017-05-09 2017-06-09 2017-12-06 Quotations Envelope Operational Vehicle 1300 CC (Locally Manufactured) = 06 Rs 12.00 Million PK-WCAP AF-5882-GO-RFQ / Purchase of field Vehicles : 03 Nos. Double Cabin 2499 Request for Single Stage - One CC LOT-I, : 01 No. Jeep, IDA / 57600 Prior Open - National 0.00 Canceled 2017-01-30 2017-03-04 2017-08-31 Quotations Envelope 1299 CC , 01 Nos Car , 1000 CC or Eq. LOT-II for WAPDA PK-WCAP AF-5884-GO-RFQ / Purchase of Office Equipment (Laptop, Desktop Pending Request for Single Stage - One with Printer) Package -A IDA / 57600 Post Open - National 0.00 Implementati 2017-02-12 2017-04-09 2017-10-06 Quotations Envelope Furniture & Fixture on (Package-B) Component = A2 (Activity:) Page 2 PK-WCAP AF-5887-GO-RFQ / Purchase of Office Equipement (Laptop, Desktop Pending Request for Single Stage - One with Printer) Package -A IDA / 57600 Post Open - National 0.00 Implementati 2017-01-30 2017-03-27 2017-09-23 Quotations Envelope Furniture & Fixture on (Package-B) Component = A2 (Activity:) IRSA PK-WCAP AF-36396-GO- RFB / Upgradation of Data Center at FFC Lot-1 ICT Equipment and Office Single Stage - One Equipment , Lot-II IDA / 57600 Post Request for Bids Open - National 0.00 Canceled 2017-11-13 2017-11-18 2017-12-30 2018-01-29 2018-03-05 2018-09-01 Envelope Equipment for Capacity Building (New Activity under Phase- II) PK-WCAP AF-36397-GO- Pending RFB / Establishment of New Single Stage - One IDA / 57600 Post Request for Bids Open - National 0.00 Implementati 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 Hydraulics and Material Envelope on Testing Lab , Peshawar, KP PK-WCAP AF-36415-GO- RFB / Purchase of Open - Single Stage - Two IDA / 57600 Post Request for Bids 0.00 Canceled 2018-02-17 2018-02-22 2018-04-05 2018-06-18 2018-07-23 2019-01-19 Telemetry System Equipment International Envelope for IRSA PK-WCAP AF-36417-GO- Pending RFQ / Purchase of Office Request for Single Stage - One IDA / 57600 Post Open - National 0.00 Implementati 2017-11-20 2018-01-15 2018-07-14 Furniture and Fixtures for Quotations Envelope on IRSA (A2) PK-WCAP AF-36418-GO- Pending RFQ / Purchase of 4x4 Field Request for Single Stage - One IDA / 57600 Prior Open - National 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 Vehicle Component = A2 Quotations Envelope on (IRSA) PK-WCAP AF-36419-GO- RFB / Computer Hardware & Software for H&R Single Stage - One Directorate, Flow Forecasting IDA / 57600 Post Request for Bids Open - National 0.00 Canceled 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Envelope Study of Kabul River, C&M Office and other related offices (Need basis WAPDA) PK-WCAP AF-36420-GO- RFB / Strenthening of Open - Single Stage - One IDA / 57600 Prior Request for Bids 0.00 Canceled 2018-07-23 2018-07-28 2018-09-08 2018-10-08 2018-11-12 2019-05-11 Surface Water Hydrology International Envelope WAPDA (BI) PK-WCAP AF-5879-GO-RFB / Procurement of Supply, Installation and Commissioning of Automatic Open - Single Stage - One IDA / 57600 Prior Request for Bids 0.00 Canceled 2017-12-19 2017-12-28 2018-02-11 2018-03-14 2018-04-03 2018-09-30 Weather Station (AWS) and International Envelope Integration of Meteorological Sensors with existing FFT Network PK-WCAP AF-68531-GO- RFB / Procurement of Supply, Installation and Commissioning of Automatic Open - Single Stage - One IDA / 57600 Prior Request for Bids 1,540,240.29 Signed 2018-07-06 2018-07-16 2018-08-30 2018-09-30 2018-10-30 2019-07-27 Weather Station (AWS) and International Envelope Integration of Meteorological Sensors with existing FFT Network Page 3 PK-WCAP AF-5876-GO-RFB / Procurement for supply and Installation of Hardware, software and Equipment fro Modern Computerized Lab Single Stage - One Equipment for Drawing & IDA / 57600 Post Request for Bids Open - National 0.00 Canceled 2017-02-08 2017-02-13 2017-03-15 2017-03-30 2017-04-09 2017-10-06 Envelope Numerical Modeling at Hydraulic Research Station (HRS) Nandipur