This report analyzes why the existing Implementation Plan (IP) of the Urban Waste Water Treatment Directive (UWWTD) did not allow Romania to comply with its obligation, and proposes a new approach to accelerate implementation. The report with an updated implementation plan of UWWTD, including prioritization of measures and new timeline for compliance of the agglomerations above 2,000 p.e., represents the Output No 4 as specified in the above-mentioned...
Voir la suite
INFORMATION
-
2020/09/30
-
Rapport
-
169043
-
1
-
2022/03/01
-
Disclosed
-
RAS on Technical Support to Romania in Analyzing and Addressing the Challenges in Meeting the UWWTD Requirements : Output No.4 - Towards a New UWWTD Implementation Acceleration Plan