The development objective of the First Phase of the Dasu Hydropower Project for Pakistan is to facilitate the expansion of electricity supply of hydro-power in Pakistan. Some of the negative impacts and mitigation measures include: (1) Pakistani rupee (PKR) 1,120,000 for each tower as compensation for the land taken for each tower. The amount may vary from on one tower to another due to location and a variety of other factors; (2) cash compensation...
See More
DETAILS
-
2023/01/01
-
Resettlement Plan
-
SFG5872
-
1
-
2024/03/01
-
Disclosed
-
Updated Resettlement Action Plan for 765KV Manshera Grid Station
Citation
World Bank.
Pakistan - First Phase of the Dasu Hydropower Project : Resettlement Plan (Vol. 1 of 4) : Updated Resettlement Action Plan for 765KV Manshera Grid Station (English). Pakistan : Borrowing Agency. http://documents.worldbank.org/curated/en/099210203112414869