Jordan - Northeast Ghor Irrigation and Rural Development Project (anglais)

Project works include: (i) 2 diversion weirs and siltation reservoirs; (ii) 55 km of pipeline and a distribution network to serve, by sprinkler irrigation, a total of 2,760 ha net; 30 km of farm roads; (iii) land leveling of about 3,000 ha and title drainage of about 520 ha; (iv) rehabilitation works on the existing East Ghor Canal; 2 assembly markets and packing and grading stations; (v) treated water supply system for construction of about...