The Block CI-27 Gas Field Expansion Project for Cote d'Ivoire had a satisfactory outcome. The project delivered on its expected outcome in maintaining the availability of clean natural gas for lower-cost power generation. However, the project was completed with a small cost overrun of 6.7 percent. There were no changes to the project development objectives (PDO), outcome targets or PDO indicators during implementation. There were also no revisions...