Gujranwala (LOT-I) Hydraulics Engineering Instruments/Equipm PK-WCAP AF-5877-GO-RFB / Procurement for Supply and Installation of LOT-I Modern Testing Lab Equipment Basic Field Soil Single Stage - One Testing Equipment (Package- IDA / 57600 Prior Request for Bids Open - National 0.00 Canceled 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Envelope A), Lab Equipment for Modern Computerized Survey Lab Along Survey Training of Rs. 3.2 Million (Package- B) LOT-II Office Equipment PK-WCAP AF-5878-GO-RFB / Procurement for Providing & fixing instruments for up Single Stage - One gradation model testing IDA / 57600 Post Request for Bids Open - National 0.00 Canceled 2017-01-25 2017-01-30 2017-03-13 2017-04-12 2017-05-17 2017-11-13 Envelope area @ Hyderabad Sindh Office / IT Equipment LOT- I, Lab Equipment LOT-II PK-WCAP AF-97490-GO- RFQ / Up-gradation of Data Center at FFC Lot-1 ICT Equipment and Office Pending Request for Single Stage - One Equipment , Lot-II IDA / 57600 Post Open - National 0.00 Implementati 2019-03-10 2019-05-08 2019-09-05 Quotations Envelope Equipment for Capacity on Building (New Activity under Phase- II) PK-WCAP AF-97493-GO- Pending RFB / Purchase of Open - Single Stage - One IDA / 57600 Prior Request for Bids 0.00 Implementati 2019-10-01 2019-10-08 2019-11-19 2019-12-19 2020-01-23 2020-06-21 Telemetry System Equipment International Envelope on for IRSA PK-WCAP AF-97496-GO- RFQ / Computer Hardware & Software for H&R Pending Request for Single Stage - One Directorate, Flow Forecasting IDA / 57600 Post Open - National 0.00 Implementati 2019-03-05 2019-04-30 2019-10-27 Quotations Envelope Study of Kabul River, C&M on Office and other related offices (Need basis WAPDA) PK-WCAP AF-97792-GO- RFB / Purchase of Field Vehicle (4x4) = 02 RS Pending Single Stage - One 10.00 Million and Purchase IDA / 57600 Post Request for Bids Open - National 0.00 Implementati 2019-03-11 2019-03-21 2019-05-02 2019-06-01 2019-07-13 2020-01-09 Envelope of Operational Vehicle 1300 on CC (Locally Manufactured) = 06 Rs 12.00 Million PK-WCAP AF-97850-GO- RFQ / Purchase of field Vehicles : 03 Nos. Double Pending Request for Single Stage - One Cabin 2499 CC LOT-I, : IDA / 57600 Post Open - National 0.00 Implementati 2019-03-28 2019-06-13 2019-12-10 Quotations Envelope 01 No. Jeep, 1299 CC , 01 on Nos Car , 1000 CC or Eq. LOT-II for WAPDA Page 4 PK-WCAP AF-97857-GO- Pending RFB / Strengthening of Open - Single Stage - One IDA / 57600 Post Request for Bids 0.00 Implementati 2019-05-13 2019-05-18 2019-06-29 2019-07-29 2019-09-02 2020-02-29 Surface Water Hydrology International Envelope on WAPDA (BI) PK-WCAP AF-107075-GO- RFB / Purchase of Computer equipment(Desktop,LCDs, Laptop, Printers, scanners, Pending Open - Single Stage - One Projectors, softwares etc), IDA / 57600 Post Request for Bids 0.00 Implementati 2019-04-08 2019-04-15 2019-05-30 2019-06-27 2019-08-01 2019-12-29 International Envelope for Provincial Irrigation on Departments (Balochistan, Khyber Pakhtunkhwa, Punjab & Sindh) PK-WCAP AF-107090-GO- RFB / Purchase of Laboratory/Scientific/Hydrauli Pending c equipment for Provincial Open - Single Stage - One IDA / 57600 Prior Request for Bids 0.00 Implementati 2019-04-08 2019-04-15 2019-05-30 2019-06-27 2019-08-01 2019-12-29 Irrigation Departments International Envelope on (Balochistan, Khyber Pakhtunkhwa, Punjab & Sindh) PK-WCAP AF-107099-GO- RFQ / Purchase/Provision of office equipment for Pending Request for Single Stage - One Provincial Irrigation IDA / 57600 Post Open - National 0.00 Implementati 2019-04-18 2019-05-30 2019-08-13 Quotations Envelope Departments (Balochistan, on Khyber Pakhtunkhwa, Punjab & Sindh) PK-WCAP AF-107100-GO- RFQ / Supply & Installation of furniture & fixture for Pending Request for Single Stage - One Provincial Irrigation IDA / 57600 Post Open - National 0.00 Implementati 2019-04-18 2019-05-30 2019-08-13 Quotations Envelope Departments (Balochistan, on Khyber