Ratings for the Geothermal Power Generation Project for Djibouti were as follows: outcome was moderately unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: availability of pre-assessment of sufficiently accurate geothermal resource data can be a determining factor in project design. A pre-feasibility study carried out by a reputable geothermal...
Voir la suite
INFORMATION
-
2021/03/31
-
Bilan de fin d’exécution et de résultats
-
ICR5401
-
1
-
1
-
2021/04/12
-
Disclosed
-
Djibouti - Geothermal Power Generation Project
-
global environment facility trust fund