Ratings for the Coffee Sector Competitiveness Project for Burundi were as follows: outcome was unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality (M and E) was modest. Some lessons learned included: in a fragility, conflict, and violence (FCV) context where the political environment can be uncertain and government policies can change abruptly, such as in the case in Burundi, it is necessary to have...
Voir la suite
INFORMATION
-
2022/03/30
-
Bilan de fin d’exécution et de résultats
-
ICR4849
-
1
-
1
-
2022/04/14
-
Disclosed
-
Burundi - Coffee Sector Competitiveness Project
-
STEP Systematic Tracking of Exchanges in Procurement