The development objectives of the Pap-Angren Railway Project are to reduce transport costs and to increase transport capacity and reliability through the construction of a rail link between the Uzbek part of the Ferghana Valley and the rest of Uzbekistan. Despite that PDO is likely to be achieved due to completion of key activities, implementation progress has been facing major challenges since July 2018. Given the persistent delays in key procurement...
Voir la suite
INFORMATION
-
2019/02/03
-
Document de projet
-
RES35123
-
1
-
1
-
2019/02/03
-
Disclosed
-
Disclosable Restructuring Paper - Pap-Angren Railway - P146328
-
economic and financial analysis