Skip to Main Navigation

India - Coal-Fired Generation Rehabilitation Project (anglais)

Ratings for the Coal-Fired Generation Rehabilitation Project for India were as follows: outcome was moderately unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: comprehensive rehabilitation of plant after 25 to 30 years of plant life takes lot of time in recommissioning of plant. Existing sites of plant should not be given up in favor of totally...