Africa - Tanzania-Zambia Transmission Interconnector Project : environmental assessment (Vol. 4 of 4) : Updated environmental and social impact assessment study for the 340km Mbeya-Tunduma–Sumbawanga 400kV transmission line and 4km Tunduma substation to Tanzania-Zambia Border 330kV transmission line (anglais)

The development objective of the Tanzania-Zambia Transmission Interconnector Project for Africa is to establish cross-border transmission capacity between the Southern African Power Pool and the Eastern Africa Power Pool to enable regional power trade. Some of the negative impacts and mitigation measures are includes : (i) prepare and implement erosion and sediment control plans,particularly in areas identified as having high erosion potential; (ii)...