Ratings for the Environmental Pollution Abatement Project for Lebanon were as follows: outcomes were moderately satisfactory, bank performance was moderately satisfactory, and monitoring and evaluation quality was substantial. Some lessons learned included: TA was grant-funded in line with the GOL’s preference, yet the modality led to unexpected delays in financing and required stop-gap measures from the UNDP and the MOE to keep the PMU running. Similar...
Voir la suite
INFORMATION
-
2023/10/11
-
Bilan de fin d’exécution et de résultats
-
ICR6197
-
1
-
2023/10/12
-
Disclosed
-
Lebanon - Environmental Pollution Abatement Project