The Modernization of Irrigated Agriculture in the Oum Er Rbia Basin of the Middle East and North Africa had a moderately satisfactory outcome, moderately satisfactory performance by the Bank and the monitoring and evaluation quality was substantial. The lessons learned were: (1) Careful selection of irrigation sectors to modernize. (2) Long duration of works typical of modernization in large scale irrigation calls for long implementation period. (3)...