Ratings of Second Infrastructure and Local Development Project for Gabon were as follows: outcome was moderately satisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include: (i) Proper baseline studies, in-depth assessments of client implementation capacity and updated urbanization data could have helped make the project design more robust and realistic; (ii) Readiness...