Pakhtunkhwa, Punjab & Sindh) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-WCAP AF-5837-CS-CQS / Procurement of Consultancy Services for the Assessment /TPV on technoligical Moderinezed Consultant Upgradation of Institutes Pending IDA / 57600 Post Qualification Open - National 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-01-14 (Punjab ,SINDH, Implementation Selection BALUCHISTAN) relevent to their Upgradation in Nandipur Gujranwala in Punjab alongwith technical Upgradation & Strengthe Page 5 PK-WCAP AF-5859-CS- QCBS / Preparation of comprehensive Integrated Master Plan for the Quality And Cost- Open - Pending IDA / 57600 Post 0.00 2017-03-20 2017-03-21 2017-04-15 2017-05-15 2017-05-30 2017-06-12 2017-06-22 2018-06-22 development and utilization Based Selection International Implementation of power and energy resources in Upper Indus Basin. PK-WCAP AF-5862-CS-CQS / Discharge measurement at key locations of the Indus Consultant Basin Irrigation System Open - Pending IDA / 57600 Post Qualification 0.00 2017-02-08 2017-02-22 2017-04-11 2017-04-26 2017-05-06 2017-11-02 (IBIS) to develop International Implementation Selection standardized water flow measurement system of the IBIS (Phase-II) PK-WCAP AF-5833-CS- QCBS / Preparation of Comprehensive Inventory of Quality And Cost- Open - IDA / 57600 Prior 0.00 Canceled 2017-03-01 2017-03-15 2017-04-09 2017-05-09 2017-05-24 2017-06-08 2017-06-16 2018-06-16 Water Resources of Pakistan Based Selection International and Updating the Indus Drainage Basin Atlas PK-WCAP AF-5840-CS- QCBS / "Up-gradation of master plan of flood management of hill torrents of Pakistan and Feasibility Quality And Cost- Open - IDA / 57600 Prior 0.00 Canceled 2017-03-15 2017-03-29 2017-04-18 2017-05-18 2017-06-02 2017-06-17 2017-06-25 2018-06-25 studies for check/recharge Based Selection International dams in Sulaiman Range, and Feasibility study of Marri Bugti Hill Torrent " PK-WCAP AF-5863-CS-CQS / "Determination of Losses & Gains obetween Several Consultant Pending reaches in Indus & Jhelum IDA / 57600 Post Qualification Open - National 0.00 2017-02-08 2017-02-22 2017-04-08 2017-04-23 2017-05-08 2017-11-04 Implementation Chenab zones (Phase-II) Selection " PK-WCAP AF-36399-CS- Consultant CQS / Preparation of Open - Pending IDA / 57600 Post Qualification 0.00 2018-06-30 2018-07-21 2018-09-03 2018-10-03 2018-11-07 2019-05-06 Implementation Framework International Implementation Selection for National Water Policy PK-WCAP AF-5861-CS- QCBS / "Automation of Flow Measurement and Information System for the Quality And Cost- Open - IDA / 57600 Post 0.00 Canceled 2018-02-26 2018-03-12 2018-04-06 2018-05-06 2018-05-21 2018-06-07 2018-07-02 2020-12-30 Indus Basin Irrigation Based Selection International System (IBIS) using Telemetry System and Modern Techniques" PK-WCAP AF-62516-CS- QCBS / Indus Basin Irrigation System: Hydraulic Quality And Cost- Open - Under IDA / 57600 Prior 0.00 2018-05-31 2018-06-14 2018-07-09 2018-08-08 2018-08-23 2018-09-09 2018-10-04 2021-04-03 Calibration of 17 Key Sites Based Selection International Implementation and Automation of Discharge Monitoring at All Sites PK-WCAP AF-5864-CS- QCBS / Procurement of Consultancy Services for Quality And Cost- Open - Flow Forecasting of Kabul IDA / 57600 Post 743,046.17 Signed 2017-02-08 2017-02-22 2017-03-14 2017-04-13 2017-04-28 2017-05-18 2017-05-28 2018-05-28 Based Selection International River Basins using RS/GIS Technique and related hydrological Models Page 6 PK-WCAP AF-97853-CS- QCBS / Up-gradation of master plan of flood management of hill torrents of Pakistan and Feasibility Quality And Cost- Open - Pending IDA / 57600 Post 0.00 2019-03-11 2019-04-16 2019-05-08 2019-06-07 2019-06-22 2019-07-16 2019-08-09 2020-08-08 studies for check/recharge Based Selection International Implementation dams in Sulaiman Range, and Feasibility study of Marri Bugti Hill Torrent " INDIVIDUAL CONSULTANTS Page 7