Albania - Critical Imports Project (anglais)

Ratings for the First Critical Imports Project for Albania were as follows: outcome was satisfactory, sustainability was uncertain, institutional development was modest, Borrower performance was highly satisfactory, and Bank performance was highly satisfactory. Some lessons learned included: for all types of emergency operations designed to address key social needs and or production bottlenecks, projects require a maximum degree of funding flexibility...