Ratings for the Huai River Basin Flood Management and Drainage Improvement Project for China were as follows: outcomes were satisfactory, risk to development outcome was moderate, Bank performance was satisfactory, and Borrower performance was satisfactory. Some lessons learned included: starting capacity building during preparation contributes to the success of projects. Community participation in the design of subprojects is crucial to maximize...
Voir la suite
INFORMATION
-
2017/06/20
-
Bilan de fin d’exécution et de résultats
-
ICR4036
-
1
-
1
-
2017/06/30
-
Disclosed
-
China - Huai River Basin Flood Management and Drainage Improvement Project
-
Urban and Rural Development